Professional Documents
Culture Documents
Realistic Look at Health of the Organization Shows clear successes & failures
1 Velocity
2 Commitment Reliability
3 Capacity Utilization
5 Scope Change
6 Defect Leakage
7 Backlog Health
1 Velocity
st
Unit of Velocity is Story Points
Target Actual
Story Points = 15 Development + Testing + Acceptance Testing Story Points = 12
1 Velocity
st
Unit of Avg. Velocity is Story Points
100 %
111 %
115 %
107 %
Velocity Trend
96 %
38 % Method 1
26 29 34 10 25 30 28
Avg.
Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Sprint 6
Velocity
130 %
115 %
111 % 107 %
96 %
Method 2
38 %
29 34 10 25 30 28
38 % Method 3
26 29 34 10 25 30 28 Step 1:
Avg.
Define Upper Limit = 40 %
Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Sprint 6
Velocity Define Lower Limit = 15 %
Step 2:
If we take 26 S.P. as average i.e. 100%
Upper Limit
Therefore,
Lower Limit
Upper Limit = 140 %
Average Velocity Lower Limit = 85 %
Velocity Trend
Step 3:
Draw Velocity Trend Bar Chart using limits
Velocity Trend
Key Highlights
120%
100 % 100 %
100% 93 %
83 %
80%
62 % 67 %
60%
40%
20%
0%
Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Sprint 6
Commitment Reliability Trend
Applying RAG Status
120%
100 % 100 %
100% 93 %
83 %
80% 67 %
62 % 0% – 80% = Red
60% 81% - 95% = Amber
40% 96% - 100% = Green
20%
0%
Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Sprint 6
3 Capacity Utilization
rd
Unit of Capacity Utilization is Efforts (We will use HOURS here)
Sprint 1 (2-4 Weeks) Available = 220 Hrs Committed = 130 Hrs CU = 59%
Sprint 2 (2-4 Weeks) Available = 240 Hrs Committed = 190 Hrs CU = 79%
Committed /
Sprint 3 (2-4 Weeks) Available = 280 Hrs Committed = 140 Hrs CU = 50% Available
Sprint 4 (2-4 Weeks) Available = 230 Hrs Committed = 200 Hrs CU = 87% * 100
Sprint 5 (2-4 Weeks) Available = 243 Hrs Committed = 221 Hrs CU = 91%
Sprint 6 (2-4 Weeks) Available = 226 Hrs Committed = 220 Hrs CU = 97%
Capacity Utilization Trend
120%
97 %
100% 87 % 91 %
79 %
80%
59 %
60% 50 %
40%
20%
0%
Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Sprint 6
Capacity Utilization Trend
Applying RAG Status
120%
97 %
100% 87 % 91 %
79 %
80%
0% – 60% = Red
59 %
60% 50 % 61% - 85% = Amber
40% 86% - 100% = Green
20%
0%
Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Sprint 6
Capacity Utilization- Factors
4 th Effort Estimation Variance
Unit of Effort Estimation Variance is Efforts (We will use HOURS here)
Sprint 4 (2-4 Weeks) Estimated = 200 Hrs Actual = 189 Hrs Variance = 6% Under-
Estimation
A-E/
Sprint 5 (2-4 Weeks) Estimated = 221 Hrs Actual = 178 Hrs Variance = 19% E
Sprint 6 (2-4 Weeks) Estimated = 220 Hrs Actual = 215 Hrs Variance = 2%
* 100
Effort Estimation Variance Trend
Hours
250
200
150
100
50
Sprint 1 (2-4 Weeks) Committed = 29 S.P. Added = 0 S.P. Removed = 10 S.P. SC = 34%
Sprint 2 (2-4 Weeks) Committed = 34 S.P. Added = 0 S.P. Removed = 0 S.P. SC = 0% Decreased Scope
Sprint 4 (2-4 Weeks) Committed = 30 S.P. Added = 0 S.P. Removed = 15 S.P. SC = 50% Increased Scope
Sprint 5 (2-4 Weeks) Committed = 45 S.P. Added = 0 S.P. Removed = 0 S.P. SC = 0% (A / C) * 100
0%
34%
50%
Health Slab:
Less than Average Velocity
52
Health Slab:
Meets Average Velocity
52
Health Slab:
Meets twice of Average Velocity
52
Health Slab:
Meets thrice or more of Average Velocity
Why Backlog Refinement?
Emergent Emergent
.
Backlog Refinement
Includes:
Adding detail to high-priority backlog items for greater comprehension
Ordering backlog items to deliver the most impact over the next sprint
Thank You
For Your Attention !