PMAY PROJECT VERTICAL-III, DEOGHAR

EUROFORM –– AA Versatile
EUROFORM Versatile Aluminum
Aluminum with
with Laminated
Laminated Ply
Ply
Formwork Construction
Formwork Construction Technique”
Technique”
WHEN IT IS SUITABLE ..?
Mass Housing, No. of Repetitions Are More, Typical Floors, Fast Construction Required, High
Quality, Column Less Structure, Highly Suitable To Load Bearing Structure (Shear wall)
Q U A L I T Y A D VA N TA G E O F E U R O FO R M
The EUROFORM formwork is specifically designed to allow rapid construction of all types of
architectural layouts.
1)      Total system forms the complete concrete structure.
2)      Custom designed to suit project requirements.
3)      Unsurpassed construction speed.
4)      High quality finish.
5)      Cost effective.
6)      Panels can be reused up to 250 times.
7)      Erected using unskilled labor.
S P E E D OF C O NS T RU C T IO N – W O RK CY C L E

1)       Deshuttering of the panels – 12 to 15 hrs


2)       Positioning brackets & platforms on the level- 10 to 15 hrs
3)       Deshuttered panels lifted & fixed on floor-7 to 10 hrs
4)       Kicker & external shutters fixed in -7 hrs
5)       Shutters are erected in 6-8 hrs Reinforcement – 10 to 12 hrs
6)       Electrical fittings -10 hrs
7) Pouring concrete