Professional Documents
Culture Documents
02W2-3 - Ch02 - Facilities Planning - Product, Process and Schedule Design
02W2-3 - Ch02 - Facilities Planning - Product, Process and Schedule Design
Chapter 2
Product, Process and
Schedule Design
Tran Van Ly
Industrial Engineering and Management
International University
22/03/17 1
Email: tvly@hcmiu.edu.vn
Lecture outline
1. Introduction
2. Product design
3. Process design
4. Schedule design
5. Facilities design
6. Summary
2
I. Introduction
• This chapter focuses on the product, process and schedule design (PP&S) functions as they
relate to facilities planning.
• Alternative facilities plans can be generated are the following:
1. What is to be produced?
2. How are the products to be produced?
3. When are the products to be produced?
4. How much of each product will be produced?
5. For how long will the products be produced?
6. Where are the products to be produced?
3
II. Product Design
• Product design involves both:
– the determination of which products are to be produced
– the detailed design of individual products
7
Process Design
1. Process identification
- Make-or-buy analysis
- Parts identification
2. Process selection
- How the product will be made
(operations, equipment, raw
material, etc.)
3. Process sequencing
- How components are put together
8
Process Design – 1. Process identification
Make-or-buy decisions
The scope of the facility depends on the level of
vertical integration
made/purchased.
of a product:
1. part numbers Fig 2_7: Parts list for an air flow regulator.
2. part name
product
4. drawing references
11
Process Design – 2. Process Selection
12
Table 2_1: Route sheet data requirements
• Route
sheet -
output of
process
selection,
it identifies
processes,
equipment
and raw
materials
Fig 2_10: Route sheet for one component of the air flow regulator 13
Process Design – 3. Process Sequencing
assembly charts
information on
production methods
• Assembly chart
determines how
together
is a combination of route
Fig 2_12: Operation process chart for the air flow regulator
sheet and assembly chart 15
Fig 2_13: Precedence diagram for the air flow regulator
16
IV. Schedule Design
• Schedule design provides answers to questions involving:
◦ Production quantity - lot size decisions
◦ When to produce - production scheduling
◦ How long to produce
Ideal
Information
Provided by
Marketing
Table 2_3: Market analysis indicating the stochastic nature of future requirements for facilities planning 18
Qualitative
Information
from
Marketing
Table 2_4: Valuable information that should be obtained from Marketing and used by a facilities planner
19
• 85% of the production volume is
Volume-variety chart – Pareto law
attributed to 15% of the production
line Volume-variety chart – Pareto law
21
Process requirements – Quantity determination
Scrap Estimates
◦ Determination of the quantity to be manufactured for each
component
For high volume production
The estimation of scrap
22
1. Calculation of production requirements
Eq 2_1
Eq 2_2
• For products with n sequential operations, the expected number of units to start into
production at the first operation is shown (On: the required production volume for the final
product):
Eq 2_3
23
Example 1: (page 51-52)
Calculating production requirements for a serial process with three operations
Thus
Since
25
Example 2: (Please see page 53-54)
Calculating production requirements for assembled products
The final products are 02 assemblies requiring 03 components (see data in fig 2-17).
Using the eq. 2_3 in calculating components requirements for assembled products.
The calculations required are also shown in this figure.
26
Fig 2_17: Component requirements for assembles and subassemblies for Ex. 2
3. Reject Allowance Problem.
E[P(Q)]
27
Eq 2_4
28
Example 3: (Please see page 55-56)
Calculating production quantities that will maximize profit
The revenue and cost functions can be given: Table 2.6: Probability distributiuons for the number of good castings (x) out of Q
29
Table 2_7: Profit from producing Q castings, with exactly x being good
30
4. Estimation of number of machines required.
– The following deterministic model can be used to estimate the
machine fraction required:
Eq 2_5
31
Example 4: (Please see page 59)
S = 2.8 minutes per part; Q = 200 units per shift; H = 480 minutes/shift; E = 0.95 and
R = 0.08
32
5. Specifying total machine requirements.
33
6. Machine assignment problem.
a: concurrent activity time (e.g: loading
and unloading a machine)
b: independent operator activity time (e.g:
walking, inspecting, packing)
t: independent machine activity time (e.g:
automatic machining time)
n’: ideal number of identical machines to
assign an operator
m: number of identical machines assigned
an operator
Tc: repeating cycle time
Io = idle operator time during a repeating
cycle
Im = idle time for each machine during a
repeating cycle Fig 2_18: Multiple activity chart for example 6 (2.7)
34
Example 6: (Please see page 60-62)
Analyzing the assignment of operators to multiple machines
Eq 2_07
Eq 2_08
Eq 2_09
Eq 2_12
Eq 2_11
35
If <1: then TC(n) < TC(n+1), and n machines should be assigned;
If >1: then TC(n + 1) < TC(n), and n + 1 machines should be assigned;
If =1: then either n or n + 1 machines should be assigned.
E.x:
Suppose C0 = $15/ hour, Cm = $50/ hour.
Therefore, = 0.30 and = 0929.
Since < 1, two machines should be assigned to an operator (example in
fig. 2-18: 3 machines).
36
Fig 2_19: Assignment of 03 machines to 01 operator
V. Facilities Design
• Once the product, process and schedule design decisions have
been made, the facilities planner needs to organize the
information and generate and evaluate layout, handling,
storage and unit load design alternatives.
37
1. Affinity diagram
38
2. Interrelationship diagraph
3. Assign raw
1. Form product 2. Assign families
materials to
families to manufacturing cells
their point of use
3. Tree diagram
39
Fig 2_22 Tree diagram for formation of product families
4. Matrix diagram
Table 2_10
5. Contingency diagram
The contingency diagram, also known as the process decision program
chart, maps conceivable events and contingencies that might occur during
implementation. It is particularly useful when the project being planned
consists of unfamiliar tasks.
The benefit of preventing or responding effectively to contingencies makes it
worthwhile to look at these possibilities during the planning phase.
40
6. Activity network diagram
Fig 2_23: Activity network diagram example for a production line expansion facilities design project.
41
7. Prioritization Matrix
Table 2_12: Prioritization Matrix for the Evaluation of Facilites Design Alternatives
42
Fig 2_24 Logical application sequence of the seven management and planning tools 43
Fig 2_25 How the seven management and planning tools facilitate the planning of a facilities design project