Professional Documents
Culture Documents
3
Distance Relay Applications
Sample Distance Relay Characteristic (Zone 2)
X
Z RELAY
1.25 Z LINE
Z LINE
Z RELAY 30
0
30
MTA R
LINE
4
Zone 3 – Remote Backup Applications
Normal Zone 2
Zone 2
Time Zone 2
Zone 1 Zone 1
5
Other Remote Backup Methods
● Direct Transfer Trip
Allow relays to be set shorter
Uses communications systems for remote
backup
● Alternative Relay Characteristics
Blinder Characteristics
Lenticular Characteristics
Proprietary Load-Tolerant Characteristics (ex.
– Schweitzer Electric Labs Load
Encroachment Characteristic)
6
Remote Backup – Direct Transfer Trip
● Requires additional communication
equipment
● Must Be Redundant – Communication
equipment more prone to fail than
relaying, breakers, or other equipment
● Requires correct operation of protective
relays on primary protected element
● Can not back up for failure of DC battery
systems, or for failure of instrument
transformers
7
Remote Backup –Blinder Characteristics
● Separate, supervising
element
● Allows full relay reach for
fault angles 300 LOAD ANGLE
retrofit
8
Remote Backup – Lenticular Characteristics
11
NERC Recommendation 8a
● All transmission owners shall, no later than September 30, 2004,
evaluate the zone 3 relay settings on all transmission lines
operating at 230 kV and above for the purpose of verifying that
each zone 3 relay is not set to trip on load under extreme
emergency conditions. In each case that a zone 3 relay is set so as
to trip on load under extreme conditions, the transmission operator
shall reset, upgrade, replace, or otherwise mitigate the overreach of
those relays as soon as possible and on a priority basis, but no
later than December 31, 2005. Upon completing analysis of its
application of zone 3 relays, each transmission owner may no later
than December 31, 2004 submit justification to NERC for applying
zone 3 relays outside of these recommended parameters. The
Planning Committee shall review such exceptions to ensure they
do not increase the risk of widening a cascading failure of the
power system.
The NERC investigation team recommends that the zone 3 relay, if
used, should not operate at or below 150% of the emergency ampere
rating of a line, assuming a .85 per unit voltage and a line phase angle
of 30 degrees.
12
Joint Task Force Recommendation 21a
NERC
● Industry is to review zone 3 relays on lines
of 230 kV and higher.
12/31/2004 12/31/2005
TPSOs Submit to Regions: TPSOs Submit to Regions:
- Certification of conformance to loadability - Certification of full conformance
- Violation mitigation (before 12/31/05) plans - Implementation dates for outstanding violations
- Applications for exceptions
9/30/2004
TPSOs report to Regions
on Zone 3 reviews
9/30/2004 -
2/10/2004 - 9/30/2004 12/31/2004 1/1/2005 - 12/31/2005
TPSOs review Zone 3 relays TPSOs mitigate TPSOs mitigate
for conformance violations violations
16
SPCTF Recommendations (Continued)
● Regions to assure that all TPSOs have responded
and respond to NERC 1 month later
● Establish Two Classes of Exception – Temporary
and Technical
● Temporary Exceptions to Request Delayed
Schedule for Workforce or Construction Clearance
Issues
● Technical Exceptions to Address Conditions Where
Thermal Limits Are Not the Practical Limiting
Condition
● SPCTF Developing Technical Exception Criteria
● SPCTF to Review All Exception Requests and
17
Report to PC
SPCTF Recommendations (Continued)
● Denied Requests Must Be Mitigated in 1 Year
● All Other Load-responsive Relays to Be Reviewed
and Addressed on a Schedule to Be Developed by
SPCTF
● Exceptions to Be Reviewed by Regions
● Regions to Identify Critical Lines 115kv and Above
for Inclusion in Review (Joint TF Recommendation
21a)
18
SPCTF Exception Criteria
● Temporary exceptions
● Technical exceptions
Realistic circuit ratings
Achieve minimum acceptable protection
Network topology
● Transmission system must be adequately protected,
and distance relaying must also allow for maximum
practical load flow
● Distance relaying must not contribute to cascading
outages
19
Temporary Exceptions
● Permit delayed implementation because of
workforce issues, construction outage constraints,
or availability of replacement equipment
● Not intended to provide for budget relief
● TPSOs must do all possible to mitigate with existing
equipment
20
Ratings and Technical Exceptions
22
Technical Exception #1
23
Technical Exceptions #2, 3, and 4
The protective relays need to accommodate
the power transfer capability of a
transmission line
2. Line only
Recertify when line is changed
3. Line and breaker interrupter rating
Recertify when breaker is underrated or
changed
4. Line and actual source impedance
Recertify annually
24
Maximum Power Transfer Diagram
Sending Receiving
XS = 0 XL XR = 0
VS VR ER = 1.0 PU
R
ES = 1.0 PU
VS VR sin
P
XL
The maximum real power that a transmission
line can transfer occurs when the voltage
angle across the line reaches 90º.
25
Maximum Power Transfer Capability
26
Technical Exception #2, 3 and 4
● Exception 2
Uses the line reactance only
1.0 per-unit source voltage at both ends
No additional margin
● Exception 3
Uses the line reactance, plus source reactance at each end
reflecting the breaker interrupting ratings
1.05 per-unit source voltage at both ends
No additional margin
● Exception 4
Uses the line reactance, plus actual system source reactances at
both ends
1.05 per-unit source voltage at both ends
No additional margin
27
Technical Exception #5
Special Considerations for Series-
Compensated Lines
Tripping relay should not operate at or
below the greater of:
1. 1.15 times the highest emergency rating
of the series capacitor
2. Itotal (calculated under Exception 2, 3, or
4 using full line inductive reactance)
Assuming
0.85 per unit voltage
28
line phase angle of 30º
Technical Exception #6
Weak Source Systems
● The tripping relay should not operate at or below
1.414 times 1.15 times Ifault assuming a 0.85 per
unit voltage and a line phase angle of 30
degrees where Ifault is the maximum end of line
three-phase fault current magnitude
FAULT
OPEN
TRANSMISSION SYSTEM
LOAD CENTER
R
29
Technical Exceptions #7 and 8
● Distance relays must be
able to adequately
protect line
X
● Exception 7 applies to Z RELAY
simple 2-terminal lines
1.25 Z APPARENT
● Exception 8 applies to 3
(or more) terminal lines Z APPARENT
● Establishes an
emergency rating based
on relay loadability
● Must be recognized by 30 0
Z RELAY 30
reliability coordinator
MTA R
● RC must take action
APPARENT
when load reaches this
30
rating
Technical Exception #7 and #8
Requires That All of Following Conditions Are Met:
● Most Sensitive Tripping Element Set for 125% of
Apparent Impedance
● MTA Set As Close as Possible to 90 degrees
● Calculate a Short-Term Rating Iemergency Based on
Relay Setting
● Iemergency Used in All Planning and Operational
Modeling for the STE Rating
● No current or Subsequent Planning Contingency
Analyses Identify Conditions where Recoverable
Flow is > Iemergency
Otherwise, must fully mitigate the conditions
31
Technical Exception #9
Generation Remote to Load
For one line connecting the aggregate generation to the
system:
● The tripping relay should not operate for 1.15 times the
Imax assuming a 0.85 per unit voltage and a line phase
angle of 30 degrees
For multiple lines connecting the aggregate generation to
the system:
● The tripping relay should not operate for 1.15 times Imax
assuming a 0.85 per unit voltage and a line phase angle
of 30 degrees if all the other lines that connect the
generator to the system are out of service
● Imax is defined as: MVA
I max max
32 3 Vrelay
Exception 9 – Generator Connected by Single Line
LOAD BUS
GENERATION BUS
33
Exception 9 – Generator Connected via Multiple Lines
GENERATION CENTER
LOAD BUS A
LOAD CENTER
R
LOAD BUS B
OPEN
R
LOAD BUS C
OPEN
34
Technical Exception #10
Load Remote to Generation
The tripping relay should not operate for 1.15 times the
maximum current flow as calculated by the TPSO
assuming a 0.85 per unit voltage and a line phase
angle of 30 degrees.
GENERATION CENTER
LOAD BUS A
LOAD CENTER
R
LOAD BUS B
R
LOAD BUS C
R
35
Technical Exception #11
Remote Cohesive Load Center
The tripping relay should not operate for 1.15 times the
maximum current flow as calculated by the
transmission owner assuming a 0.85 per unit voltage
and a line phase angle of 30 degrees.
TRANSMISSION SYSTEM
LOAD CENTER
R
R
36
Technical Exception #12
Cohesive Load Center Remote to Transmission
System
The Tripping relay should not operate for 1.15 times the
maximum current flow as calculated by the TPSO
assuming a 0.85 per unit voltage and a line phase angle
of 30 degrees.
TRANSMISSION SYSTEM
LOAD CENTER
R
R
37
Some Possible Mitigation Methods
● Must adequately protect system
● Increase distance relay maximum torque
angle
● Utilize load-tolerant relay characteristics
(blinders, lens characteristics, SEL load
encroachment, etc)
● Utilize transfer trip for remote backup
● Transmission system modifications to
facilitate protection
● Others?
38
SPCTF – Next Distance Relay Activities
40
Questions?
● Charles Rogers (Consumers Energy) – Chairman,
SPCTF
● Bob Cummings (NERC) – Director – Reliability
Assessments and Support Services
41