RECONNAISSANCE
WALK OVER SITE
GOOGLE EARTH
Establish survey stations (line of sight between stations)
Main survey station : A survey station is a prominent point on the chain line and
can be either at the beginning of chain line or at the end. Eg.: A, B, C, D, E
Main Survey lines or Primary control lines : The line joining the main
survey stations are called main survey lines. Eg.: AB, BC, CD, DE,
EA. Used to gather information around perimeter of site
Base line : The longest main survey line is called base line. It is a longest line
passing through the center of the area. Eg.: AC
Check line or proof lines : are the lines which are run in the field to check the
accuracy of the work. Eg.: BD, BE
DIAGONAL CHECK LINES: AC, BD, BE, CE
USED TO TRIANGULATE CHAIN LINES
WELL-CONDITIONED TRIANGLES( Well
proportioned / Well shaped )
Tie lines : These lines selected to closer to the details, which are otherwise away
from the main survey lines to avoid longoffset.
Tie station or subsidiary station Eg.: E, F.
ONCE THE FRAMEWORK OF THE CHAIN SURVEY IS ESTABLISHED THEN
MEASUREMENTS CAN BE TAKEN FROM EACH CHAIN LINE & SURVEY
STATIONS TO FIND THE LOCATION OF DISTINCT FEATURES SUCH AS
PAVEMENT, KERBS, TREES ETC.
DETAIL IS ADDED TO FRAMEWORK
BY TAKING TWO TYPES OF
MEASUREMENTS:
1. OFFSETS
2. TIES