Professional Documents
Culture Documents
Terry Wipf
Iowa State University
(on behalf of Iowa DOT)
Mackey Bridge
Boone County
Overview
Design by Iowa DOT
– First concerted ABC concept
3 span pre-stressed girder
– 47’-5, 56’-6, 47’-5 Spans
– 33’-2 width overall
Precast substructure and superstructure elements
Challenge
Steep learning curve
– First use in Iowa – no designer, contractor,
fabricator or inspector experience
AASHTO Standard Specification
– limited guidance on full depth post-tensioned deck
panels
Limited literature and national experience with this
style of deck system
The project was let with short lead time for the
contractor and fabricator
Goals of Monitoring Program
Evaluate
– Structural performance of precast concrete
bridge elements in the laboratory
– Constructability of connections
– Handling of components
Monitor and evaluate structural
performance of field bridge during and
after construction
Substructure
35
30
Height, in.
25
20
15
10
0
-40.00 -20.00 0.00 20.00 40.00 60.00 80.00
Microstrain
Lessons Learned
Council Bluffs, IA
Overview
Reconstruct the 24th Street Interchange over I-
80 / I-29
Replace existing structure with a Two-Span
CWPG 354’ x 106’ bridge
Use staged construction to maintain one-lane
traffic in each direction plus a turning lane
Use ABC techniques
24 Street - Highways for Life
th
Evaluate
– Constructability of connections
– Handling of components
Monitor and evaluate structural
performance of field bridge during and
after construction
Full-Depth Precast Deck Panels
Deck is made up of two panels
Pre-tensioned and post-tensioned
concrete deck panels
Cast-in-place transverse joint between
panels
Cast-in-place longitudinal joint that will tie
the two phases of construction
PCC overlay over precast deck panels
Precast Deck Panel
Plan View
Deck Panels
Pre-Construction Testing
Investigation of Shear Stud Installation
and Testing
Evaluation of Concrete Consolidation in
Shear Stud Pocket and Beam Haunch
Evaluation of Joint Shear Transfer
End of Floor
Section
Longitudinal
End of Floor Section Closure Pour
Shear Stud Pocket / Haunch Pour Testing
Joint Tests
Post-Construction Testing
Diagnostic load tests
Deck panel joint performance
Long term structural performance
P/T and pretension reinforcement
corrosion
Lessons Learned
Collaboration with the industry prior to design
was very important for the success of this
project
Preconstruction testing program to evaluate
selected items and this was very helpful
Experience gained with many innovations
introduced
Lab testing to validate design assumptions
prior to construction will reduce risk
Precast Bridge Approach
Demonstration Project
O’Brien County
Iowa 60
Why Precast Concrete Panels?
Expedited construction
– Overnight placement
– Reduced user cost
– Almost immediate exposure to traffic
Controlled Fabrication Conditions
– Adequate curing, reduced curling
PPCP Bridge Approaches
– Rapid replacement of bridge approaches
Challenge
How take skew into account
How to implement a precast approach
– Use for ABC repair (time)
Deteriorated approach slabs
– Post tensioning
– Grouting
– Tie transverse in keyways without match cast
– Gain Industry experience
– How forces from precast tied to integral abutment
would affect bridge
Demonstration Project
Precast Prestressed Bridge Approach Slabs
– ~77 ft at either end of a skewed bridge
– Tied to integral bridge abutment
2-way Post-Tensioning
Partial-width panels (lane-by-lane construction)
Installed over crushed aggregate base graded
to crown
Panels: 14 ft x 20 ft x 12 in.
Precast Approach Slab Layout
25.0' 3 spa. @ 20.0'
2 spa. @ 14'
6 spa. @ 2.0'
Longitudinal PT (1 - 0.6" dia. strands)
Transverse PT (1 - 0.6" dia. strands)
The Companion Bridges
Southbound Bridge Schematic
Expansion
Approach Slab Integral Abutment
Joint
Single Row of
HP10x57 Piles
Polyethylene Sheet
Integral
Connection
Goals of Monitoring Program
Verify structural performance of PPCP as
bridge approach pavement
– Joint openings
– Bridge movements
– Girder flexural behavior
– Pile axial/flexural behavior
Provide useful comparison with adjacent
CIP bridge approach pavement
Instrumentation Plan
NB Bridge
40
20
0
(me)
L oad S train
-20
-40
-60
-80
-100
4/13 5/11 6/8 7/6 8/3 8/31 9/28 10/26 11/23 12/21 1/18 2/15 3/14 4/11
Time
Monitoring Lessons Learned
The two approaches impacted the
bridges in different ways
The integral connection between both
types of approaches appear to be
functioning well
A force exists at the joint between the
approach and the mainline pavement
ABC Lessons Learned
Significant experience (Precast/PT)
The forces developed in the slab and
bridge are large enough that they need to
be considered in the design process
Can take next step for ABC repair under
staged construction
Precast Bridge Approach
Demonstration Project
Bremer County
U.S. 63
Project Details
Precast system shown to be feasible from
O’Brien Project
ABC schedule
– 12 hr closures (NB daytime; SB night time)
– One traffic lane w/ shoulder for staged
construction
Bremer County Project
Panel Layout
12 ft Roadway panel width
3’-10 and 7’-10 shoulder panel width
1’-10 Cast-in-place shoulder at gutterline
match w/ existing pavement and wing
Approach length ~ 24 ft from bridge at
roadway centerline
Pavement tied to bridge abutment
EF joint precast in panels and next to
existing pavement for expansion
Individual Panel Description
12 inches thick, 9.5 inches at abut.
Skewed at abutment ~ 2.5 degrees
fc = 5000 psi
Epoxy coated rebar (mild reinforcing)
Mechanical connection with 3” x 12”
grouted pockets (1’-0 spacing)
Longitudinal Section
Expansion
Precast Panel
Joint
Polyethylene Sheet
Existing Integral
Pavement
Connection
Longitudinal Joint at Centerline
Project Construction