Professional Documents
Culture Documents
By:-
Gaurav Goyal
Asstt Prof, LMTSOM
1 03/02/22 05:52
MRP
Material requirements planning (MRP): Computer-
based information system that translates master schedule
requirements for end items into time-phased
requirements for subassemblies, components, and raw
materials.
2 03/02/22 05:52
SOME KEY TERMS
GROSS REQUİREMENTS
The total expected demand for an item or raw material
during each time period without regard to the amount on
hand.
SCHEDULED RECEİPTS
Open orders (orders that have been placed and are) scheduled
to arrive from vendors or elsewhere in the pipeline by the
beginning of a period.
PROJECTED ON HAND
The expected amount of inventory that will be on hand at the
beginning of each time period.
NET REQUİREMENTS
The actual amount needed in each time period.
3 03/02/22 05:52
SOME KEY TERMS
PLANNED-ORDER RECEİPTS
The quantity expected to be received by the beginning of the
period in which it is shown.
PLANNED-ORDER RELEASES
Indicates a planned amount to order in each time period;
equals planned-order receipts offset by lead time
LEAD TIME
Lead time is the period between a customer's order and
delivery of the final product
4 03/02/22 05:52
Independent and DependentIndependent
DemandDemand
A Dependent Demand
B(4) C(2)
6 03/02/22 05:52
DEPENDENT VS INDEPENDENT
DEMAND
100 x 1 =
100 tabletops
Continuous demand
400 –
Discrete demand
400 –
No. of tables
300 –
No. of tables
300 –
200 –
200 –
100 –
100 –
1 2 3 4 5
Week M T W Th F M T W Th F
7 03/02/22 05:52
INDEPENDENT DEMAND
Demand for the tables
Quantity
Time
Inventory of tables
On-hand
inventory
8 Time
03/02/22 05:52
From Aggregate Plan to MRP
Aggregate Production Plan
No
Can we produce 10,000 equivalent
Capacity ? units (total for products A, B and
C) per month for the next year?
Yes
Master Production Schedule
11 03/02/22 05:52
MRP Inputs MRP Processing MRP Outputs
Changes
Order releases
Master
schedule Planned-order
schedules
Primary
reports Exception reports
Bill of Planning reports
materials MRP computer Secondary
Performance-
programs reports control
reports
Inventory
records Inventory
transaction
12 03/02/22 05:52
MRP Inputs
Master Production Schedule
Time-phased plan specifying timing and quantity of
production for each end item.
Material Requirement Planning Process
r e
c tu
t ru
S
u ct
rod e s
P ee T im
Tr ea d
L
13 03/02/22 05:52
Master Schedule
14 03/02/22 05:52
Bill-of-Materials
15 03/02/22 05:52
Product Structure Tree
Figure 13.5
Level Chair
0
1 Leg Back
Assembly Seat Assembly
16 03/02/22 05:52
Nature of MRP
B ik e Level 0
F ra m e S eat B ra k e K it F ro n t W h e el R e ar W h eel
Level 1
R im S p o kes
Level 2
H o op W ire
Level 3
18 03/02/22 05:52
MRP Processing
Gross requirements
Schedule receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases
19 03/02/22 05:52
MRP Processing
Gross requirements
Total expected demand
Scheduled receipts
Open orders scheduled to arrive
Planned on hand
Expected inventory on hand at the beginning of each
time period
20 03/02/22 05:52
MRP Processing
Net requirements
Actual amount needed in each time period
Planned-order receipts
Quantity expected to received at the beginning of the
period
Offset by lead time
Planned-order releases
Planned amount to order in each time period
21 03/02/22 05:52
End od Session 6
22 03/02/22 05:52
MRP Example
23 03/02/22 05:52
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
It takes 2 LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
A’s for On- Net requirements 20
each X hand Planned order receipt 20
25 Planner order release 20
C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
24 03/02/22 05:52
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
It takes 1 B Proj. avail. balance 25 25 25 25 25 25 25 25
for each X On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
25 03/02/22 05:52
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 3 C’s C Gross requirements 45 40
LT=2 Scheduled receipts
for each A Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
26 03/02/22 05:52
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 2 C Gross requirements 45 40
LT=2 Scheduled receipts
C’s for each Proj. avail. balance 10 10 10 10 10
B On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
27 03/02/22 05:52
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) D(5) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 5 D’s C Gross requirements 45 40
LT=2 Scheduled receipts
for each B Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
28 03/02/22 05:52
Assignment question
29 03/02/22 05:52
Updating the System
Regenerative system
Updates MRP records periodically (less dynamic)
Net-change system
Updates MPR records continuously (more dynamic)
30 03/02/22 05:52
MRP Outputs
Planned orders - schedule indicating the amount and
timing of future orders.
Order releases - Authorization for the execution of
planned orders.
Changes - revisions of due dates or order quantities, or
cancellations of orders.
Performance-control reports - used to track problems
like missed delivery dates and stock outs in order to
evaluate system performance.
Planning reports - are useful in forecasting future
inventory requirements.
Exception reports - call attention to major discrepancies
such as late and overdue orders, excessive scrap rates etc.
31 03/02/22 05:52
Other Considerations
Safety Stock
term used by inventory specialists to describe a level of
extra stock that is maintained below the cycle stock to
buffer against stockouts.
Safety Stock exists to counter uncertainties in supply
and demand
More complex for dependent demand items as compared
to independent demand items
Safety stock should be as minimum as possible
32 03/02/22 05:52
Benefits of MRP
Low levels of in-process inventories
33 03/02/22 05:52
Requirements of MRP
Computer and necessary software
Accurate and up-to-date
Master schedules
Bills of materials
Inventory records
Integrity of data
34 03/02/22 05:52