You are on page 1of 9

Topic:-

Substation Diagnostic Testing


Practices (O&M DT Team).

.....Kailas Daulat Yelmame


(DyEE, EHV Substation Maintenance
Subdivision ,Nashik)
Substation Equipment's Diagnostic
Testing by (O&M Team)
• Power Transformers & ICTs.
• Current Transformers (CTs).
• Potential Transformers (PTs).
• Circuit Breaker’s.
• Isolators.
• Capacitor Banks.
• Battery's.
• Cables.
• Thermovision.
Power Transformers and
ICTs Diagnostic Testing.
IR (Insulation Resistance) Testing:
1) Insulation ages and Deteriorate because moisture , dust,
electrostatic stress.
2) IR Test detect Insulation quality within the Transformers.
3) Detect the degree of dryness of paper insulation.
4) Instruments required: IR Tester (Range
500V,1000V,2500V,5000V,10000V).
5) For Transformer winding with in voltage rating up to 11kV , 2.5kV
IR tester sufficient.
6) For EHV level 5kV-10kV IR Tester.
Connection Diagram for IR Value Testing