You are on page 1of 22

MAINTENANCE OF ELECTRICAL EQUIPMENT

SYSTEMS AT PT TELKOM INDONESIA


(PERSERO) TBK (TELKOM) SURABAYA

Andhika Aryaputra W 0711184000009


Fredy Riko Alamsyah 07111840000021
<<
COMPANY PROFILE
PT Telkom Indonesia (Persero) Tbk (Telkom) is a State-Owned Enterprise (BUMN)
which is engaged in information and communication technology (ICT) services and
telecommunications networks in Indonesia. Telkom's shareholder is the Government of the
Republic of Indonesia with 52.09%, while the remaining 47.91% is controlled by the
public. Telkom's shares are listed on the Indonesia Stock Exchange or Bursa Efek
Indonesia with the code "TLKM" and the New York Stock Exchange (NYSE) with the
code "TLK".
Telkom Group's business activities grow and change in line with the development of
technology, information and digitalization, but are still in the corridor of the
telecommunications and information industry. This can be seen from the business lines that
continue to develop to complement the existing legacy.
TELKOM’S VISION AND MISSION
VISION

• To become the digital telco of choice to advance society Core Values


A = Amanah
MISI K = Kompeten
• Accelerate the development of infrastructure and smart digital platforms that are H = Harmonis
sustainable, economical, and accessible to the whole community.
• Developing leading digital talent that helps drive the nation's digital capabilities and L = Loyal
digital adoption rate. A = Adaptif
• Orchestrate the digital ecosystem to provide the best customer digital experience
K = Kolaborasi
TELKOM’S BUSINESS FIELD

Digital Connectivity Digital Platform Digital Services


Fiber to the x (FTTx), 5G, Data Center, Cloud, Internet of Enterprise, Consumer
Software Defined Networking Things (IoT), Big Data/ Artificial
(SDN)/ Network Function Intelligence (AI), Cybersecurity
Virtualization (NFV)/ Satellite
CME
( CIVIL, MECHANICAL,
ELECTRICAL )
CME
The scope of Operation and Maintenance
management of Power Supply devices includes:
a. Map of the role of managing the operation and
maintenance of power supply devices between
DSO, TReg and Witel units.
b. Management of operation and maintenance of
power supply devices.
c. Support management includes measuring tools &
work facilities and supporting tools.
d. System management power supply device
performance.
FOCUS OF CME STO KEBALEN
About the job description, CME has several focus devices that must operate optimally without any damage to
the equipment, such as :

GENERATOR EXCITATION PRECISION AC TRANSFORMER


CME CHECK UPS

Checklist BIR
Checklist is done by checking all Patrol or a routine of cleaning the
equipment whether it is functioning equipment and starting equipment
properly or not such as generators which run every
Friday
CME TELKOM INSPECTION
Weekly :
 Room and Equipment BIR Check
 Daily Fuel Tank Check
 DEG Starter Battery Check
 Running the DEG Test
Monthly :
 DEG Oil Level Check
 Cooling System Check
 Fan Strap Tightness Check
 DEG Starter Battery Parameter Measurement
 DEG Heater Check
 DEG Running Test
Every 6 months:
 Check the water content in the fuel tank daily & monthly
 Grounding Measurement
 Starter Battery Charger System Check
 Engine oil change
 Inspection or replacement of diesel and oil air filters
Annually :
 Radiator water replacement
 Protection simulation test / alarm system
 Meter accuracy check
ON JOB TRAINING
WORK OF ORDER
WORKS DURING OJT
During the On Job Training, we get several opportunities from doing checklists and also BIR. The checklist
carried out is to carry out patrol monitoring of equipment from each room's AC, battery voltage, rectifier
voltage, while for BIR, diesel generator testing is carried out, cleaning of the generator and cleaning of
damaged precision AC.
WORKS DURING OJT
We also do the work of changing the fan in the generator room in one of the STOs under CME STO
KEBALEN, and after the analysis there was a problem with one of the outlets that experienced a short which
resulted in the MCB on the generator panel trip.
WORKS DURING OJT
In addition, we also carry out office work. For example, making or re-wiring SLD or Single Line Diagrams
from several STOs under CME STO KEBALEN Surabaya, namely STO LAMONGAN, STO SUKODADO,
STO SEDAYU.
ON JOB TRAINING
ASSESMENT
ASSESSMENT IN OJT
The assessment that we do is to do an analysis and also re-wiring the SLD in the STO
Kebalen, here you can see the SLD on the old STO Kebalen
ASSESSMENT IN OJT
After doing some analysis, we think that the SLD on the STO Kebalen is less
effective because if there is a disturbance in one of the transformers it will result in
a load from the STO Kebalen which will trip and will not be supplied by electricity.
For this reason, additional Wiring is made after the two transformers to connect
them in parallel. therefore we suggest for SLD from STO Kebalen to be like this.
ANALYSIS
ANALYSIS ASSESMENT IN OJT
It can be seen that if we parallel the two transformers but these two transformers do not
connect in the same system for the transformer, we suggest a system switch between
transformers. Where we give a special line that connects the output of the transformer and
we give the ACB of 6.3 kA. When there is a problem with one of the transformers, ATS will
automatically switch the load to the Diesel Generator. At that time we can activate the ACB
manually so that ATS will read PLN back on and turn off the generator automatically. There
we can start repairing or replacing a damaged transformer. That way you can save on the use
of generators.
ANALYSIST ASSESMENT IN OJT
In addition, if we parallel the transformer, it is likely that we have to add capacity in both
transformers because the power that comes out of PLN When full load is used is 2770 kVA,
if we continue to use the same transformer before with a capacity of 1600 kVA it will most
likely not be strong enough to supply all of the transformers load. From our consideration it
is necessary to increase the capacity of the transformer to 3000 kVA as a form of fulfilling
the power supply of the entire system in this Kebalen STO.
THANK YOU
REFERENCES
STT PLN, 2016; JURNAL SUTET Vol 6 No.2;ISSN 2356 – 1505
RANCANG BANGUN SISTEM MONITORING TEGANGAN, ARUS, DAN
FREKUENSI KELUARAN
Adi F. I et al; 2020 ; GENERATOR 3 FASA PADA MODUL MINI POWER
PLANT DEPARTEMEN TEKNIK INSTRUMENTASI Vol I No.2; AMORI; ISSN:
2721-3560