Professional Documents
Culture Documents
MATERIAL REQUIREMENTS
PLANNING
Chapter 9
Learning Objectives
1. Describe what material requirements planning
(MRP) is.
2. Understand how the MRP system is structured.
3. Analyze an MRP problem.
4. Evaluate and compare MRP lot-sizing techniques.
9- 2
Material Requirement Planning (MRP)
9- 3
Material Requirements Planning (MRP)
9- 4
MRP System Structure
MRP
system
inputs
MRP
system
outputs
9- 5
MRP System Structure
¨ MRP system has essentially three sources of
information:
1. Master production schedule states the number of
items to be produced during specific time periods
2. Bill of materials (BOM) identifies the specific
materials used to make each item and the correct
quantities of each
3. Inventory record file contains data such as number
of units on hand and on order
9- 6
Master Production Scheduling
Week
9- 8
Bill of Materials (BOM)
¨ Contains the complete product description, listing
the materials, parts, and components along with the
sequence in which the product is created
¨ Often called the product structure file or product
structure tree because it shows how a product is put
together
9- 9
BOM Example
Product A Product A
– the end consists of 2
item B and 3 C
Product C consists
Product B of 2 F, 5 G and 4
consists of 1 H
D and 4 E
9- 10
Alternate BOM Structures
9- 11
BOM Hierarchy (Levels)
Higher levels (Iower
numbers) refer to end
products
Basic
information
describing the
item
Information
about part
availability
Additional
information
that may be
useful
9- 13
MRP Explosion Process
The requirements for end items are retrieved from the
master schedule
• These are referred to as “gross requirements” by the MRP program
9- 14
MRP Explosion Process (continued)
9- 15
MRP Example – Ampere, Inc.
¨ Ampere, Inc., produces a line of electric meters installed in
residential buildings
¨ Meters are of two basic types for different voltage and
amperage ranges
¤ Some subassemblies are sold separately for repair or for
changeovers
¨ The problem is to determine a production schedule to
identify each item, the period it is needed, and the
appropriate quantities
¨ The schedule is then checked for feasibility, and the schedule
is modified if necessary.
9- 16
Future Requirements – Meters A and B
and Subassembly D
9- 17
Product Structure and Inventory Data
9- 18
MPR Record
9- 19
MRP Planning Schedule
Exhibit 9.13 9- 20
Example 9.1
From p. 284
9- 21
Example 9.1
9- 25
Lot-for-Lot
Produces exactly
Sets planned orders what is needed each
to exactly match the week with none
net requirements carried over into
future periods
9- 26
Economic Order Quantity
Wk 1 2 3 4 5 6 7 8
NR 50 60 70 60 95 75 60 55
9- 28
Comparison – Lot-for-Lot and EOQ
Lot-
for-
Lot
EOQ
9- 29
Least Total Cost
¨ Least total cost method (LTC) - a dynamic lot-sizing
technique that calculates the order quantity by
comparing the carrying cost and the setup costs for
various lot sizes and then selects the lot in which
these are most nearly equal
¤ Lot sizes evaluated are designed to cover an increasing
amount of time (1 week, 2 weeks, etc.)
¨ Influenced by the length of the planning horizon
9- 30
Least Total Cost
9- 31
Least Unit Cost
¨ Least unit cost method - a dynamic lot-sizing
technique that adds ordering and inventory
carrying cost for each trial lot size and divides by
the number of units in each lot size, picking the lot
size with the lowest unit cost
9- 32
Least Unit Cost
9- 33
Choosing the Best Lot Size – Example
(continued)
¨ The total cost for the eight weeks:
¤ Lot-for-lot method - $376.00
¤ Economic order quantity - $171.05
9- 34
MRP Matrix
¨ Scheduled Receipts: orders that have already released and are scheduled to
arrive as of the beginning of the period
¨ Projected available balance : amount of inventory that is expected at the end
of a period
Projected available balance (t)= projected available balance (t-1) + scheduled
receipts(t) + planned order receipts(t) – gross requirement(t)
Note: “safety stock” of an item will be retained throughout periods once it is
obtained.
¨ Net requirements: the amount needed when the projected available balance
plus the scheduled receipts in a period are not sufficient to cover the gross
requirement.
¨ Planned order receipts: the amount that will be ordered and when that amount
must be received
¨ Planed order releases: this determines when orders should be placed (i.e.,
released) so that they are received when needed
9- 35
Exercise
Each unit of A is composed of one unit of B, two units of C, and one units of D. C
is composed of two units of D and three units of E. Item A, C, D, and E have
on-hand inventories of 20, 10, 20, and 10 units, respectively. Item B has a
scheduled receipt of 10 units in Period 1, and C has a scheduled receipt of
50 units in Period 1. Lot-for lot (L4L) is used for Item A and B. Item C
requires a minimum lot size of 50 units. D and E are required to be
purchased in multiples of 100 and 50, respectively. Lead times are one
period for Items A, B, and C, and two periods for Items D and E. The gross
requirements for A are 30 in Period 2, 30 in Period 5, and 40 in Period 8.
The company does not carry any safety stock for any item.
(a) Show the master production schedule.
(b) Draw the bill of materials (product structure tree)
(c) Show the inventory records file.
(d) Using the MRP matrix, find the necessary planned order releases for all
items.
(e) Show the planned order report
9- 36
Extra MRP Example
Item On-Hand Lead Time (W eeks)
X X 50 2
A 75 3
B 25 1
A(2) B(1) C 10 2
D 20 2
9- 37
Week: 1 2 3 4 5 6 7 8 9 10
X X
LT=2
Gross requirements
Scheduled receipts
95
each X C
LT=2
Gross requirements
Scheduled receipts
45 40
each X C
LT=2
Gross requirements
Scheduled receipts
45 40
Exhibit 9.2
9- 44
Question Bowl
9- 45
Question Bowl
9- 48
Question Bowl
a. BOM file
b. Exception report
c. Planning report
d. All of the above
e. None of the above
Answer: a. BOM file (Correct answer can
also include Master Schedule and Inventory
Records File.) 9- 49
Question Bowl
9- 50
Question Bowl
a. Work overtime
b. Renegotiate the due date and reschedule
c. Subcontract to an outside shop
d. All of the above
e. None of the above
¨ Read Chapter 9
¨ Understand Ch 9 Solved Problems
¨ Solve Problems: 9, 12, 17, 21, and extra problem
in the solutions.
9- 53