Professional Documents
Culture Documents
PRACTICE - 2
UNIT 5 – EMERGENCY SPECIALIZATIONS
FOR AN ARCHITECT
UNIT 5 – CONSTRUCTION
MANAGEMENT
TOPICS THAT WILL BE COVERED!!!
Project Management (Concept, Objectives,
Planning, Scheduling, Controlling and Roles and
Responsibilities of a Project Manager)
Construction Management (Role, Function and
Responsibilities of a Construction Manager)
Suitability of an architect as a
construction/project manager
Programme Evaluation Review Techniques
(event, activity, dummy network rules, graphical
guidelines for network – PERT Network)
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROJECT
MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
An endeavor to accomplish a specific objective
through a unique set of interrelated tasks and
the effective utilization of resources
Has a “well-defined objective” stated in terms of
scope, schedule & costs
Projects are “born” when a need is identified by
the customer – the people or organization willing
to provide funds to have the need satisfied
People are critical in accomplishing the
objectives
Tools & Techniques aid them
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
So, what are few examples of “PROJECT”??
Planning a wedding
Designing and implementing a system or solution
Hosting a holiday party
Designing & producing a brochure
Holding a high-school reunion
Setting up of factory
Etc, etc, etc, etc…
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
“… a non-routine, non-repetitive, one-off-
undertaking, normally with discrete time,
financial and technical performance goals…”
- Harison
“… a system involving the coordination of a
number of separate department entities
throughout the organization and which must
be completed within prescribed schedules &
time constraints… “ – PMI
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
WHAT IS PROJECT MANAGEMENT???
“… discipline of planning,
organizing, motivating &
controlling resources to achieve
specific goals while honoring
the preconceived constraints
such as scope, time, quality and
budget…”
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
Learn to make adjustments
Don’t fail to plan ahead
Train the crew
“… If you don’t
know where you
are going, any road
will take you
there….”
- Confucius
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
For a successful construction project,
A selection process based only on the lowest bid &
which fails to consider quality
Involvement of multiple parties, from the owner to
architects, engineers, general contractors, subbies
and countless vendors
Long term nature of construction projects
Failure to select a “project delivery system”
appropriate to the project
Incomplete drawings and specifications
Unrealistic cost projections
Unrealistic scheduling
UNIT 5 – CONSTRUCTION
MANAGEMENT
OVERVIEW OF PROJECT MANAGEMENT
For a successful construction project,
Unforeseen site and weather conditions
Poor communication & coordination among the
project participants
Attempt by parties to unfairly shift project risks
onto other parties, who have no control over
such risks
Failure to provide adequate contract
administration
UNIT 5 – CONSTRUCTION
MANAGEMENT
TEN COMMANDMENTS OF CONSTRUCTION
Deal with responsible people
Use common sense
Conduct a very thorough site inspection
Define and communicate clear project goals
Enter into and enforce a fair contract
Develop comprehensive drawings and specifications
Make and monitor a realistic construction schedule
Make a realistic budget projection
Face problems promptly & squarely
WORK TOGETHER!!!!
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROJECT DESCRIPTION
The Project Description has three parts:
PURPOSE & SCOPE
Statement of Purpose (Why are we doing this
project, benefits, etc)
Scope can be defined in various ways (organization
structure, departments, geography, process, etc)
Specific “out-of-scope vs. in-scope” items (define
the project limitations and what is not included up
front)
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROJECT DESCRIPTION
The Project Description has three parts:
GOALS & OBJECTIVES
What defines a successful project?
Measures (How will you know you achieved success?)
Critical success factors (document the influences or
barriers to success)
ASSUMPTION, DEPENDENCIES & CONSTRAINTS
Assumptions: factors considered true or certain (Person X
will lead the team, Exec has approved $$$ for project,
etc)
Dependencies on other departments, team or projects
Constraints: factors that will limit the team’s options
(have $$$ allocated for this project, 6 month window for
project, etc)
UNIT 5 – CONSTRUCTION
MANAGEMENT
PLANNING, SCHEDULING & CONTROLLING
The aim of PSC is to show the PM at all times
Precisely where the work stands, and where it should
stand
When delays occur, what must be done to offset them
The cost of correcting delays, compared to the cost of
drag-out that will otherwise accrue
The impact of delays and difficulties which occur on
project completion, start-up, production and the
Owner's return on investment
The earliest practicable time that project completion
and start-up can be expected, if all goes well
UNIT 5 – CONSTRUCTION
MANAGEMENT
PLANNING, SCHEDULING & CONTROLLING
"Planning" means determining what work must be
done to achieve the project objective and the
relationships between the various activities
"Scheduling" means deciding when the various
activities will be carried out
"Control" means making full use of the tools
provided by the scheduling and monitoring
operations and refers to the process of analyzing
data, investigating causes of backlog,
determining solutions, comparing the cost of
these drag-out costs, and preparing specific
recommendations to the Project Manager
UNIT 5 – CONSTRUCTION
MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
PLANNING, SCHEDULING & CONTROLLING
Steps in Planning
DEFINE – the objectives of the project in definite words
ESTABLISH – goals and stages intermediate to attain the final
target
DEVELOP – forecast and means of achieving goals/activities
EVALUATE – organization’s resources – financial, managerial
and operational – to carry out activities and to determine
what is feasible and what is not
DETERMINE – alternatives – individual courses of action that
will allow to accomplish goals
TEST – for consistency with company’s policy
CHOOSE – an alternative which is not only consistent with its
goals and concept but also one that can be accomplished
with the evaluated resources
UNIT 5 – CONSTRUCTION
MANAGEMENT
PLANNING, SCHEDULING & CONTROLLING
Steps in Scheduling
CALCULATE – detailed controlled information
ASSIGN – timings to events and activities
GIVE – consideration to the resources
ALLOCATE – the resources
Steps in Controlling
ESTABLISH – standards or targets. These targets are generally
expressed in terms of time
MEASURE – performance against the standards set down in the
first step
IDENTIFY – the deviations from the standards
SUGGEST AND SELECT – corrective measures – should involve
identifying, decision making and organizing and leadership
skill of the decision maker
UNIT 5 – CONSTRUCTION
MANAGEMENT
ROLES & REPONSIBILITIES OF A PM
Planning and Defining Scope
Activity Planning and Sequencing
Resource Planning
Developing Schedules
Time Estimating
Cost Estimating
Developing a Budget
Documentation
Creating Charts and Schedules
Risk Analysis
UNIT 5 – CONSTRUCTION
MANAGEMENT
ROLES & REPONSIBILITIES OF A PM
Managing Risks and Issues
Monitoring and Reporting Progress
Team Leadership
Strategic Influencing
Business Partnering
Working with Vendors
Scalability, Interoperability and Portability
Analysis
Controlling Quality
Benefits Realization
UNIT 5 – CONSTRUCTION
MANAGEMENT
CONSTRUCTION
MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
CONSTRUCTION MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
CONSTRUCTION MANAGEMENT
A typical construction manager has a scope of
work that is limited to the
pre-construction/construction phase
A construction manager will supervise all
construction aspects of a project and will
typically participate in pre-construction
meetings, provide onsite supervision during
construction, and manage sub-contractors
They may also directly hold subcontractor
contracts, and is therefore liable for all of the
subcontractors’ work
UNIT 5 – CONSTRUCTION
MANAGEMENT
ROLES AND RESPONSIBILITIES OF A CM
Manage and oversee the day-to-day construction management of the
project
Prepares, supervises and approves the development of PEP (Project
Execution Plan) [from construction point of view] and its
implementation plus ensuring Lessons Learned are properly documented
through out the life of the project including Project Close-out
Manage the construction effort and be the construction representative
of the company with Client
To plan, develop and organize the construction effort to formulate the
most cost-effective plan to timely completion within budget and to
implement the execution of that plan
Responsible for implementation of the scope of work as related to
construction/ fabrication, pre-commissioning, load-out and offshore
installation hook-up and offshore pre-commissioning and commissioning
of the facilities in conformance with project specifications, Scope of
Work, and in accordance with the approved Project Schedule
UNIT 5 – CONSTRUCTION
MANAGEMENT
ROLES AND RESPONSIBILITIES OF A CM
Monitor and report to Project Manager / Sr
Construction Manager of project details, including
progress, risks and opportunities in a timely manner
Ensures all changes to specifications, work scope and
drawings are documented
Define clear roles & responsibilities and deliverable
requirements in terms of both scope and schedule to
all the team members
Review man-hours and duration forecasts to
completion for onshore construction and man-hours,
duration and manning forecasts for offshore hook-up
and offshore installation durations and resource
requirements
UNIT 5 – CONSTRUCTION
MANAGEMENT
ROLES AND RESPONSIBILITIES OF A CM
Monitor construction productivity and schedule
performance and investigate reasons for less
than satisfactory performance
Provide recommendations and institute measures
for improvement by modification to operating
procedures/work instructions
Adhere to Company Safety Standards and
promote safety culture among the ranks through
out the Company
Any other ad-hoc projects and duties as required
by the management
UNIT 5 – CONSTRUCTION
MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
HOPE BASED PROJECT MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
REALITY BASED PROJECT MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
CONSEQUENCES OF “MORE” AS A MISSION
STATEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
ALWAYS BEWARE OF “SURPRISES”
UNIT 5 – CONSTRUCTION
MANAGEMENT
SOMETIMES, PUSHING TOO HARD JUST
DOESN’T WORK OUT WELL
UNIT 5 – CONSTRUCTION
MANAGEMENT
PUBLIC STATEMENTS DON’T ALWAYS REFLECT
REALITY…..
UNIT 5 – CONSTRUCTION
MANAGEMENT
….. AND SO ARE A LOT OF MEETINGS!!!
UNIT 5 – CONSTRUCTION
MANAGEMENT
SUITABILITY OF AN ARCHITECT TO BE
PM/CM
UNIT 5 – CONSTRUCTION
MANAGEMENT
SUITABILITY OF AN ARCHITECT TO BE
PM/CM
Can an architect be a PM or CM?? Debate…
Itdepends on the size of the firm
Which is then determined by the structure and
organization of the firm or office
Followed by responsibilities
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROGRAMME EVALUATION REVIEW
TECHNIQUE
Event
Activity
Dummy network rules
Graphical guidelines for network
PERT Network
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT
Quotes from you and me
Chances of you getting a handsome job will improve if
you obtain a masters degree
Probably, collections jump in this month
Most probably, ERP implementation will be done by
September
Odds are greater for a better thesis review this
time???
Manchester United getting stronger in the BPL is not
impossible but is highly improbable
Defects from new machines are unlikely
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT
Each statement involves uncertainty
Chances = Odds = Likelihood = PROBABILITY
Real life is usually full of uncertainty
Almost nothing is for sure
In such situations, we cannot “PROVE”
anything
ALL WE CAN DO IS ASSIGN A PROBABILITY TO
EACH OF THE DIFFERENT POSSIBLE
OUTCOMES
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT
What are your chances of getting a handsome job
after masters?
How much you are confident about the collection
percentage rise this month?
What are your odds that your thesis review will be
better this time?
What is the possibility of Manchester United getting
stronger in the BPL??
What is the probable number of times the new
machine would churn out good production?
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT
PROBABILITY THEORY PROVIDES TOOLS TO
DECISION MAKERS TO QUANTIFY
UNCERTAINTIES
HOW ABOUT IN PROJECT MANAGEMENT??
TIME ESTIMATES TYPES
Deterministic Approach
Non-deterministic/Probabilistic Approach
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT
Assigning Probabilities
Classical Approach – assumes equally likely outcomes
(card games, dice games, tossing coins etc)
Relative Frequency Approach – uses relative
frequencies of past occurrences as probabilities
(decision problems in the process of management,
delay in delivery of product)
Subjective Approach – Guess based on past experience
or intuition (at higher level of managerial decisions
for important, specific and unique decisions)
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT
Relative Frequency Approach
Making use of relative experiences of the past
Example of attrition rate in an organization every
year coz of better prospects
Subjective Approach
Based on personal judgments
Uses individual’s experience and familiarity of the
facts
Example could be the share prices fluctuation over
the past few months
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT PROBABILITY APPROACH
Activity completion times are seldom known with
certainty
PERT is a technique that treats activity completion
times as “random” variables
Completion time estimates can be estimated using
the “Three Time Estimate Approach”
In this approach, three time estimates are required
for each activity (PROBABILISTIC APPROACH)
a = an optimistic time to perform the activity
m = the most likely time to perform the activity
b = a pessimistic time to perform the activity
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT PROBABILITY APPROACH
With three time estimates, the activity completion
time can be approximated by a “beta distribution”
Beta distribution can come in varied shapes:
UNIT 5 – CONSTRUCTION
MANAGEMENT
MEAN & SD FOR ACTIVITY COMPLETION
TIMES
The best estimate for the mean is a weighted average
of the three time estimates with weights 1/6, 4/6,
1/6 respectively on a, m and b
Since most of the area is with the range from a to b
(b-a) and since most of the area lies 3 standard
deviations on either sides of the mean, then the SD is
approximated by Range/6
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ASSUMPTIONS
Assumption 1
A critical path can be determined by using the mean
completion times for the activities.
The project mean completion time is determined
solely by the completion time of the activities on the
critical path.
Assumption 2
There are enough activities on the critical path so that
the distribution of the overall project completion time
can be approximated by the normal distribution.
Assumption 3
The time to complete one activity is independent of
the completion time of any other activity.
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT TIME ESTIMATES
Taking uncertainties into account…
Optimistic Time Estimate
Shortest possible time in which an activity can be completed,
under IDEAL CONDITIONS
Represents the time in which we could complete the activity if
everything went along perfectly with no problems or adverse
conditions
Better than normal conditions are assumed to prevail
Represented by to or a
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT TIME ESTIMATES
Taking uncertainties into account…
Pessimistic Time Estimate
Best guess of the max time that would be required to complete
the activity
Represents the time it might take to complete a particular
activity if everything went wrong and abnormal situations
prevail
Does not include possible effects of highly unusual
catastrophes such as EQ, floods, fires etc.
Represented by tp or b
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT TIME ESTIMATES
Taking uncertainties into account…
Most Likely Time Estimate
Also the most probable time – the time in the mind of the
estimator, representing the time the activity would most often
required if normal conditions prevail
Lies between the optimistic and pessimistic time estimates
Reflects a situation where conditions are normal, things are as
usual and there is nothing exciting
Represented by tm or m
UNIT 5 – CONSTRUCTION
MANAGEMENT
FREQUENCY DISTRIBUTION
Time estimates are difficult to ascertain – needs some
guidance based on experience or past/available
information
Plot a graph with the three time estimates
The way in which the time estimates behave!!!
What we get is a “unimodal curve” which is
symmetrical
Also called “normal curve”
Not necessary that all the times it may be “normal”
Some may have to “skew” due to which it is not
symmetrical
UNIT 5 – CONSTRUCTION
MANAGEMENT
FREQUENCY DISTRIBUTION
UNIT 5 – CONSTRUCTION
MANAGEMENT
FREQUENCY DISTRIBUTION
UNIT 5 – CONSTRUCTION
MANAGEMENT
FREQUENCY DISTRIBUTION
So, what do we infer???
“…A WIDE RANGE IN TIME ESTIMATES REPRESENTS
GREATER UNCERTAINTY AND HENCE LESS
CONFIDENCE IN OUR ABILITY TO CORRECTLY
ANTICIPATE THE ACTUAL TIME THAT THE
ACTIVITY WILL REQUIRE…”
UNIT 5 – CONSTRUCTION
MANAGEMENT
MEAN, VARIANCE AND STANDARD DEVIATION
Whatever be the form of the curve, the following
aspects of the characteristics of the distribution
are important:
Mean time or average time
Deviation
Variance
Standard Deviation
UNIT 5 – CONSTRUCTION
MANAGEMENT
MEAN, VARIANCE AND STANDARD DEVIATION
Mean: defined by the algebraic sum of time
durations taken by various jobs divided by the
number of jobs
Deviation: difference between the time under
consideration and the mean time. Difference
may be either positive or negative
UNIT 5 – CONSTRUCTION
MANAGEMENT
MEAN, VARIANCE AND STANDARD DEVIATION
Variance: is the mean of squared deviation.
Expressed by σ2
Variance is calculated in the following steps:
Obtain the mean of the distribution
Determine the deviation of each time from the mean
Find square of these individual deviations
Find the mean of the squared deviations
To note: deviations may be negative but their squares will
always be positive. Hence, VARIATION WILL ALWAYS BE
POSITIVE. Cannot have zero value unless each individual
deviation is zero
Variance is commonly used in statistics as a measure of
variability of distribution
UNIT 5 – CONSTRUCTION
MANAGEMENT
MEAN, VARIANCE AND STANDARD DEVIATION
Standard Deviation: the square root of the
variance. SD is denoted by σ
UNIT 5 – CONSTRUCTION
MANAGEMENT
NORMAL PROBABILITY DISTRIBUTION
UNIT 5 – CONSTRUCTION
MANAGEMENT
NORMAL PROBABILITY DISTRIBUTION
The mean of the NPD is denoted by µ
It can be proved that:
Approximately 68% of the values of ND lie within ±σ
from the average, where σ is the SD. Means that the
shaded area of the curve between x = µ - σ to x = µ +
σ is 68% of the total area
Approximately 95% of all the values lie within ± 2σ from
the average. All area of the curve between x = µ - 2σ to
x = µ + 2σ is 95% of the total area
Approximately 99.7% of all the values lie within ± 3σ
from the average. Means that the area of the curve
between x = µ - 3σ to x = µ + 3σ is 99.7%
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT NETWORKS
Before proceeding further;
Two basic elements of network are:
EVENT
ACTIVITY
EVENT - the commencement or completion of an
activity
EVENT – a specific definable accomplishment in a
project plan, recognizable @ a particular time
ACTIVITY – the actual performance of a task or the
work required to complete a specific event
ACTIVITY – a recognizable part of a work project
that requires time and resources for its completion
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS
An event has 3 basic properties
Either the start or completion of an activity
Represents a noteworthy, significant &
recognizable point in the project – act as control
points
An accomplishment occurring at an instantaneous
point of time but requiring no time or resources
itself
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS
An event MUST satisfy the following
requirements
Must be positive, specific, tangible & meaningful
to the project
Should be definitely distinguishable as a specific
point in time
Should be really understood by all concerned
with the project
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – REPRESENTATION
20 Activity B
Tail Event
Activity C
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – SPECIFYING THE EVENTS
HEAD EVENT
Marks the “ending/completion” of an activity
If a particular head event represents the
completion of the project – “final/end event”
Activity Activity
10 n
Activity B 10 n
Activity C Activity Q
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – SPECIFYING THE EVENTS
DUAL ROLE EVENTS
Most of the events serve dual function (head
event to some activity and tail event to another
activity)
All events except initial & final events are dual
role events
Activity A Activity B
11
Activity A
Activity P
Activity B 26
Activity Q
Activity C
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – SPECIFYING THE EVENTS
DUAL ROLE EVENTS
2
A D
B E
1 3 5
C
F
4
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – SPECIFYING THE EVENTS
Event 1: Initial event/tail event for A & B
Event 2: Head event for A/tail event for D
Event 3: Head event for B/tail event for C &
E
Event 4: Head event for C/tail event for F
Event 5: Head event for D,E,F/final or end
event
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – INTER-RELATIONSHIPS
Things to consider:
What event or events must be completed before a
particular event under consideration can be
started??
What event or events must follow the particular
event under consideration??
What activities can be accomplished
simultaneously??
The order or sequence relates various events as:
Successor Events (event that follows another event)
Predecessor Events (event that occurs before another
event)
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – INTER-RELATIONSHIPS
2
1 3 5
4
UNIT 5 – CONSTRUCTION
MANAGEMENT
EVENTS – INTER-RELATIONSHIPS
Events 2,3,4 & 5 are successor events to event 1
Events 2,3 & 4 are immediate successor events
to event 1
Event 5 is the immediate successor event to
events 2,3 & 4
Event 1,2,3 & 4 are predecessor events to event
5
Events 2,3 & 4 are immediate predecessor events
to event 5
UNIT 5 – CONSTRUCTION
MANAGEMENT
ACTIVITIES
A significant activity must be:
A positive, specific, tangible & meaningful effort
Such that the primary responsibility of effort can
be determined
Having a description understandable by all
concerned with the project
Having a time span
UNIT 5 – CONSTRUCTION
MANAGEMENT
ACTIVITIES – REPRESENTATION &
IDENTIFICATION
Activitiesare represented by simple “arrows”,
usually drawn from left to right
Length of arrow neither represents the
magnitude of the work involved nor the time
required for its completion
Not a vector quantity
Length of the arrow is chosen to suit the drafting
convenience
UNIT 5 – CONSTRUCTION
MANAGEMENT
ACTIVITIES – REPRESENTATION &
IDENTIFICATION
- In terms of events
they connect
Activity Representation
- By use of alphabets
for different
activities
2 3
Activity (2,3) - By writing actual
performance over
the arrow
10 11 Identification
Activity P
Install Machine
2 3 Description
[Activity (2,3)]
UNIT 5 – CONSTRUCTION
MANAGEMENT
ACTIVITIES – INTER-RELATIONSHIPS
Parallel Activities
Can be performed simultaneously & independently to
each other
Series Activities
Which are to be performed one after the other, in
succession
Can’t be performed independently to each other
A
Fix sanitary
12 fittings P Q
B Excavate Concrete
Foundations Foundations
Fix electric
fittings
PARALLEL SERIAL
UNIT 5 – CONSTRUCTION
MANAGEMENT
ACTIVITIES – INTER-RELATIONSHIPS
Predecessor Activities
Activities that are required to be performed before
another job/activity can begin
Activities that are required to be performed
immediately before another activity without an
intervening activity – IMMEDIATE PREDECESSOR
ACTIVITY
Successor Activities
Activities that can be performed after the
performance of other activity
Activities that immediately follow another activity –
IMMEDIATE SUCCESSOR ACTIVITY
UNIT 5 – CONSTRUCTION
MANAGEMENT
Activity Predecessor Successor
A - C*, E
B - D*, E
C A* E*
D B* E*
E A, C*, B, D* -
C
A
B D
UNIT 5 – CONSTRUCTION
MANAGEMENT
DUMMY ACTIVITY
Dummy – type of operation in the network which
neither requires any time nor any resources but
is merely a device to identify a dependence
among operations
Dummy – a connecting link for control purposes
or for maintaining uniqueness of activity
Represented by arrow – but since it’s not an
activity, it is represented by dashed arrows
UNIT 5 – CONSTRUCTION
MANAGEMENT
DUMMY – USES
Serve two purposes
Grammatical Purpose
Used to prevent 2 arrows having common beginning &
end points
Inconvenience results when the network is used for
computations (uniqueness is lost)
A A 3
1 2 1
B B
2
UNIT 5 – CONSTRUCTION
MANAGEMENT
DUMMY – USES
Serve two purposes
Logical Purpose
Used to give a clear logical representation in a
network having an activity common to two sets of
operations running parallel to each other
UNIT 5 – CONSTRUCTION
MANAGEMENT
NETWORK RULES
Initial node has only outgoing arrows – only single
initial node
Event can’t occur until all the activities leading to
it are completed
Event can’t occur twice (no looping back)
Must not be any dead end left except final node.
Final node has only incoming arrows. Only one final
node
No activity can start until its tail end event has
occurred
Arrow should represent singular situation
(uniqueness to be maintained)
UNIT 5 – CONSTRUCTION
MANAGEMENT
NETWORK RULES
UNIT 5 – CONSTRUCTION
MANAGEMENT
NETWORK RULES
Representation of the network should be such
that every activity is completed to reach the end
objective
Constraints and inter-dependencies should be
shown properly on the network by use of
appropriate dummies
Logic of network should always be maintained
Show time flow from left to right
UNIT 5 – CONSTRUCTION
MANAGEMENT
GRAPHICAL GUIDELINES FOR NETWORK
Arrows doesn’t indicate duration – arrows should
be of equal size wherever possible
Angle between arrows leaving or joining nodes
should be as large as possible so that more space
is available for addition of other relevant
information in the diagram
Straight arrows should be used
Arrows should normally not cross each other. If
crossing happens, length of arrow should be
broken to bridge over the other
UNIT 5 – CONSTRUCTION
MANAGEMENT
GRAPHICAL GUIDELINES FOR NETWORK
UNIT 5 – CONSTRUCTION
MANAGEMENT
NUMBERING THE EVENTS
Essential to number the events or node points
Numbering should be scientifically done so that they reflect
a logical sequence
Fulkerson Rules could be used in a big network
There is a single initial event in a network diagram. This initial
event will have arrows coming out of it and none entering it.
Number this initial event as 1
Neglect all the arrows emerging out of the initial event numbered
1. Doing so will apparently provide one or more new initial events
Number these apparently produced new initial events as 2,3,4 etc
Again neglect all emerging arrows from these numbered events,
this will created few more initial events
Follow Step 3
Continue this operation until the last event, which has no emerging
arrows, is numbered
UNIT 5 – CONSTRUCTION
MANAGEMENT
Other Rules
Tailevent must have a lower number than the
head event
For bigger networks, to avoid renumbering, enter
the number in multiples of 10
This process is known as “SKIP NUMBERING”
UNIT 5 – CONSTRUCTION
MANAGEMENT
Using Fulkerson rule, number the events of
the network as shown below:
UNIT 5 – CONSTRUCTION
MANAGEMENT
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
SLACK
The difference between the two times (TL & TE)of an
activity indicates the range between which the
occurrence time of an event can vary
Slack may be simply defined as the difference
between the latest allowable time and the earliest
expected time of an event
S = TL - TE
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
Earliest Event Time (TE)
After determining or estimating the time duration for an
activity, determine the time of occurrence of an event at
the “head of the activity”
Earliest time at which an event can occur
Time by which all the activities discharging into the event
under consideration are completed
Time of completion for each activity is known (t ij)
TjE = TiE + tij
TjE = earliest occurrence time for the tail event
TiE = earliest occurrence time for the head event
ij = activity under consideration
tij = time of completion of activity ij
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
Earliest Event Time (TE)
TE=0 TE=5 TE=12 TE=16
A B C
10 11 12 13
t=5 t=7 t=4
SLACK 30
TL=15 tE=4
tE=10
tE=7
TE=0 TE=5 TE=22 TE=27
10 20 50 60
tE=5 tE=12 tE=5
TL=0 TL=5 TL=22 TL=27
tE=8
TE=13 tE=8
40
TL=19
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
SLACK
Event No TE TL S = TL-TE
10 0 0 0
20 5 5 0
30 15 15 0
40 13 19 6
50 22 22 0
60 27 27 0
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS TE=15
SLACK 30
TL=15 tE=4
tE=10
tE=7
TE=0 TE=5 TE=22 TE=27
10 20 50 60
tE=5 tE=12 tE=5
TL=0 TL=5 TL=22 TL=27
tE=8
TE=13 tE=8
40
TL=19
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
SLACK
Positive Slack – when TL is more than TE for an event.
An indication that the event is ahead of schedule
Negative Slack – when the scheduled time Ts (and
hence TL is less than TE and its an indication that the
event is behind the schedule
Zero Slack – is obtained when TL = TE for an event. It
is an indication that it is an on schedule condition
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
Exercise 1
Determine the CP for the network:
20
tE=23.7
tE=9.8 tE=0
40 tE=10.2 60
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
TE=9.8
20
TL=12.3 tE=23.7
tE=9.8 tE=0
TE=0 TE=12.3 TE=30.3 TE=33.8 TE=42
40 tE=10.2 60
TL=12.8
TL=23
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
Event No TE TL S = TL-TE
10 0 0 0
20 9.8 12.3 2.5
30 12.3 12.3 0
40 11.7 12.8 1.1
50 30.3 30.3 0
60 21.9 23.0 1.1
70 33.8 33.8 0
80 42.0 42.0 0
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
Exercise 2
The expected time of completion (in days) for each activity of a
network is shown in. Determine the CP. It is given that the
scheduled completion time is 21 days.
2 6
1 5 7 9
3 4 8
UNIT 5 – CONSTRUCTION
MANAGEMENT
PERT ANALYSIS
TE=4 TE=10
2 tE=6
6
TL=10
TL=4
tE=3
TE=0 tE=4 TE=14 TE=22
TE=11
1 5 tE=3
7 tE=6
9
tE=6 TL=10 TL=13
TL=-1 tE=2 tE=3 TL=21
TE=5
tE=5
TE=8 TE=17 tE=5
3 tE=3
4 tE=6
8
TL=16
TL=8
TL=4
Event Earliest Event Time Latest Event Time Slack
No
1 - - 0 0 2 4 0 -1 -1
3 5 -1
2 1 4 4 4 6 6 4 4 0
3 1 5 5 5 4 3 5 4 -1
5 6 4
4 3 3 8 8 5 2 8 8 0
8 6 10
5 3 6 11 11 7 3 10 10 -1
4 2 10
6 2 6 10 10 7 3 10 10 0
7 5 3 14 14 8 3 13 13 -1
6 3 13 9 6 15
8 4 6 14 17 9 5 16 16 -1
7 3 17
9 7 6 20 20 - - 21 21 -1
8 5
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROBABILITY OF MEETING SCHEDULED DATE
After calculating TL, TE and critical path???
An unanswered question!!!
WHAT IS THE PROBABILITY OF MEETING THE
SCHEDULED TIME???
Apply probability theory to the network analysis
Things to discuss:
CP – time wise, the longest path along a number of activities
Three time estimates
Time estimates having beta distribution
Computation of tE assuming beta distribution
tE is such that there is a 50-50 completion chance
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROBABILITY OF MEETING SCHEDULED DATE
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROBABILITY OF MEETING SCHEDULED DATE
The probability of completion of the activity
within some other time Ts will be equal to the
area under the curve up to the vertical line thru
Ts divided by the total area of the curve
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROBABILITY OF MEETING SCHEDULED DATE
Summation of ΣtE of all activities along the CP is
equal to TE of the last event
tE of individual activities has random probability
distribution (β) and the variation of TE for the
project, as a whole has a ND for practical purposes
CENTRAL LIMIT THEOREM
This theorem states that if there are n activities, each
having its own β – distribution with means µ1, µ2, µ3….., µn
and SD σ1, σ2, σ3,….., σn respectively, then the distribution
of time for the project as a whole will be approximately be a
ND curve. ND curve will have a mean µ and variance σ2 given
by
µ = µ1+µ2+µ3+…..+µn
σ2 = σ21+σ22+σ23+…..+σ2n
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROBABILITY OF MEETING SCHEDULED DATE
Procedure
Properties of ND curve and the % probability
distribution table can be used only if the random
curve obtained from a particular network is reduced
to normalized form
Obtained by making TE value for the end event
coincide with the modal value of the ND curve
Following procedure is adopted for determining the
probability of meeting the scheduled completion
time:
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROBABILITY OF MEETING SCHEDULED DATE
Procedure
Determinethe SD (σ) appropriate to the CP for the
network, using the relations
σ = √Sum of variances along the CP (or)
σ = √Σσ2ij, where σ2ij = variance for activity i-j along the CP
= (tijp – tijo/6)2
Knowing the scheduled completion time (ts) and EET
of completion (TE), find the time distance TS- TE and
express it in terms of probability factor Z by the
relation:
Z = (TS - TE)/σ or Z = (TS - TE )/ √Σσ2ij
UNIT 5 – CONSTRUCTION
MANAGEMENT
PROBABILITY OF MEETING SCHEDULED DATE
Procedure
The probability factor (Z) is the same as
normal deviate of table
When Z is positive (TS to the right of TE) the chances of
completing the project on time are more than 50%
When Z is zero (TS coinciding with TE), the chances of
completing the project on time is 50-50
When Z is negative (TS to the left of TE), the chances
of completing the project on time is less than 50%
STANDARD NORMAL DISTRIBUTION FUNCTION
UNIT 5 – CONSTRUCTION
MANAGEMENT
EXERCISES
A Project is expected to take 15 months along the CP, having a
SD of 3 months. What is the probability of completing the project
within (a) 15 months (b) 18 months and (c) 12 months?
TE = 15 months & σ = 3 months
(a) Given, Ts = 15months
Z = (15-15)/3 = 0
From table, for Z=0, probability = 50%
(b) Given, Ts = 18months
Z = (18-15)/3 = 1
From table, for Z=1, probability = 84.13%
(c) Given, Ts = 12months
Z = (12-15)/3 = -1
From table, for Z=-1, probability = 15.87%
UNIT 5 – CONSTRUCTION
MANAGEMENT
EXERCISES
PERT calculations yield a project length of 50 weeks, with a variance of
16. Within how many weeks would you expect the project to be
completed with probability of (a) 95% (b) 75% and (c) 40%?
SD σ = √16 = 4
For 95% probability Z≈ 1.65, Now Z = (TS - TE)/σ
TS = σZ + TE
= 4x1.65 + 50 = 56.6 ≈ 57 Weeks
For 75% probability Z≈ 0.69
Ts = σZ + TE
= 4x0.69 + 50 = 52.76 ≈ 53 Weeks
For 40% probability Z≈ - 0.25
Ts = σZ + TE
= 4x (-0.25) + 50 = 49 Weeks
UNIT 5 – CONSTRUCTION
MANAGEMENT
Linear Interpolation
4-10-22
1 4 5
5-8
-1 7
-16 2-5-8
7
4-
3
UNIT 5 – CONSTRUCTION
MANAGEMENT
Solution
Determine the expected time of completion (tE) an variance σ2 for
each activity using the relations
1 - - 0 0 2 10 0 0 0
3 9 2
2 1 10 10 10 4 9 10 10 0
5 7 23
3 1 9 9 9 4 8 11 11 2
5 5 25
4 2 9 19 19 5 11 19 19 0
3 8 17
5 2 7 17 30 - - 30 30 0
3 5 1
4 11 30
CP = 1-2-4-5 = 30 days
UNIT 5 – CONSTRUCTION
MANAGEMENT
Solution
TE=10
2 tE= tE=7
E= 10 9
t TL=10
TE=0 TE=19 TE=30
tE=11
1 4 5
tE=
9
tE=5
TL=0 TL=19 TL=30
TE=9
E=8
t
3
TL=11
UNIT 5 – CONSTRUCTION
MANAGEMENT
Solution
Now, deviation along the CP is given by σ = √Σσ2ij
Where Σσ2ij = sum of variances along the CP
= σ21-2 + σ22-4 +σ24-5
= 4 + 9 + 9 = 22
σ = √Σσ2ij = √22 = 4.69
3-5-13 2-4-6
3 0-
7 8
0 -0
0
-2
2-3-10
11
8-
17
3-7-
-20
5
UNIT 5 – CONSTRUCTION
MANAGEMENT
Solution
Activity to tL tp tE σ2
1-2 2 5 8 5 1
2-3 8 11 20 12 4
3-4 0 0 0 0 0
2-4 4 7 16 8 4
2-5 4 9 20 10 7.11
4-6 7 10 13 10 1
5-6 3 7 17 8 5.44
3-7 3 5 13 6 2.78
6-7 2 3 10 4 1.77
7-8 2 4 6 4 0.44
Event Earliest Event Time Latest Event Time Slack
No
1 - - 0 0 2 5 0 0 0
2 1 5 5 5 3 12 5 5 0
4 8 9
5 10 9
3 2 12 17 17 7 6 25 17 0
4 0 17
4 2 8 13 17 6 10 17 17 0
3 0 17
5 2 10 15 15 6 8 19 19 4
6 4 10 27 27 7 4 27 27 0
5 8 23
7 3 6 23 31 8 4 31 31 0
6 4 31
8 7 4 35 35 - - 35 35 0
CP = 1-2-3-4-6-7-8 = 35 days
UNIT 5 – CONSTRUCTION
MANAGEMENT
Solution
TE=31
TE=35
TE=17
3-5-13 2-4-6
3 0-
7 8
0 -0
0
TL=31
-2
2-3-10
TL=35
11
TE=15
TL=19
UNIT 5 – CONSTRUCTION
MANAGEMENT
Solution
Now, deviation along the CP is given by σ = √Σσ2ij
Where Σσ2ij = sum of variances along the CP
= σ21-2 + σ22-3 +σ23-4 + σ24-6 + σ26-7 +σ27-8
= 1+4+0+7.11+1.77+0.44 = 14.32
σ = √Σσ2ij = √14.32 = 3.78
Ts = σZ + TE
= (3.78 x 1.65) + 35 = 41.2 days
UNIT 5 – CONSTRUCTION
MANAGEMENT
A project consists of 16 activities having their predecessor
relationship as follows:
A is the first activity of the project
B,C & D follow A and can be done concurrently
E & G cannot begin until C is completed and can be performed
simultaneously
F is the immediate successor to activities B & E
H & K run in parallel and both succeed G
L succeeds F & H
I & J are immediate successor activities to activity D
M & N are immediate successor to I & K. However, both M & N can
be performed concurrently
Activities O & P are the last activities. Activity O is the immediate
successor to N & L. Activity P is the immediate successor to M & J
DRAW THE NETWORK AND NUMBER THE EVENTS
UNIT 5 – CONSTRUCTION
MANAGEMENT
A project consists of eight activities M, N, O, P, Q, R, S &
T. Draw the network and number the events if,
Activities M,N & Q can start concurrently
Activities O & P are concurrent and depend on the completion of
both M & N
Activities R & S are concurrent and depend on the completion of O
Activity T depends upon the completion of P, Q & R
A project consists of eight events having predecessor
relationships as under. Draw the network.
Event Predecessor Event Predecessor
1 - 5 3,4
2 1 6 3,5
3 1 7 6
4 2,3 8 4,7