METHOD STATEMENT

MECHANICAL & ELECTRICAL WORKS

PT. PEMBANGUNAN PERUMAHAN (PERSERO)

TANGGUH LNG PROJECT BD-1 BUILDING WORKS


Document No. :

Expired date :

Revise No / date :

Date for review :

METHOD STATEMENT FOR MECHANICAL & ELECTRICAL

Revised :

Cause of Revision : Disposition :

APPROVED BY :
Dept. Engineering Operation Project Manager

Signature

Name
Date

Distribution to :
1.
2.
3.
METHOD INSTALLATION
FIRE ALARM

MATERIAL
 Main equipment of fire alarm
 Detector of speator Floor Slab
 Installation cable PVC Conduit
 Conduit
 Terminal box Tee Doos
 Supporting material

Flexible Conduit
EQUIPMENT
Ducting
Tongs, Screwdriver etc
Water pass
Key pas
Distance Variable

SCOPE OF WORK

 Installation of conduit
Ceiling Grill Supply
 Installation of fire alarm cable

 Installation of cable rack


 Installation of terminal box

 Installation of detector

 Installation of main equipment Alarm Detector

STAGES OF DETECTOR INSTALLATION

 Marking plafond using chalks

 Pull installation cable out of plafond


 Install detector & connect to its installation cable

 Strengthening detector using screw


 Protect detector from paint dirt & dust
Diagram Block of Fire
Alarm

Main Equipment of Fire Alarm


ROR
Detector

Annunciation

TBF
Smoto
Data MDF Detector
zone

RUANG KONTROL

TBF

Electronic Shaft
Power Master Heat
Suppl Control Fire Detector
y Alarm

Fixed
TBF Temp
Detector

Sprinkl Pump
er Signa
Signal l
grounding

Flow Hydrant
Switch Panel
INSTALLATION METHOD
OF
FIRE FIGHTING
A. MATERIAL
- Pums
- Valve
- Pipe Gip/ black steel
- Hydrant box & Acc
- Hydrant Pillar
- Siamese Connection
- Head Sprinkler
- Fire Extinguisher
- Supporting material

B. EQUIPMENT
- machine weld
- hand gear
- settle drill & Hand drill
- tactol
- Pipe toy, Pass toy, etc

C. SEQUENCE OF IMPLEMENTATION
C.1. Installation of Indoor Pipe
-Marking pipe stream conform to shop drawing and co-ordinate with stream
lines. Other works such as AC pipe stream,
Plumbing, Tray Cable etc.
-Cut pipe conform to dimension required.
-Cover pipe Black Steel (GIP if it will be painted all over the pipe) with base
paint (zinc chromatee).
-After base painted cover the pipe with red paint.
-Install both hanger and support pipe conform to marking result.
-Install pipe GIP/Black Steel conform to dimension on shop drawing,
connecting pipe diameter less than
2,5 inch with drat and diameter 2,5 inch or more with weld.
-Use rope & water pass to measure the straightness of pipe.
-Do painting work for pipe connection area.
-Do pipe pressure test with pressure conform to specification available.
-For installation of fire sprinkler dropper pipe must be co-ordinate prior to
plafond work (architectural)
and other ME work.
-Do pressure test once more if dropper pipe has already been installed.
C.2. Installation of Outdoor Pipe

-Marking stream pipe.


-Dig pipe stream at depth fit to its
elevation.
-Connect to pipe upon excavation.
-Cover pipe with zinc chromate.
-Do pressure test of pipe with
pressure conform to
technical specification available.
-Give sand layer on excavation base.
-Put down the pipe into excavation.
-Lfires excavation with sand.
-Fill the excavation.

C.3. Installation of Indoor


Hydrant Box
-Marking the location of hydrant box placing at height over 150 cm.
-Make hole at brick layer conform to marking dimension.
-Install hydrant box on its position.
-Install installation pipe direct to hydrant box.
-Protect hydrant box from dirt and paint.
-Hydrant accessories is installed after the condition of project is safe.

C.4. Installation of Outdoor Hydrant Box, Pillar & Siamese Connection

HYDRANT BOX
-Marking the location of hydrant box placing.
-Make the foundation of hydrant box
-Install hydrant box on its position.
-Protect hydrant box from dirt and paint.
-Accessories hydrant is installed after the condition of project is safe.

HYDRANT PILLAR
-Marking the location of hydrant pillar placing & siamese connection
-Dig the location of marking and pipe stream direct to its position.
-Connect installation pipe direct to the location of both hydrant pillar and
siamese connection.
-Install hydrant pillar and siamese connection.
C.5. Installation of Head Sprinkler

-Installation of dropper is done if plafond has already been installed


-Use seal tape for connecting sprinkler to dropper pipe.
-Protect head sprinkler from dirt and paint.

C.6. Installation of Pump


-Marking the location of pump placing.
-Make the foundation pump, notice the
straightness and the
smoothness of the foundation.
-Install installation pump room piping first.
-Install pumps and their valves.
-Connect to power installation to pump.
-Adjust pressure of pump switch as follows :
- Joctoy Pump On position 8,5 Bar
Off position 9 Bar
- Electric Pump On position 7 Bar
Off manual
- Diesel Pump On position 6 Bar
Off manual
-Do running test pump.

C.7. Test of Fire


Fighting
HYDRANT TEST
-Close all of faucet on hydrant box
and hydrant pillar.
-Prepare fire extinguish slang
conform to its dimension.
-Position pump adjustment on auto
-Open valve on hydrant box and
hydrant pillar

TEST SPRINKLER
-Open valve on installation of fire
sprinkler.
-Prepare valve cover operator on
floor/zone which will be tested.
-Position pump adjustment on auto.
-Heat the head sprinkler with fire.
-After sprinkler is broton, and test is
defined OK, close immediately valve on
installation direct to test area
-Replace head sprinkler which is broton
Diagram Block of Fire
Hydrant
Air Vent
Floor - floor To MCFA

Flow
Switch
Head SprinklerHead Sprinkler Hydrant Box

Field

Mechanical Shaft
Hydrant Siamese Hydrant
Pillar Conection Box

Ruang Pump

Gate Valve

Diesel
Pump
Che
ck
Valv Electric Pump
e

Grou
Joctoy
nd
Pump
tank

Bell Alarm Safe


ty
valv
e
Deep PDAM
Well
INSTALLATION METHOD
OF GROUNDING PANEL
A. MATERIAL
- Cable BC
- Copper Plate
- Isolator
- Copper Rod
- Screws

B. EQUIPMENT
- Hand Drill
- Tongs, Screwdriver etc
- Iron saw machine

C. SEQUENCE OF IMPLEMENTATION

with copper plate

- Marking stream of grounding, space between isolator 50 cm &


height 30 cm from floor
- Install isolator, use dynabolt 8 mm

- Install copper plate around panel room until grounding control basin

- Connect among copper plate with jointing from copper material

with cable BC

- Marking stream of grounding, space between isolator 50 cm & height 30 cm from


- Install isolator, use dynabolt 8 mm

- Install cable BC around panel room until grounding control basin

- Connect among BC with jointing from copper material


GROUNDING OF PANEL ROOM

panel TM
trafo

BRC
wire

LVMDP

Grounding
BC / Copper Plate Markan
INSTALLATION
METHOD OF
CLEAN WATER
INSTALLATION
A. Material
- Pump – pump
- Valve
- Gyp Pipe / ABS
- Supporting material & fitting

B. Equipment
- weld machine
- hand gear
- settle drill & hand drill
- tackle
- toy of pipe, pass toy, etc

C. Sequence of Impglueentation

C.1. Installation of Indoor Pipe

-Marking pipe stream conform to shop drawing and coordinate to with stream of. an
pipe stream AC, Sewage water, Fire Fighting,Tray Cable etc.
-Cut pipe conform to dimension required.
-Cover gyp pipe (if it will be painted all of them/exposee area) with base paint (zin
-After base painted cover pipe with paint(color conform to technical specification)
-Install hanger and support pipe conform to marking result.
-Install pipe GIP conform to dimension on shop drawing, the connection of pipe, dia
2,5 inch with drat and diameter 2,5 inch above with weld.
-Use rope & water pass to measure the straightness pipe.
-Do painting work for pipe connection area.
-Do pressure test pipe with pressure conform to specification available.
-For installation of pipe on the wall, must be co-ordinate prior to ceramic work (arc
and sanitary.
-Do pressure test one more time if pipe on the wall has already been installed.
C.2. Installation of Pipe Outdoor
-Marking pipe stream.
-Dig pipe stream at depth fit to its elevation.
-connect to pipe upon excavation.
-Cover pipe with zinc chromate.
-Do pipe pressure test with pressure conform to technical specification available.
-Give sand layer on excavation base.
-Put down the pipe into excavation.
-Cover excavation one more time with sand.
-Fill the excavation.

C.3. Valve Installation


-Check the location of valve placing (does space among pipes which has already been
width of valve ?)
-Prepare valve with its flange.
-Install valve.
-Do pressure test of valve on that installation.

C.5. Installation Pump


-Marking the location of pump placing of.
-Make the foundation pump, notice the straightness and the smoothness of the fou
-Install installation pump room pumping first.
-Install Pump and their valves.
-Connect to power installation to pump.
-For automatically transfer pump using water level control (usually use electrode)
-Pump booster adjustment with pressure switch as follows
- - on position of pressure installation 2.5 Bar pump I (first) ON
- - If pressure back to 3 Bar pump Off.
- - But if pressure in orderly fell down till position 1.5 Bar pump II ON
- - If pressure go up again until 2 Bar pump II Off
- - Pump I and II always change position one to the other(alternated paral
-Do running test pump.
SKEMATIK DIAGRAM AIR BERSIH
E
H UR
OC
BR
T HE
OK
LO

Pump
Boost Wat
er er
tank
Elevated Water Tank

URE
H
OC
BR
3rd upper
T HE
level to
O OK
below L
Gravity
System

Water Pump

Garden installation
Pump
transf
er
Pipe of
Ground
PDAM
Reservo
ir
Diagram Block of Clean
Roof
Water Mecha
nical
Shaft

Pump Booster
Roof Tank

2nd upper level to below

Gat
e
Val
Toilet Toil Pantry ve
et

3rd upper level to below

Toilet Toil Pantry


et

R. Pump

Sand
Filte Grou
r nd
tank Fiel
Che
ck d
Valv Kra
Deep PDAM e Pump Transfer
n
Well
INSTALLATION
METHOD OF
SEWAGE WATER INSTALLATION
A. Material
- Pumps
- Valves
- PVC Pipe
- Supporting
material

B. Equipment
- Hand gear (gerinda)
- Iron saw machine
- Settle drill & Hand drill
- Key pipe, Pass toy, etc

C. Sequence of Impglueentation

C.1. Installation of Indoor Pipe


-Marking pipe stream conform to shop drawing.
-Cut pipe conform to dimension required.
-Fabricate hanger pipe conform to requirement.
-Install hanger and support pipe conform to result of marking, notice pipe slope( 1-2% ).
-Install pipe PVC conform to dimension on shop drawing, connecting pipe using glue.
-Use rope to measure the straightness of pipe.
-Do painting works for the are of expose.
-Do soak test for holing test pipe.4

C.2. Installation of Pipe Outdoor


-Marking pipe stream.
-Dig pipe stream at depth fit to its elevation.
-connect to pipe upon excavation along the space among control basin.
-Do soak test to test holing of pipe.
-Give sand layer on excavation base.
-Put down the pipe into excavation.
-Cover one more time the excavation with sand.
-Fill the excavation.
C.3. Installation of Submersible Pump

-Clean control basin from garbage and mud.


-Install pump at control basin.
-Connect to pipe from and to pump complete with check valve.
-Connect the chain of pump power to panel pump (source of power).
-Pump Test.

Diagram Block of
Sewage Water
(Example)
Vent

Male Female
Toilet Toilet

CO Closet Urinoir LV FD FD Lavatory Closet CO


Mechanical Shaft

Kitchen

Kitchen Sink

Basement Grease Trap

CO Closet Urinoir LV FD

Sump Pit Sump City


Pump Saluran

STP
tigmatic diagram of sewage water

F C
D O

F C
D O

F C
D O

F C
D O

CITY
SALUR
AN

F C
D O
WASTE
THREATMEN
T CENTER
INSTALLATION METHOD OF GENSET
A. MATERIAL
- Genset
-Spring Mounting
-Silencer
-Solar Tank
-Solar Pump
-Exhaust Radiator
-Fitting, Valve & Hanger

B. EQUIPMENT
- Fork Lift/ Gyp Pipe
-Hydraulic Jack
-Hand Drill
-Pass toy, Screwdriver etc
-Beams

C. EQUIPMENT OF GENSET

- Make sure that the foundation of Genset has


been made properly
- Marking the location of spring mounting placing

- Drill dynabolt hole


- Put Genset upon the foundation

- Use hydraulic jack for installing spring mounting

- Ready to be installed with its accessories

floor plate beyond


D. INSTALLATION ASESORIES GENSET
-Make sure that the position of Genset is level

-Install attenuator

-Install flexible duct


-Install Ducting BJLS as a connector to attenuator

-Install Grill attenuator


-Install Silencer Genset
-Install piping of exhaust
-Install solar tank
-Install fuel piping
-Install Pump & its valves

floor plate beyond

daily
tank

- Ready to be installed complete with the accessories

Hand Electric
Pump Pump

monthly

tank
INSTALLATION METHOD OF
SANITARY
A. Material
-Sanitary material :
- Closet
- Wastafel
- Urinoir
- etc.
-Supporting material

B. Equipment

-toy of pipe,
-Pass toy, etc

C. Sequence of Pelaksanaan

C.1. Installation Bath Tub


- Marking the location of placing of bath tub and pipe pembuangan
- Install the foundation for the seat of bath tub with brick layers

- Install pipe pembuangan complete with its U trap

- Install bath tub

- Check with water pass from each side to make the bath tub in straight

water pass
water pass

Bath tub

Installan bata

Ke saluran
air bekas
C.2. Installation Sitting Closet

- Marking the location of drilling point on the floor


- Make a hole at the floor with concrete drill conform to dimension fisher

- Install fisher.
y
Pouring silicon
around
Sparing pipebuangan sparing pipe

X and Y are
conformed to
closet type

Location of fisher
C.3. Installation of Squatting Closet

- Marking the location of closet placing

- Make brick layer of closet

- Install Squatting Closet

X and Y fit to closet


type
SECTION X

ELECTRICAL WORK
INSTALLATION
METHOD OF
ELECTRICITY
INSTALLATION
A.
MATERIAL

- Cable NYA / NYM / NYFBGY


- Weld Dop

B. EQUIPMENT
- Pancingan Wire
- Tongs, Screwdriver
- Paper tape and coloring

C. SEQUENCE OF IMPLEMENTATION

INDOOR INSTALLATION
-Insert pancingan wire into conduit
pipe conform to its group
-Pull cable with pancingan wire assist
-Mark cable conform to group with
tape and coloring
-The connection of cable could only be on
tee dos and with dope weld
-Merger cable which has already been installed

OUTDOOR INSTALATION

- Marking stream of installation


- Mark the location of lamp pillar
- Dig stream of which has already been marked
- Lay cable NYFBGY conform to dimension on
shop drawing conform to its group
- Cover with sand
- Fill the excavation with soil one more.
Clamp
conduit
Pipe
10 cm
60 cm 60 cm

Clamp
conduit Pipe 10 cm

Tee doos
10 cm

10 cm

5 cm

5 cm
Clamp

Bended Sock 5 cm

1. Drawing of Detail Installation Conduit


2. Conduit Pipe Distance Adjustment

Cable Rack

Clamp
conduit pipe
Installation
Cable
1.0 m
Cable Cable ties 60 cm 60 cm

Plate beton

Dynabolt
Hanger
Concrete Plate

Clamp
Cable Rack Tee doos

dope weld

3. Drawing of Cable Rack Installation Detail


4. Installation of installation cable

INSTALLATION METHOD OF CONDUIT & ELECTRICITY CABLE


PVC CONDUIT

CABLES
PLATE 12 mm

HANGER FLEXIBLE CONDUIT

TIE BEAM
HANGER

PIPE

CABLE TRAY
FLOOR SLAB (t = 12 cm)

HANGER SUPPORT OF FIRST LAYER


OF STEEL FRAME WORK

CABLE TRAY FRAME WORK

FLEXIBLE PIPE

SOCKET

PVC CONDUIT PVC CONDUIT

PROPOSED OF INBOW
ELECTRIC & ELECTRONIK
INSTALLATION FIRST LAYER OF STEEL FRAME
WORK
CABLE ON TRAY
-Make sure that width of tray is enough for the amount of cable
that will be installed
-Cut cable with the length exceeded 1 meter from requirements
-Pull cable one by one with the sequence from the edge
-Use cable ties as cable tighten with the distance of 1 meter
-Cable is ready to be connected to panel

CABLE ON LADDER

-Make sure that the width of ladder is enough for number of cable
that will be installed
-Cut cable with the length is exceeded 1 meter from requirements
-Pull cable one by one with the sequence from the edge
-Use ropes if cable will be installed vertically
-Use cable ties as cable with the distance 1 meter away
-Cable ready to be connected to panel

INSTALLATION OF TL RESSECED MOUNTED


- Marking plafond using chalk/coloring
- Hole plafond conform to marking, for acoustic
coordinated to plafond frame
- Install hanger wire

- Install lamp by uninstalling the lamp

- Tighten hanger wire

- Connect to installation

- Installation TL after the condition of project safe from stealing

INSTALLATION TL CEILING MOUNTED


- Marking plafond with chalk / color pencil, and install hanger wire.

- Pull cable installation & hanger wire direct to the outside


of plafond
- Install lamps if plafond is completely done
- Use screw for lamp tighten

- Connect to installation
METODE
PEMASANGAN
KABEL TRAY &
LADDER
A.
MATERIAL
- Kabel Tray
- Kabel
Ladder
- Gantungan
- Kabel NYA
- Fitting &
Jointing

B. PERALATAN

- Kunci Pas
- Tang,
Obeng
- Bor
Tangan
- Kapur
Tulis
C. URUTAN PELAKSANAAN

KEBEL TRAY

-Marking jalur tray sesuai shop drawing, tandai lokasi pengeboran untuk gantungan
-Bor lokasi gantungan
-Pasang gantungan tray sesuai dengan ketinggian yang diminta
-Tray dengan lebar 100 cm ke atas harus dipasang support pada tiap balok struktur atasnya
- Pasang kabel tray
-Pada setiap sambungan pasang penghubung grounding dengan kabel NYA 2,5 mm.

KEBEL LADDER

-Marking jalur ladder sesuai shop drawing, tandai lokasi pengeboran untuk gantungan
-Bor lokasi gantungan/support
-Pasang gantungan/support ladder
- Pasang kabel ladder
-Pada setiap sambungan pasang penghubung grounding dengan kabel NYA 2,5 mm.
FLOOR SLAB TEE DOOS
PVC CONDUIT

FLEXIBLE CONDUIT
DISTANCE VARIABLE

CEILING

LAMP

TEE DOOS
FLOOR SLAB

COVER HANGER
PVC CONDUIT
DISTANCE VARIABLE

CABLE NYA IN
STEEL TUBE LAMP HANGER

LAMP
INSTALLATION OF ROAD AND GARDEN LIGHTING
- Marking lamp position
- Make the foundation lamp pillar
- Built lamp pillar
- Install lamp onto pillar
- connect to installation

INSTALLATION OF SWITCH AND STOP KINTAK


- Marking stream of
conduit on wall
- Make hole at brick layer, don’t forget to use cutter
- Install conduit & inbow dos
- Wait until wall was finish at
architectural
- Connect switch, stop kontak with the installation
- Install switch & stop kontak, use water pas to
make it straight level
Installation of switch & Stop kontak

break stream of
conduit switch

break stream of conduit


stop kontak
150 cm

30 cm
INSTALLATION SWITCH AND STOP KONTAK

cable cable
installation installation
conduit conduit

wall

wall
cable cable
inbow dos swit
installation installation
switch ch
150 cm
150 cm
inbow dos stop 30 stop
kontak cm kontak 30
cm
INSTALLATION METHOD OF
LIGHTNING PROTECTION
A. MATERIAL
- Conduit PVC
- Lightning Protector Pillar
- Cable Coaxial / BC / NYY

m
- Copper Rod

30
- Head Lightning Protector

=1
on
cti
ot e
Pr
i us
B. EQUIPMENT

d
Ra
F”
“E
- Grounding test
- Tongs, screwdriver, iron saw machine
- Bending conduit

C. SEQUENCE OF IMPLEMENTATION

- Determine the location of grounding


- Mark grounding with copper rod

- Make control basin

- Arrange Lightning Protector & lamp on Lightning Protector Pillar

- Install Lightning Protector on the location conforming to drawing

- Pull coaxial cable & connect to Markan

- Architectural Finish

LIGHTNING PROTECTION SYSTEM


& AREA PROTECTION
Grounding Pit Inspection

LIGHTNING PROTECTION
SYSTEM PLAN

LIGHTNING PROTECTOR
HEAD DETAIL
Down Conductor
500
PVC Clamp
Inspection Box 500

Down Conductor

Column Inspection
2.00 m

Conduit
Wall
50 500
Floor
2000
Ground Surface 500
Down Conductor
Grounding Pit
500

GROUND CONDUCTOR SECTION DETAIL

GROUND CONDUCTOR CLAMP DETAIL

10 cm
Ground Surface

Concrete Cover

Light Concrete To Inspection Box Termination


BCC 50 mm2
320 mm
Jointing Clamp

Gravel 20 cm
100 mm

To Another Grounding Pole Shaft Be Needed


100100 400 100100

Copper Rod dia. 25 mm


GROUNDING PIT DETAIL

INSPECTION BOX DETAIL


INSTALLATION METHOD
OF TELEPHONE
INSTALATION
A. MATERIAL

- PABX
- Telephone
- Telephone Outlet
- Installation cable
- Conduit
- Terminal box
- Supporting material
Making hole for telephone outlet
conduit stream

B. EQUIPMENT

- Tongs, Screwdriver etc


- Water pass 30 cm
- Pass toy
Installation of Telephone Outlet

C. SEQUENCE OF IMPLEMENTATION

- Installation of installation conduit

- Installation of phone cable installation

- Installation of installation
cable rack
- Installation of terminal box

- Installation of telephone outlet

- Installation of main equipment


Telephone
Diagram Block

Telephone Main Equipment

Teleph
Powe one
r Outlet
Suppl Computer TBT
y

Teleph
Printer
RUANG KONTROL one
Stabiliz PABX Outlet
Electronic Shaft

er TBT

Consol
Operation

MDF
Telep Direct
hone TBT Channel

Public Telp.

grounding
Power Cable
Junction Box of Telkom
Data Cable

Extension Cable

Direct Channel Cable


TRANSFORMATOR

INSTALLATION
METHOD OF
TRANSFORMATOR
20 cm
A. MATERIAL

- Transformator
- Rectangle steel 5 cm 20 cm
- Foundation Material

B. EQUIPMENT

- Tongs, Screwdriver
- Pass toy
- Hand drill

C. SEQUENCE OF IMPLEMENTATION

-Make transformator foundation conform to shop drawing,


each side is exceeded by width of 20 cm
- Put transformator upon the foundation
- Prop transformator wheel with rectangle steel 5 cm
- Install grounding transformator

to
grounding
``

``
INSTALLATION METHOD
OF
TRAY CABLE & LADDER
A.
MATERIAL

- Cable Tray
- Cable
Ladder
- Hanger
- Cable NYA
- Fitting &
Jointing

B. EQUIPMENT
- Pass toy
- Tongs,
Screwdriver
- Hand Drill
- Chalk

C. SEQUENCE OF IMPLEMENTING
TRAY CABLE

-Marking stream of tray conform to shop drawing, mark the location of drilling for
hanger
-Drill the location of hanger
-Install hanger tray conform to the height required.
-Tray 100 cm width or more must have installed support on each beam beyond.
- Install cable tray
- On every connection install grounding connector with cable NYA 2,5 mm.

LADDER CABLE

-Marking stream of ladder conform to shop drawing, mark the location of drilling
for hanger
-Drill the location of hanger/support
-Install hanger/support ladder
-Install cable ladder
-On every connection install grounding connector with cable NYA 2,5 mm.
INSTALLATION METHOD OF PANEL
A. MATERIAL
- Panel
-Dynabolt
-Foundation Material
B. EQUIPMENT
- Hand Drill
- Pass toy, Screwdriver etc
-Water pas

C. INSTALLATION PANEL

C.1. Free Standing


-1. Make sure that the foundation Panel has been made properly

-2. Marking the location of panel placing

-3. Drilling dynabolt hole

-4. Put Panel upon the foundation

-5. Tighten dynabolt baut

``
C.2. Semi In bow Panel

-1. Marking the location of panel at height of 180 cm up level


-2. Make hole at brick layer

-3. Install dynabolt

-4. Install panel if wall around it has already been plastered/finish


C.3. Wall Mounted Panel

-1. Marking the location of panel at height of


180 cm up level
-2. Install dynabolt

-3. Install panel


PLANNING OF
SITE PLAN

SITE PLAN HAS TO BE COMPLETED WITH THE FACILITIES AS


FOLLOWS :
• Office
• Warehouse /
storage
• Workshop
• Utilities
• Environtment

THE BASIS OF HOUSEKEEPING

 PDCA :
 Plan : planning of Site
Plan
 Do : who & how
 Check & Action : standard procedure
/ maintenance

 BOCAL :
 Bahan :
warehouse
 Orang : by
whom
 Cara :
management
 Alat : work
shop
 Lingkungan : site
plan
Planning of Site Plan Requirement

• Equipment & temporary building have to be drawn in fair


scale
• To be planned for site plan modification based on the
project activity sequence
• M/E installation & equipment will be planned on the basis of
the accurate calculation
• Traffic flow should be in accordance with logical & based
on the pattern of the activity
• Site plan has to be socialized with outer environtment

Housekeeping Management

 5 S (seiri, seiton, seiso, seiketsu, shitsuke)


 JIT (just in time)
 ISO 9000 with standard procedure
5 S
 Seiri : classifying
 Seiton :
arrangement
 Seiso : cleaning
 Seiketsu :
stabilization
 Shitsuke :
familiarization
 Seiri =
classifying
 Stratification management &
overcome the obstacle
 Dispose of the obsolete
goods
 Handle of dirtiness
 Handle of damaged goods
 Cleaning of room
 Seiketsu =
stabilization
 Seiton =  Visual management & 5 S
arrangement stabilization
 Sign board
 Functional keeping and waste
 Coloration code
of time for watching
 Checking mark
 Special place for all of the  Cabling arrangement
goods  Label of voltage, limit,
 Archive standard temperature, loading capacity
& dimension
 Tidy the equipment & job site
 Site arrangement & labeling
 Seiso =  Shitsuke =
cleaning familiarization
 Cleansing as checking and  Familiarize building &
cleanness stratification discipline
 More efficient cleansing  on job site
 Clean & check of the  Commitment
equipment & tools  Procedure & 5 S manual
 Checking of cleansing & standard
correction  Individually
 Everyone is house keeper and responsibility
cleansing officer  Routine of training &
practice
 Seiri
 Seito
n
 Seiso
 Seike
tsu
KYK & 5 S
 Shits
uke
ACTIVITY
 Kike
n
 Yoch
i
 Kats
udo

• Method & work


JIT (just in time)
scheduling
• Material scheduling
• Equipment scheduling
• Subcontractor
scheduling
• Man power scheduling

JIT (just in time)


Characters
 Procurement & delivery of material on site at the basis of
needs and on time
 No over stock of material on job site warehouse
 No idle equipment
 The amount of labor comply with need

ISO 9000
 Management
Commitment
 Working Procedure
Ladder
Safe enough and
comfortable
PP-5th Floor

TEMPORARY SUPLY OF POWER DIAGRAM


PP-4th Floor

PP-3rd Floor

PP-2nd Floor

2
Y
m
Y
2

m
N
50 Y
m
X NY

6
m

X
MEDICINE & LIBRARY

4
2
m

PP-1st Floor
4
m
70
X
4
Y
Y

``
N

SDP-MedIcine

PP-2nd Floor

2
Y
m
Y
m
2

N
25 Y
m
X NY

6
m

`` 4
X
PP-1st Floor
4

SDP-U

GENERATOR 100 Kva


``
SDP-Library

PP-5th Floor

PP-4th Floor

DENTISTRY PP-3rd Floor

PP-2nd Floor
2
50 Y
m

2
6 Y
X NY
m

m
X NY
m
4

PP-1st Floor

``
SDP-P

GENERATOR 75 Kva
TEMPORARY SUPLY OF WATER DIAGRAM
FOR MEDICINE BUILDING

Elevated
Water Tank

Gate Gate Gate Gate


Valve Valve Valve Valve
Project
Office
P P

50 m3

Water Pump
Foot Valve Water Pump
Kap = 50 Kap = 135 lt/m
Foot Valve lt/m Floater
Head = 36 m
Head = 30 m Valve

TEMPORARY SUPLY OF WATER DIAGRAM


FOR LIBRARY BUILDING

Elevated
Water Tank

Transportation by water tank 5000 lt


Gate Gate
Valve Valve
Project
P Office

50 m3 10 m3
(Medicine)

Foot Valve Water Pump


Kap = 50 lt/m
Head = 30 m
TEMPORARY SUPLY OF WATER DIAGRAM
FOR DENTISTRY BUILDING

Elevated
Water Tank

Gate Gate Gate


Valve Valve Valve
Project
Office
P P

50 m3

Water Pump
Foot Valve
Water Pump
Kap = 50 lt/m Kap = 135 lt/m
Foot Valve Head = 30 m Floater Head = 36 m
Valve