Gantt Chart
3
Completed In Progress Incomplete
0 2 4 6 8 10 12 14 16 02
Planning
Feasibility Analysis
Resource Management
Requirement Analysis
Skill Development
Pseudocode
Coding
Debugging
Launch
Currently here
03
5
ID Task Predecessor Duration(Weeks) 04
1 Planning None 1
2 Feasibility 1 1
Analysis
3 Resource 2 1
Management
4 Requirement 2 2
Analysis
5 Skill Development 3 5
6 Pseudocode 2,4 2
7 Coding 5,6 4
8 Debugging 7 2
9 Launch 8 1
05
Pert Diagram
7
Pert Diagram 06
Critical Path 07