Temporary Electrical installations are required to be
designed and erected to be in use for a short period of time for various purposes like green field project, construction site, exhibitions, public functions etc.
These are connected to supply source in open ground
which are not protected from environmental hazards as compared to permanent structures.
In such installations, major risk of Fire due to short circuit
and shock due to exposure to live wires is involved. Classification on the basis of duration of installation 1. Temporary installations for duration not exceeding 6 months. Outdoor installations open to sky or partially covered, Erected in the vicinity of construction site for lighting and motive load
2. Temporary installations for duration not exceeding 45
days. Includes fairly large loads such as for exhibitions, Fairs etc.
3. Temporary installations for duration not exceeding 7
days for week long Public function or for Festivals or any other reason.
4. Temporary installations for duration not exceeding 24
hours for purposes of marriages, reception, religious / public function, celebraions etc. General requirements for Temporary Electrical installation
1. Substation
2. Power distribution
3. Control of circuits
4. Sub circuits
5. Earthing
6. Protection and Safety
1. Substation • Where the load requirement is large and Power supply authority does not have net work in the vicinity of temporary installation, then it would be necessary to establish a temporary Sub station where the switch and transformer can be installed.
• Sub station site should be as close to load centre as
possible
• If overhead line is laid, then the supporting poles,
conductors, materials of the line, insulation and the method of stringing the conductors and the mechanical strength of the line should conform to the relevant provisions of IS : 5613 (Part 1/sec1) -1970 & IS: 5613(Part1/ sec2) – 1971 • For the supply voltage above 650 V, Enclosure to install the switch gear and the metering arrangements shall be erected.
• The sub station surrounding area should be kept clean
of grass, weeds and any combustible/ flammable material.
• Only authorized person should carry out any work in
substation. 2. Power Distribution
A unit containing the main control gear and principal
protective device should be provided at the Origin of each installation
Main switch should be installed in an enclosure as
near to metering point as possible
The enclosure should be such that the equipment
inside should not be affected by environmental conditions
Emergency switch should be provided on the supply
line The connection from the main switch to point of supply should be through armored cable and termination should be protected from rain water
For Emergency access, the main switch should be
located at a height not exceeding 1.5 mts.
The cable should be laid either underground or
overhead
If the cable is laid underground, the same safety
precautions should be taken as required for permanent power connection If the cable passes below a passage, it should be laid through whole or split pipes to protect the cable from movements on the passage / road
In case of overhead cable laying, the cable
should be supported on rigid poles or fixed to the wall using cleat and saddle arrangement of proper size.
The height of the cable should be more than 2
mts when run inside the compound and 5 mts when laid along the road A separate earthing should be established inside the installation premises
While selecting the equipment and cables, the
rating should be decided on the basis of load and environmental conditions
The incoming supply point should be placed at
one end of the site so that it is not accessible to general public 3. Control of circuits
Everysupply and distribution units should have
a device on the incoming cable for switching and isolating
Themain switch should be protected from
water ingress.
The incoming and outgoing cables of main
switch should be supported firmly The main switch should be installed on a firm and vertical surface to withstand mechanical vibrations
Theventilation in main switch room should be
adequate
Only authorized persons shall enter main switch room. 4. Sub circuit
Theoutgoing end of the main switch should be
connected to Bus bar of required size
Varioussub circuits should be connected to the
Bus bar through double or triple pole switches
Theswitches should be rigidly supported at a
height of 1 to 2 mts from the floor There should be minimum clear distance of 60 mm between the switches
Theout going wires from the sub circuits
should be properly cleated. Any wire above 2 mts. in length should have guide wire support. 5.Earthing • There should be provision of double earthing for all appliances and equipment in temporary installation
• If armored cables are used, the armoring should be
connected to earthing of power supply authority
• An independent earth continuity wire should be used
for local earthing.
• The earth electrode should be buried near supply
intake point for local earthing Contd… • The earth continuity wire should be single core insulated wire.
• It should be connected to local earth plate and taken
along the cable connecting supply intake point and main switch
• The sub distribution boards should be connected to
earth continuity wire and in turn terminated to a common bus. 6. Protection & Safety • Protection against overload, short circuits and earth leakage should be provided through protective devices.
• Circuit protection devices are designed to
automatically limit or shut off the flow of electricity in the event of over load, ground-fault or short circuit conditions.
• Fuses, circuit breakers, and ground-fault circuit
interrupters are three known examples of such devices Never remove a grounding device from any electrical source, tool, or equipment.
Never remove the ground prong from an electrical
cord or device of any kind.
Never by-pass grounding or circuit breaker protection
at any time.
If you find any of the above have occurred, repair and
/ or report immediately. • Fuses and circuit-breakers are over-current devices that are placed in circuits to monitor the amount of current that the circuit will carry.
• They automatically open or break the circuit when the
amount of current flow becomes excessive.
• Fuses are designed to melt when more current than
the rated value flows through them.
• Circuit breakers, on the other hand, are designed to
trip / open the circuit by electro-mechanical means. Fuses and circuit breakers are intended primarily for the protection of conductors and equipment.
They prevent over-heating of wires and
components that might otherwise create hazards for operators.
They also open the circuit under certain
ground-fault conditions. • The ground-fault circuit interrupter, or GFCI, is designed to shutoff electric power within as little as 1/40 of a second.
• It works by comparing the amount of current
going to electric equipment against the return current from the equipment through return path.
• If the current difference exceeds 6 milli amperes
the GFCI interrupts the current quickly enough to prevent electrocution.
• The GFCI is used in high-risk areas such as wet
locations and construction sites. • It should be ensured that there is no risk of electric shock or fire due to temporary installation
The flammable material should not be stored near
electrical equipments
The power supply panel should be readily accessible
to allow power shutdown
Proper protective equipment should be worn and
used. Suitable Fire extinguishers should be kept at supply intake point and near the main switch
ELCB (Earth Leakage Circuit Breaker) of
proper Rating should be used to prevent Electrical shock hazard
No Cable should remain immersed in water
Regular Testing of Electrical Equipment should be carried out to detect defects
Work Permit System should be introduced and
followed strictly
Do not allow people to work on live lines or live
Feeders Causes of Electrical Accidents
1. Unprotected temporary Electric Power
Connection
2. Open Distribution Boards/Switch Boards
3. Switches, Fuses and Cutouts of improper
rating.
4. Badly insulated Cables laid on the Ground
Contd…
5. Damaged Cables Lying in water
6. Damage to underground cables while digging
or excavating
7. No proper Earthing to Electrical Equipment
8. Overloading the Feeders
Contd….
9. Instead of using three pin plugs, jamming of
of cables in the sockets by make shift arrangements such as matchsticks
10. Working on Live Lines or on Live Feeders
11. Use of Improper Tools
12. No Usage of Personal Protective Equipment
Contd…. 13. Unqualified/ Unauthorised person working on Electrical Equipment
14. Short Circuits
15. Improper Welding Machine connection and
improper Welding cable
16. Flouting of all Electrical Safety Rules
Prevention of Electrical Accidents
1. Electrical System in the plant should be
properly designed and regularly inspected by competent Engineer 2. Low Voltage System should be used where ever possible 3. The Electrical cables should be laid properly and should be hung overhead preferably 4. Proper Junction Boxes and Distribution Boards should be provided at every floor 6. Switches, Fuses and Cutouts should be of proper Rating 7. Three Pin Plug Socket should be used with proper Earth connection 8. Loose wires should not be pushed into sockets with matchsticks 9. Ordinary PVC Cables should not be used in the construction site instead use armoured cables 10. Do not overload the Feeders 11. Double Earthing should be provided to all Electrical Equipment 12. Do not allow people to work on live lines or live Feeders 13. Ensure that Proper tools and Personal Protective Equipment are provided and they are used 14. Regular Testing of Electrical Equipment should be carried out to detect defects 15. Welding Machine connection should be done properly using lugs 16. Inspect cables and wiring regularly to prevent short circuits