works by
CRB & CEO
Progress of Signalling works (As on 1st Oct 22)
LC gate Interlocking 6 7
BPAC 4 4
Financial Progress for year 2022-23
(Rs in Cr)
Status of
S. No. Division No of IBS Sanctioned Commissioned Status of Tender
Building
KIR: 06 Stations
Harischandrapur, Old Malda on 03.04.22,
1 KIR 6 Kumarganj on 22.05.22 by O/L, 0
Bathnaha on 13.06.22 by CON,
RQJ by O/L on 11.07.22 & ICY by CON.
RNY: 04 station
3 RNY 4 0
Jogighopa on 28.07.22,
Bongaigaon, Chaprakata & Bijni on 30.08.22 by CON.
LMG: 05 stations
4 LMG 5 0
Chongajan by CON, Moinar Bond (Siemens Mark-I to Mark-II) by O/L
Rani Gaidinliu, Thingou & Khonsang by CON.
15
Position of IBS work targeted in FY 2022-23
No of IBS No of IBS
No of IBS No of balance IBS to Status of Detailed Status of Status of
S. No. Rly Target for 2022-23 commissioned commissioned
Sanctioned be commissioned Estimate Tender Building
against target beyond target
1 NFR 9 9 0 0 9 9 0 0
Status of
S. No. Division No of IBS Sanctioned Target for 2022-23 Status of Tender
Building
1 KIR 0 0 0 0
Technical bid opened on 30.08.22. Financial bid (66% above, single offer)
4 LMG 11 2 opened on 27.10.22. Tender under evaluation at HQ. 0