Professional Documents
Culture Documents
2
Standard Costing and Variance Analysis
10-2
Standard Costs
Standards are benchmarks or “norms” for
measuring performance. In managerial accounting,
two types of standards are commonly used.
Standard Costs
Deviations from standards that considered significant
are brought to the attention of management, a
practice known as management by exception.
Standard
Amount
Direct
Material
Direct Manufacturing
Labor Overhead
Variance Analysis
Variance Analysis
+ Unfavorable - Favorable
10-8
Learning Objective 1
Answer
Standard Quantity Actual Quantity Actual Quantity
× × ×
Standard Price Standard Price Actual Price
200 kgs. 210 kgs. 210 kgs.
× × ×
$5.00 per kg. $5.00 per kg. $4.90 per kg.
= $1,000 = $1,050 = $1,029
Answer
Standard Quantity Actual Quantity Actual Quantity
× × ×
Standard Price Standard Price Actual Price
200 kgs. 210 kgs. 210 kgs.
0.1 kg per Jacket 2,000
× × ×
Jackets = 200 kgs
$5.00 per kg. $5.00 per kg. $4.90 per kg.
= $1,000 = $1,050 = $1,029
Answer
Standard Quantity Actual Quantity Actual Quantity
× × ×
Standard Price Standard Price Actual Price
200 kgs. 210 kgs. 210 kgs.
× × 210 kgs
$1,029 ×
$5.00 per kg. $5.00 per kg.
= $4.90 per kg $4.90 per kg.
= $1,000 = $1,050 = $1,029
Materials Variances:
Using the Factored Equations
Materials quantity variance
MQV = (AQ × SP) – (SQ × SP)
= SP(AQ – SQ)
= $5.00/kg (210 kgs – (0.1 kg/Jacket 2,000 Jackets))
= $5.00/kg (210 kgs – 200 kgs)
= $5.00/kg ×10 kgs = $50 U
Answer Unit
Answer Unit
Recall that the standard quantity for 1,000 Units
is 1,000 × 1.5 Kgs per Unit = 1,500 Kgs.
Standard Quantity Actual Quantity Actual Quantity
× × ×
Standard Price Standard Price Actual Price
Learning Objective 2
Answer
Standard Hours Actual Hours Actual Hours
× × ×
Standard Rate Standard Rate Actual Rate
2,400 hours 2,500 hours 2,500 hours
× × ×
$10.00 per hour $10.00 per hour $10.50 per hour
= $24,000 = $25,000 = $26,250
Answer
Standard Hours Actual Hours Actual Hours
× × ×
Standard Rate Standard Rate Actual Rate
2,400 hours 2,500 hours 2,500 hours
× × Jacket 2,000
1.2 hours per ×
$10.00 per hour Jacketsper
$10.00 = 2,400
hour hours$10.50 per hour
= $24,000 = $25,000 = $26,250
Answer
Standard Hours Actual Hours Actual Hours
× × ×
Standard Rate Standard Rate Actual Rate
2,400 hours 2,500 hours 2,500 hours
× × hours
$26,250 2,500 ×
$10.00 per hour = $10.50
$10.00per
perhour
hour $10.50 per hour
= $24,000 = $25,000 = $26,250
Quality of production
supervision.
Quality of training
provided to employees.
Production Manager
10-30
Answer Unit
Larger variances, in
How do I know dollar amount or as
which variances to a percentage of the
investigate? standard, are
investigated first.
10-34
Exercise:
Orange Company manufactures chairs. The following unitary standards have
been set by the production- engineering staff and the controller:
Direct Material: Direct Labor:
Quantity : 3 M2 Quantity, 0.2 hour
Price, $4 per M2 Price, $8 per hour
Actual costs incurred in the production of 10,000 chairs were as follows:
Direct Material: $94,500 for 27,000 M2
Direct Labor: $15,400 for 2,200 hours
Requirements
1.Calculate the direct material and direct labor variances, indicate whether each
variance is Favorable (F) or Unfavorable (U).
2.What are the possible reasons behind each variance (you should mention at
least 2 reasons for each variance?
3.Should only unfavorable variances be investigated? Explain
10-35
Answer
Direct Materials Variances
SQ 3× 10,000 AQ 27,000 AQ 27,000
× × × × × ×
SP 4 SP 4 AP 3.5 94500/27000
120,000 108,000 94,500
Quantity variance 2 -1 Price variance 3 – 2
108,000 – 120,000 94,500 – 108,000
(12,000) (13,500)
F F
Reasons There are many possible There are many possible
reasons. Among the most reasons. Among the most
likely are: likely are:
A change in The price of the materials
manufacturing process fell
resulted in lower material
wastage than expected.
10-36
Answer
Direct Materials Variances
Favorable Quantity variance Favorable Price variance
Reasons A change in manufacturing The price of the materials fell
process resulted in lower Errors in estimating the price
material wastage than expected. of materials when the budgets
Higher quality workers caused were set
a lower than expected level of A reduced price was charged
wastage of materials during by the supplier because the
production. amount purchased increased
Lower than expected pilferage A different supplier was found
of raw material stocks. who charged a lower price for
Errors in calculating the usage the same or better quality of
rate when the budgets were set. material
Higher quality materials than The supplier charged a lower
anticipated from the supplier. price for a poorer quality of
Higher quality materials as a material
result of buying more A different supplier was found
expensive materials than who charged a lower price for
anticipated. a poorer quality of material.
10-37
Answer
Direct Labor Variances
Answer
Direct Labor Variances
Answer
3- Both unfavorable and favorable variances should be investigated. A
favorable expense variance for example could indicate costs are being cut that
might impact future operations.
Types of Errors
Errors can be classified into those that do and those that do not affect the trial
balance. Errors that do not affect the trial balance means that it still balances. Errors
that affect the trial balance result in a discrepancy that prevents it balancing.
Errors not affecting the trial balance:
1.Errors of omission (double-entry error)
2.Errors of principle
3.Errors of commission
4.Compensating errors
5.Complete reversal of entries
6.Errors of original entry.