CE Board And CE license Reshuffling

Proposal
Content
• Introduction
• Thresholds and Methodology
• Requirement
Introduction
Introduction

CE resources are baseband processing resources in a NodeB. The more CEs a NodeB supports, the
stronger the NodeB's service processing capability.
If the uplink/downlink license- or hardware-based CE usage is consistently greater than 70% during peak
hours for three consecutive days in a week
CE capacity expansion Should be Done as follows:
  If the license-based CE usage exceeds its capacity expansion threshold, CE resources are limited by the
license. In this situation, upgrade the license file.
  If the hardware-based CE usage exceeds the capacity expansion threshold, CE resources are limited by
the hardware capacity. In this situation, add UBBP or WBBP boards.

4
CE Expansion Thresholds and
Methodology
CE Expansion Thresholds
Donor site Receiver site

KPI/ counters Threshold KPI/ counters Threshold


UL CE Utilization <40% UL CE Utilization >70%
DL CE Utilization <40% DL CE Utilization >70%
ULCE Rejection <100 ULCE Rejection >500
ULCE Rejection <100 ULCE Rejection >500

 export 30 days data per hour from PRS or U31. Microsoft Excel
Worksheet
 pivot the data
 take Average
 calculate average of large of 7 Days.
 Manipulate the data according to the attached formula on the excel sheet. Microsoft Excel
Worksheet

6
CE reshuffling Methodology :
According to the proposal, if the license-based CE usage exceeds its capacity expansion threshold and if CE resources
are limited by the license or if HW Board Capacity is available. In this situation, Add Soft CE license.
In order to add required Soft CE license make sure sufficient CE license on the pool on the RNC.
If there is no sufficient CE license on the pool, reshuffle CE license based on CE Utilization And CE rejection.
Receiver site
 High CE utilization And High CE Rejection .
 CE Utilization >70% which shows high CE utilization.
Donor site
 Low CE utilization and low CE Rejection.
 CE utilization <40% which shows no low CE Utilization.

7
CE board reshuffling Methodology :
If the hardware-based CE usage exceeds the capacity expansion threshold, CE resources are limited by the hardware
capacity. In this situation, add CE board.
Donor and receiver sites selection is based on CE resource utilization and Rejection.
Receiver site
 High CE utilization And High CE Rejection
 If the current CE board is fully configured.
 CE Utilization >70% which shows high CE utilization.
Donor site
 Low CE utilization and low CE Rejection.
 CE utilization <40% which shows no low CE Utilization.
 Should have more than 2 CE Boards.
 Carrier configuration of the Donor should be checked, if the carrier configuration is U333 or more the
remaining CE board should support 12 cells or the remaining Board Should be 2 if the boards are
supporting 6 number of cells.
 Donor and receiver should be located on the same region.

8
Requirement
Requirement
Configured license requirement and Hard ware Capacity requirement
Huawei ZTE
counters Names Counter Description counters Names Counter Description
# of BPK Board DL hardware capacity
VS.HW.DLCreditAvailable DL hardware capacity
# of BPK Board UL hardware capacity
VS.HW.ULCreditAvailable UL hardware capacity Maximum available CE for NodeB currently configured DL CE
Downlink license
VS.LC.DLCreditAvailable.Shared currently configured DL CE license
currently configured UL CE
VS.LC.ULCreditAvailable.Shared currently configured UL CE license Maximum available CE for NodeB Uplink license

In order to get configured CE license and CE board capacity information, extract data from
 PRS And U2020 from Huawei Side. Microsoft Excel
Comma Separated Values Fi
U31 from ZTE Side.

Microsoft Excel
Comma Separated Values Fi

10
Hard ware capacity
Board types and board capacity.
capacity
Vendor board types Numberof Cells Number of UplinkCEs Number of Downlink CEs
WBBPf1 6 192 384
WBBPf5 6 384 512
WBBPd1 6 192 192
Huawei WBBPf3 6 384 512
UBBPd1 6 384 512
UBBPd4 6 512 768
UBBPe4 12 1024 1024
BPK_d 12 768 768
ZTE BPK_e 6 384 384
BPK_e1 6 192 192

In order to get configured CE license and CE board capacity information


To export CE license configuration from U2020
U2020 License NodeB license Export
In order To export board capacity And Board type from U2020
U2020 configuration inventory management BTS3900 export

11
RAN Optimization Section 08/31/21
Cont.…

 In order To export board capacity And Board type from U31(ZTE)


U31 configuration Common wireless configuration application inventory management
Spare part management online hardware inventory query export

 To export CE license configuration from U31(ZTE)


U31 Performance History performance Query or Query templet management

12
RAN Optimization Section 08/31/21