TO STUDY THE PROBLEM IN CC#13,14,15
By
T.PYDI REDDY
JUNIOUR OFFICER (103278)
CENTRAL MAINTENANCE MECHNICAL
charging
conveyors of blast
furnace
Total length of belt replaced during the period 2012-
13 was 36359 meter and 38091 meter during 2011-12
Conveyor belt replacement due to Through Cut was
12857 meter during 2012-13 & 10482 meter during
2011-12.
Conveyor belt replacement due to Wear Out was
17398 meter during 2012-13 and 24823 meter during
2011-12
Conveyor belt replacement due to Belt burnt was
1220 meter during 2012-13 and 1578 meter during
2011-12
Conveyor belt replacement
Conveyor belt shortening
Pulley bearing changing
Pulley lagging
Pulley replacement
Idlers replacement
Mechanical maint. of drive mechanism and other
accessories
Structural repairs
Mechanical fasteners
Vulcanizing
- Cold vulcanizing
- Hot vulcanizing
Off-Centering of belt
Belt Snap
Longitudinal cuts
Failure of pulleys
Failure of lagging
Failure of couplings
Failure of Hold back
Failure of internals of gear box
Winding of belt on pulleys
Belt elongation
Belt Slippage
Client jamming
Pocket formation
Ply Separation etc
Transferring of material from Coal tipplers to
Stockyard. Conveys all materials like Boiler coal
and Coaking coal etc. Any stoppage of conveyors
lead to tippling delay causing huge demurrage
charges
Joint failures & Through Cuts (Longitudinal,
Width Wise)
1. Installation of belt scales.
2 Interlocking of belt scale adjustment to the GPL 1&2.
3. Narrowing of skirt board & GPL feed point.
4. Installation and deflection plates at GPL point.
5. Installation of high trough angle 30 deg at feed point.
6. Reviewing of counter weight and take up sheave pulley.
7. Better replacing existing sheave pulley with anti frictional
ball bearing mounted sheave pulley.
8. Increase the diameter of the drive pulley from 500mm to
630 mm
Idlers Jamming due to poor house keeping
No lagging to the drums except drive tail pulley.
TIS (Tramp Iron Separator) not working properly feeding Chute
Skirt board liver not in proper position.
Zero speed meter sensor is not available after the feeding Chute.
Counter weight ropes holding pulley jamming
Take up trolley not in fee movement on rails due to material
pillager.
Huge jamming drive snap pulley
More belt pieces are invested for immediate belt running purpose;
it will cause more joint failures.
Improper inspection of Idlers and Bad Joints.
Clear the Idlers Jamming and maintain good house keeping
Proper lagging to the all drums
Good Maintenance of TIS (Tramp Iron Separator)
Put Skirt board liners properly to feeding chute
Arrange zero speed meter sensor
Clear spillage material on counter weight hold pulleys
Maintain take-up trolley in free movement
Frequently maintain of the drive snub pulley.
At the time of belt repair, Inserted long length pieces to reduce
the no. of joints.
Periodical inspection of Idlers and Bad joints
Maintenance of good house keeping to surrounding
area is very neat and clean.
Reduce conveyor and mechanical Break downs.
Machine availability is Improve more.
Utilization of less man power.
Transport to more material through this CC# 13, 14,
15 conveyors.
Follow good safety conditions.
No accidents less break downs.
Spare parts, cost very less for competitive production
cost..
Spillage cleaning is the main cost factor in running of these
conveyors. The cost incurred for cleaning of conveyor can be
saved by taking preventive measures such as avoiding spillage,
running belt in centre etc.
Savings by avoiding spillage in these conveyors:
No. of workers engaged for daily Cleaning: 4
Labour component for each worker : Rs 330/-
Labour component per day: Rs.330*4 = Rs1320
Labour component per year= Rs 1320*365 = Rs 4.81 lakhs
=Rs 4.81 lakhs perannum
CONCLUSION