PIKIT ETERNAL

GARDEN/PUBLIC
CEMETERY
LOWER LADTINGAN, PIKIT NORTH COTABATO
SITE
DEVELOPMENT
PLAN
COMPARTMENTS
Elite – 672
Medium-Duplex – 2,880
Medium – 228
Down Size– 3,312
Upsize – 7,200
SCOPE OF WORK
BIG COMPARTMENTS w/in Perimeter
7,200 units x P4,560/Compartment = P 32,832,000.00
MEDIUM COMPARTMENT (DUPLEX TYPE)
2,880 units x P 4,900/Compartment = P 14,112,000.00
ELITE Compartments
672 units x P 4,900/compartment = P 3,292,800.00
Medium Compartment
228 units x P 4,900/compartment = P 1,117,200.00
Small Compartments for bones
3,312 units x P1,500 = P 4,968,000.00
Concreting w/in the Perimeter w/ Culverts
436meters @ 4.0m width & 0.15m Thk

436 meters x P 6,150 = P 2,681,400.00


Fence in front w/ grills & plantbox
297meters x P 9,000 = P 2,673,000.00
Guard House – P 460,000.00
Water System – P 470,000.00
4-Door Comfort Rooms – P 400,000.00
Chapel – P 1,100,000.00
Landscaping – P 1,500,000.00
TOTAL ESTIMATED PROJECT
COST:
P 65,606,400.00