Professional Documents
Culture Documents
Aggregate Production
and Resource
Requirement Planning
Resource Requirement Planning
Inventory
Subcontract
Aggregate Production
Planning
Based on the planning horizon, We can
divide plans into 3 general categories:
Aggregate Production
Planning
Aggregate Production
Planning
The heart of the medium range planning is
the aggregate production plan.
In aggregate planning, given the demand
forecast, production capacity, inventory
levels, size of work force, and other
inputs
The planner has to select the rate of output
for the next 3 to 18 months.
An Example Aggregate
Plan
A company produces four models of
TV
An Example Aggregate
Plan
An Example Aggregate
Plan
Here, operations manager makes decisions
about intermediate range capacity
without getting into details of specific
products, parts, or people.
Later, he/she deals with financial data,
personnel, capacity, and availability of raw
material as well.
The Concept of Aggregation
Aggregate planning is a “big picture”
approach that does not focus on individual
products or services. Instead, the focus is on
groups of similar products of an entire
product line.
Examples:
Total number of bikes produced
Total number of customers served
Relationships Of
Aggregate Plan
Aggregate Planning Process
13-14
Strategies In Aggregate
Planning
Overtime Price
Mixed
Strategy
Sub-
Inventor
contract
y
Strategies In Aggregate
Planning
1. Changing inventory levels
This is to increase inventory during periods
production rates.
In this option, often new employees need
to be trained.
Strategies In Aggregate
Planning
3. Varying production rates through
overtime or idle time :
There is always a limit for overtime.
Costs also increase.
Strategies In Aggregate
Planning
4. Subcontracting
Costly, opens doors to competitors, hard
to find perfect subcontractor.
5. Using part time workers
e.g., Fast food restaurants
Strategies In Aggregate
Planning
6. . Back ordering at high demand
periods :
Back ordering means that a firm promises
Inputs Outputs
Master
Forecast Scheduling Master production
schedule
Customer orders
Master Production
Schedule
MPS specifies what is to be made AND when.
MPS is a STATEMENT OF PRODUCTION, It is Not a
Forecast.
A Master Production Schedule or MPS is the plan that a
company has developed for production, inventory,
staffing, etc.
It sets the quantity of each end item to be
completed in each week of a short-range planning
horizon.
A Master Production Schedule is the master of all
schedules. It is a plan for future production of end items.
MPS INPUTS:
MPS OUTPUT
Forecast Demand
(production plan):
Amounts to be
Production Costs
Produced
Inventory Costs
Staffing Levels
Customer Orders
Quantity Available to
Inventory Levels
Promise
Supply Lot Size
Projected Available
Production
Balance
Lead Time
Capacity
Material Requirement Planning (MRP)
31
Key Outputs of MRP
100 x 1 =
100 tabletops
100 tables
33
MRP Input & Output
MPS
Material Inventory
BOM Requirements
Planning
Records
File
(MRP)
Clipboard
Rivets (2)
Finished clipboard Pressboard (1)
Major Inputs to MRP Process:
Bill of Material
Level 0
Clipboard
Top clip (1) Bottom clip (1)
(1)
37
Example
Assume that, this week’s Demand for product
A is 50 units.
Each unit of A requires two units of B and
three units of C.
Each unit of B requires two units of D and
three units of E.
Each unit of C requires one unit of E and two
units of F.
Each F requires one unit G and two units of
D.
Example : To produce 50 units of A,
calculate the required quantity for each of
the component
Example
Therefore, Demand for B,C,D,E,F,G is
completely dependent on the demand for
A.
Once we develop product structure, We
can get the Number of units Required to
Satisfy demand for product A.
Example
For example: For part B: 2 x 50 = 100
units of B is required.
Similarly, For part C: 3x50 = 150 units
of C is required.
Example
For part E: 3(B) + 1(C) = 3(100) + 150 =
450 units of E is required.
For part F: 2(C) = 2(150) = 300 units of F is
required.
For part D: 2(B) + 2(F) = 2(100) + 2(300) =
200 + 600 = 800 units of D is required.
For part G: 1(F) = 300 units of G is required.
Major Inputs to MRP Process:
2. Master Production Schedule (MPS)
Level Chair
0
1 Leg Back
Assembly Seat Assembly
44
Explosion Example
How many leg assemblies are needed for 1
chair?
How many Cross bars are needed for 5 chairs?
_________________________________________________
Contains an extensive amount of information on every
item that is produced, ordered, or inventoried in the
system
_____________________________________________
DESCRIPTION INVENTORY POLICY
Item
____ Pressboard Lead time 1
Item no. 734 Annual demand 5000
Item type Purch Holding cost 1
Product/sales class Comp Ordering/setup cost 50
Value class B Safety stock 0
Buyer/planner RSR Reorder point 39
Vendor/drawing 07142 EOQ 316
Phantom code N Minimum order qty 100
Unit price/cost 1.25 Maximum order qty 500
Pegging Y Multiple order qty
LLC 1 Policy code 3 46
MRP Processes – 4 Basic
Steps
1. Exploding the bill of material
___________________________________
2. Netting out inventory
___________________________________
___________________________________
3. Lot sizing rule – How many units
___________________________________
___________________________________
___________________________________
4. Time-phasing requirements
___________________________________
47
MRP Matrix
Gross Requirement
Derived from planned order releases of the parent
Actual / estimated demand, in case of final product
Schedule Receipts
Items on order
Scheduled to arrive in the future time period
Projected on hand
Current inventory, or anticipated inventory at the end of period
Projectedon-hand
on-hand Inventoryon-
Inventory on- Scheduled//
Scheduled Gross
Gross
Projected
Inventoryat atend
end handat
hand atend
endof
of planned
planned requirements
requirements
Inventory
ofperiod
of periodtt = periodtt--11
period + receiptsin
receipts in - inperiod
in periodtt
periodtt
period
48
MRP Matrix
Net requirements
Actual quantity to produce based on projected on hand and on-
order quantity
Planned Order Receipts
Quantity, when orders need to be received
Consider lot sizing rule:
Planned Order Release
When order need to be placed to receive on time
Consider lead time
49
MRP Outputs
Planned orders - schedule indicating the
amount and timing of future orders.
Order releases - Authorization for the
execution of planned orders.
Changes - revisions of due dates or order
quantities, or cancellations of orders.
Performance-control reports
Planning reports
Exception reports
50
MRP in Services
51
Benefits of MRP
52
Requirements of MRP
Computer system and necessary software
Mainly discrete products
Stable lead times
Accurate and up-to-date
Master schedules
Bills of materials
Inventory status records
Integrity of data
Requirements of MRP
54
MRP Matrix
15-55
MRP: Example
Master Production Schedule
1 2 3 4 5
Clipboard 85 95 120 100 100
Lapdesk 0 60 0 60 0
15-56
MRP: Example (cont.)
Product Structure Record
Clipboard Level 0
Lapdesk Level 0
15-57
MRP: Example (cont.)
15-58
MRP: Example (cont.)
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Gross Requirements 85 95 120 100 100
Scheduled Receipts 175
Projected on Hand 25 115
Net Requirements 0
Planned Order Receipts
Planned Order Releases
15-60
MRP: Example (cont.)
20 units available
(20 - 120) = -100 — 100 additional Clipboards are required
Order must be placed in Period 2 to be received in Period 3
15-61
MRP: Example (cont.)
15-63
MRP: Example (cont.)
15-64
MRP: Example (cont.)
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Planned Order Releases 100 100 100
ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Planned Order Releases 50 50
ITEM: PRESSBOARD LLC: 0 PERIOD
LOT SIZE: MIN 100 LT: 1 1 2 3 4 5
Gross Requirements
Scheduled Receipts
Projected on Hand 150
Net Requirements
Planned Order Receipts
Planned Order Releases
15-65
MRP: Example (cont.)
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Planned Order Releases 100 100 100
ITEM: LAPDESK LLC: 0 x1 PERIOD x1 x1
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Planned Order Releases 50 50
ITEM: PRESSBOARD LLC: 0 x2 x2 PERIOD
LOT SIZE: MIN 100 LT: 1 1 2 3 4 5
Gross Requirements 100 100 200 100 0
Scheduled Receipts
Projected on Hand 150
Net Requirements
Planned Order Receipts
Planned Order Releases
15-66
MRP: Example (cont.)
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Planned Order Releases 100 100 100
ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Planned Order Releases 50 50
ITEM: PRESSBOARD LLC: 0 PERIOD
LOT SIZE: MIN 100 LT: 1 1 2 3 4 5
Gross Requirements 100 100 200 100 0
Scheduled Receipts
Projected on Hand 150 50 50 0 0 0
Net Requirements 50 150 100
Planned Order Receipts 100 150 100
Planned Order Releases 100 150 100
15-67
MRP: Example (cont.)
15-68
Overview of the MRP System
Product Master
Inventory
Structure Production
Master File
File Schedule
Material
Requirements
Planning
70
Example MRP Matrix
71
MRP Example 1
Given the following information, determine when orders
should be released for A, C, and D and the size of those A
orders
LT=3
C(3) D(2)
LT=4 LT=2
A 10 0 100, period 8
C 140 0
D 200 250, period 2
72
Parts On hand Scheduled Demand
Receipts
A 10 0 100, period 8
C 140 0
D 200 250, period
1 22 3 4 5 6 7 8
A Gross Req 100
LT=3 Scheduled
Receipt
Proj available 10 10 10 10 10 10 10 0
Balance (10)
Net 90
Requirement
Planned Order 90
Receipt
Planned Order 90
Release
1 2 3 4 5 6 7 8
Gross Req 180
D
LT=2 Scheduled 250
Receipt
Proj available 200 450 450 450 270 270 270
Balance (200)
Net
Requirement
Planned Order
Receipt
Planned Order
11 22 3 3 4 4 55 6 6 7 7 88 99 10
10
XA Gross
Gross Req
Req 90
95
Scheduled
Scheduled
Receipt
Receipt
Proj
Proj available
available 75 75 75 75 75 75 75
Balance
Balance (75)
(50)
50 5 5 50 50 5 50 50 50 0
Net 0 0 0 15
Requirement
Net
Requirement
45
Planned 15
Planned Order
Order Receipt
Receipt
45
Planned 15
Planned Order
Order Release
Release
45
B Gross Req 45
Scheduled
Receipt
Proj available 25 25 25 25 25 25 25
Balance (25)
Net 20
Requirement
Planned 20
Order Receipt
Planned 20
Order Release
1 2 3 4 5 6 7 8 9 10
C Gross Req 45 40
Scheduled
Receipt
Proj available 10 10 10 10
Balance (10)
Net 35 40
Requirement
Planned 35 40
Order Receipt
Planned 35 40
Order Release
1 2 3 4 5 6 7 8 9 10
D Gross Req 100
Scheduled
Receipt
Proj available 20 20 20 20 20 20
Balance (20)
Net 80
Requirement
Planned 80
Order Receipt
Planned 80
Order Release
MRP Processing:
Example 2
Item On-Hand Lead Time (Weeks)
X X 50 2
A 75 3
B 25 1
A(2) B(1) C 10 2
D 20 2
Requirements
Requirementsinclude
include95
95units
units(80
(80firm
firmorders
ordersand
and15
15forecast)
forecast)
of
ofXXin
inweek
week10
10
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
ItIttakes
takes
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
22A’s
A’sfor
for On-
hand
Net requirements
Planned order receipt
20
20
each
eachXX 25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
ItIttakes
takes Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
11BBforfor hand Planned order receipt 20
each
eachXX
25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
ItIttakes
takes33
C
LT=2
Gross requirements
Scheduled receipts
45 40
C’s
C’sforfor On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each
eachAA
hand
10
Planned order receipt
Planner order release 35
35
40
40
ItIttakes
takes22
C
LT=2
Gross requirements
Scheduled receipts
45 40
C’s
C’sforfor On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each
eachBB
hand
10
Planned order receipt
Planner order release 35
35
40
40
ItIttakes
takes55
C
LT=2
Gross requirements
Scheduled receipts
45 40
D’s
D’sforforeach
each On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
BB hand
10
Planned order receipt
Planner order release 35
35
40
40
Safety Stock
Not much for items with dependent demand
Lot sizing
Lot-for-lot ordering
Economic order quantity
Fixed-period ordering
Part-period model
82
MRP Outputs
Manufacturing Orders
Purchasing Orders
Various Reports
8
3
Hubbell Lighting Case
8
4
Hubbell Lighting Case
Before MRP After MRP
Implementation Implementation
8
5
Capacity Requirement
planning (CRP)
Capacity is the maximum output rate of a facility
Capacity planning is the process of establishing the
output rate that can be achieved at a facility:
Capacity is usually purchased in “chunks”
86
Measuring Capacity Examples
There is no one best way to measure capacity
Output measures like kegs per day are easier to understand
With multiple products, inputs measures work better
87
Capacity Planning
Capacity of a plant is the ability to meet the
demand in terms of products or services
offered by the plant.
Time horizon in capacity Planning:
Long Term : Establishes a firm’s overall level of
resources.Eg. Buildings, Equipments,etc.
Intermediate Range: Hiring or laying off
labour,etc.
Short Range: overtime, production routing, etc.
Capacity Planning
Capacity is the upper limit or ceiling
on the load that an operating unit can
handle.
The basic questions in capacity handling
are:
What kind of capacity is needed?
How much is needed?
When to increase?
Importance of Capacity
Decisions
Impacts ability to meet future demands
Affects operating costs
Major determinant of initial costs
Involves long-term commitment
Affects competitiveness
Affects ease of management
CRP
MRP planned
order
releases
Capacity Open
Routing
requirements orders
file
planning file
15-91
Measuring Available Capacity
Design capacity:
Maximum output rate under ideal conditions
A bakery can make 30 custom cakes per day
when pushed at holiday time
Effective capacity:
Maximum output rate under normal (realistic)
conditions
On the average this bakery can make 20
custom cakes per day
Actual output
rate of output actually achieved--
Measures effectiveness
Use either effective or design capacity in
denominator
94
Example of Computing Capacity Utilization: A bakery’s
design capacity is 30 custom cakes per day. Currently the bakery is
producing 28 cakes per day. What is the bakery’s capacity
utilization relative to both design and effective capacity?
actual output 28
Utilizatio n effective (100%) (100%) 140%
effective capacity 20
actual output 28
Utilizatio n design (100%) (100%) 93%
design capacity 30
95
Making Capacity Planning
Decisions
96
CRP
Michel makes bow ties. His company is called Michel's Bows. It has
grown over the years and has customers all over the world. It's not just Michel
making the bow ties now. He has several employees that also sew the
bow ties. Each month, Michel performs
Companies perform MRP so they can see what materials are needed, in what
quantity, and when they are needed to successfully fill all their orders.
The MRP tells companies when to order the materials so they can make the
products to fulfill demand. CRP tells companies how many products they can
make per employee, per workstation, etc. per hour, per day, per month.
For Michel, his MRP tells him when he needs to order his
fabrics and in what quantity to make the bow ties that his
customers have ordered.
His CRP tells him how many bow ties each of his employees
and himself can make per hour, per day, etc.
he adds the set-up time for the week. Billy gets ( 300 * 0.5 ) + 0.83
= 150.83 work hours needed per week to fulfill 300 bow ties per
week.
Manufacturing Resources Planning- MRP II
Expanded MRP with emphasis placed on integration of:
Financial planning
Marketing
Engineering
Purchasing
Manufacturing
Human resources
Manufacturing Resources Planning
(MRP II)
Goal: Plan and monitor all resources of a
manufacturing firm (closed loop):
manufacturing
marketing
finance
engineering
Simulate the manufacturing system
MRP II : Manufacturing
Resource Requirement
Planning
MRP- II is defined as a method for the
effective planning of all resources of a
manufacturing company. Ideally, it addresses
operational planning in units, financial
planning, and has a simulation capability to
answer "what-if" questions and extension of
closed-loop MRP
104
MRP II
Market Master
Finance Manufacturing production schedule
Demand
Rough-cut Capacity
capacity planning planning
Adjust
production plan
Yes No Requirements No Yes
Problems? schedules Problems?
105
Difference Between MRP &
MRP-II
MRPII is concerned with
MRP is concerned the coordination of the
primarily with entire manufacturing
manufacturing production, including
materials materials, finance, and
human relations
The goal of MRPII is to
provide consistent data to
all players in the
manufacturing process as
the product moves through
the production line.
MRP allows for the MRPII systems begin
input of sales forecasts with MRP, material
from sales and requirements planning.
marketing. These
forecasts determine
the raw materials
demand.
• MRP systems draw on a master production schedule, the
breakdown of specific plans for each product on a line.
• While MRP II allows for the coordination of raw materials
purchasing, MRPII facilitates the development of a detailed
production schedule that accounts for machine and labor
capacity, scheduling the production runs according to the arrival
of materials.