You are on page 1of 11

PETROCHEMICAL DEVELOPMENT

PROJECT IN ECUADOR
PARTICIPANTS
EP PETROECUADOR
ECUADORIAN PUBLIC
HYDROCARBONS COMPANY

&
"EP UPSE“
UNIVERSITY
PUBLIC COMPANY
PILOT PLAN FOR PETROCHEMICALS
DEVELOPMENT IN ECUADOR
Consortium between:
EP Petroecuador and EP UPSE
PROJECT OBJECTIVE:
Delegate the partial operation of Cautivo Refinery
from La Libertad to EP UPSE for Petrochemical
research and development.
The equipment and facilities will be made by private
investors.
SUMMARY ANALYSIS

• The consortium will permit us to start a basic


petrochemical project at the Cautivo Refinery.
• Ecuador is a net importer of petrochemical products,
having imported millions of dollars annually in basic
products, polyethylene and polyvinyl chloride being the
most imported products.
• We are also fertilizers importers.
• Ecuador imports an overage of 280,000 tons of Urea
annually (777 tons/day; the country requires 1500
tons/day).
According from Ecuador Central Bank data (BCE): total imports during 2020
were $16,986.8 million dollars FOB
https://blogs.cedia.org.ec/obest/wp-content/uploads/sites/7/2021/04/Impor
taciones-ecuatorianas.pdf

IMPORT
chemical
products data
IMPORTACIÓN
1. The Public Company EP UPSE creates a Petrochemical Unit.
2. Petroecuador delegates the partial operation of El Cautivo
refinery to EP UPSE for the project.
3. The Unit would be in charge of analyzing the raw material that
the refinery would have to provide for the project.
4. Calculation of available raw material and define the products to
be processed.
5. Location for the processing plant and the basic engineering
PETROCHEMICAL project.
6. Invitation APROQUE members and Plastics Association to
PROJECT STAGES participate in the project.
7. At the same time, talks would be held with possible investors.
8. Invitation to investors to visit the refinery and project
presentation.
9. Definition of detailed engineering.
10. Process plant acquisition
11. Plant construction
12. Production and marketing.
 

1. May 2-10 /2022.- Signing EP Petroecuador - UPSE EP


agreement.
2. May 24 – 30.- EP Petroecuador delegates El Cautivo refinery
for the project.
3. May 2 – 15.- The EP UPSE will initiate the project outlines.
IMPORTANT 4. May 15 – onwards.- EP UPSE Operational Unit would oversee

MILESTONES analyzing refinery facilities to be provide for the project;


plant location; available raw material and define products to

TO FULFILL be processed.
5. May 16 continue talks.- with companies specializing in the
manufacture of petrochemical plants to define the
technology applicable to the project.
6. June 8 – 9 - Participation at DOWNSTREAM USA 2022 to be
held at the NRG Center, Houston, USA. In this expo we will
invite potential investors and present the project.
7. November 9 – 11 “ECUADOR OIL & POWER 2022” Participation to
officially launch the project for which we would invite other potential
participants in the project.

IMPORTANT
8. November 9 - APROQUE and the Plastics Association will be invited to
participate in the project.

MILESTONES
9. November 10 - At the same time, will be contacted possible investors.
11. November 11 - Invitation to investors to visit the refinery.

TO FULFILL 12. Definition of detail engineering.


13. Equipment acquisition.
14. Plant Construction.
15. Production and marketing.
Petrochemical plant General scheme