Professional Documents
Culture Documents
Course
Sharing Experience on Power System Protection.
Jogjakarta March 10, 2003
GENERATED POWER FOR JAWA
BALI
Year : 2001 - 2004
100%
90%
80%
70%
60%
50%
40%
30%
20% SURALAYA
10%
SURALAYA
0%
2001 2002 2003 2004
1 Power Output
9 Turbin Manufacture Mitsubishi Heavy Industri ( Tandem Compund Quadraple Exhaust Reheat Condensing )
11 Generator Transformer Manufacture Mitsubishi Electric Company ( OFAF cooling Off Load Tap Changer )
PT Indonesia Power’s Power Plants Location
Jakarta
Installed
Capacity 9,094
Bandung
Semarang MW
Banjarnegara
Surabaya
Grati
Denpasar
HP HEATER 8 COND
DEAERATOR LP HEATER 4 POLISH
DEMIN
HP HEATER 7 PLANT
ASH LP HEATER 3
FWT
180 k, 142 C 28 k. 40 C
HP HEATER 6
LP HEATER 2
DESAL PLANT
BFP LP HEATER
GLAND ST
COND
LP HEATER
SUBFP
CAPABILITY CURVE SPECIFICATION
Applicable for Unit No 5 to 7
Generator Mitsubishi Electric
600
PF 0,85
400
Current : 19.253 A
Power Factor : 0,85
Phase :3
200
Frequency : 50 Hz
MEL
No of pole :2
MVAR
0 MW
200 400 600 Cooling System : Hydrogen at
Steady 5kg/cm2
state limit
Ecxitation Voltage : 590 V
UNDER EXCITATION
200
EXCITER
CAPABILITY CURVE
Brushless type , Output : 3300 KW,
Voltage 590 V current 5593 A
SURALAYA SPP
1 2 3 4 5 6 7
A
Station Use Bus-
500 kV bars
to GANDUL to CILEGON
1 2 3 4 5 6
A
150 kV
B
to CILEGON To SALIRA
HOT START-UP
START UP CURVE OF SURALAYA POWER PLANT
600
2
500 200 100 4
180
1
400 160 80
140
300 120 60
100
200 80 40
60 3 3000
100 40 20 2000
20 1000
0 2 4 6 8 10 12 14 16
hours
Legend :
1. Main steam pressure (kg/cm2)
2. Main steam temperature (oC)
3. Turbine speed (rpm)
4. Generator Loading
START-UP TIME OF SURALAYA SPP
DURATION OF
CONDITION MAX START-UP START-UP TIME START UP COST
UNIT No. TYPE st STOP
Turbin 1 Metal Temp. per YEAR up to 100% LOAD (in Million Rp. )
( hour )
0
COLD < 190 C >36 hours 3 times 17 hours 221
1-4 WARM 0
190 C - 370 C
0
8 - 36 hours 2 times 12 hours 170
0
HOT > 371 C < 8 hours 1 time 7.9 hours 102
0
COLD < 190 C > 36 hours 3 times 17 hours 324
5-7 WARM 0
190 C - 370 C
0
8 - 36 hours 2 times 12 hours 218
0
HOT > 371 C < 8 hours 1 time 7.9 hours 155
Estimated Time to Restart Power plants following
blackout
FATEST START-UP TIME OF SURALAYA AFTER BLACK-OUT
BACK FEEDING (INCOMING POWER SUPPLY) AFTER BLACK-OUT
< 1 hours 1 - 8 hours 8 - 36 hours > 36 hours
No. DESCRIPTION
With With-Out With With-Out With With-Out With With-Out
By-Pass By Pass By-Pass By Pass By-Pass By Pass By-Pass By Pass
By Pass not
By Pass not
By Pass not
By Pass not
Available
Available
Available
Available
4 Start-Up Unit 5,3 5,3 9,9 14,2
5 Ramping 0% to 100% Load 4,1 4,1 4,1 5
TOTAL TIME (HOURS) 9,4 11,4 16 21,2
B. UNIT 5-7 (3 Unit Start)
Condensor Damage, Turbin Damage (Lub Oil Pump not
1 Consequence Minimum Impact running), Air Heater Damage, Steam Drum Boiler Drop (long
firing), Back-Up Battery Time LOW
Available
Available
By Pass
By Pass
By Pass
By Pass
4 Start Unit 3,8 7,9 7,9 12
5 Ramping 0% to 100% Load 4,1 4,1 4,1 5
TOTAL TIME (HOURS) 7,9 7,9 12 17
ANTICIPATION AGAINTS
BLACKOUT
• Established internal supply to avoid any damages
which may be occurred upon blackout
• Established routine check and test any essential
supply which maintain protection to the apparatus.
• Set-up islanding operation to speed up recovery
• Set-up initial HOUSE LOAD operation if
islanding operation fail to establish
BLACKOUT ON 24 OCTOBER
1988
The main cause of failure Atwas
13.13 the
WIT air supply for instrument
All Suralaya generators (at that moment Unit No. 2,3 and 4
mean 1200 MW in operation) tripped out and then caused
cascaded tripping to others generators. This failure put Java-
Bali in blackout immediately since at that time the overall loads
only 3635 MW.
BLACKOUT ON 13 APRIL 1997
All Suralaya plants (Unit no 1-7 except No.2 whose Unit 1 = 390 MW, Unit 2 = Overhaul
out for maintenance) being in normal condition, Unit 3 = 390 MW, Unit 4 = 390 MW
17:30
operated at 2895 MW ( 85% of Total Capacity of Unit 5 = 600 MW, Unit 6 = 525 MW
3400 MW ) Unit 7 = 600 MW
17:57 UNIT No. 4 TRIP Caused by Furnace Draft > Max (Boiler)
18:02 UNIT No. 5 TRIP Caused by Main Steam Temp High (Boiler)
18:05 UNIT No. 7 TRIP No Flame of any Burner detected , (Boiler trip)
18:05 All voltages (150 and 500 kV) were out of service Suralaya Black-Out
SURALAYA CONDITION JUST AFTER BLACKOUT
UNIT No. STATE OF THE PLANT ACTION TO BE TAKEN
UNIT 2 Overhaul
NOTE : 12 September 2002 was the first black out occurred to Unit no. 5 up to 7
RESTORATION OF SURALAYA
AFTER BLACK-OUT ON 12 SEPTEMBER 2002
12 Sept 23:15 12 Sept 02:45 HOT Start Recovery Time 9 jam 35 mnt
Turbin has been trip at roll out due to the
13 Sept 10:45
UNIT 3 failure in lubrication system
Start Up has been performed after
03 Okt 02:00 04 Okt 17:00 repairing on turbine bearing & Impeller of
Main Oil Pump (MOP)
13 Sept 01:00 Trip again due to second Black-Out
UNIT 4
HOT Start Recovery Time 23 hours 12
13 Sept 11:45 13 Sept 18:12
minutest
UNIT 5 15 Sept 18:04 16 Sept 06:54 COLD Start Recovery Time 3 days
COLD Start Recovery Time 54 hours and
UNIT 6 13 Sept 10:25 14 Sept 03:33
33 minutes
Rolled up aborted due to high turbine
12 Sept 20:15
vibration
UNIT 7
COLD Start Recovery Time 55 hours 43
14 Sept 19:51 15 Sept 04:43
minutes
RECOVERY PROCESS FOLLOWING
BLACKOUT
• Since there was no power enough to restart from station use while
turbine speed down to zero which normally took 45 minutes, back
feeding should returned at a proper time (less than 60 minutes) to
ensure that restarting enable as soon as possible.
• Since Auxiliary Steam is necessary to fire plants No 1 to 4 , it could be
supplied by remaining steam which still held in any steam drum of
boilers. If any unit can be restarted within 2 hours all units then can
easily be restarted, but if none of them could not be started or
restarted after 2 hours there will be no auxiliary steam enough to
restart any plant. In this situation Auxiliary Boiler should be started
and this will take at least 2 hours to produce auxiliary steam which
the amount also be limited. Only up to two plants can be started at the
same time.
RECOVERY PROCESS FOLLOWING
BLACKOUT
(continued)
• After back feeding return to Suralaya Start-Up for plants No
1 to 4 still limited to two units due to limitation on start up
transformer capability an the auxiliary steam produced on
auxiliary boiler.
• When back feeding applied to Plants No 5 to 7 all plants can
be restarted since atomizing process used instruments air.
• If HOUSE LOAD success to establish, resynchronize to the
grid should be taken less than two hours since control system
will recall for tripping due to Low Power Turbine Limit
action.
Scenario to Perform Island Load of Suralaya SPP
Same
50 Hz Action 50 Hz NORMAL OPERATION
Fre q =
Freq = 51,5 Hz
48,3 Hz
PMT
NO
PMT GANDUl 1
NO TRIP ?
GANDUl 1
TRIP ?
YES
YES
PMT NO
GANDUl 2
TRIP ?
PMT NO
GANDUl 2
TRIP ? YES
YES
Unit 1 NO
ONLINE ?
SINKRON
YES
Unit 7 NO
ONLINE ? Unit 5 NO
SINKRON ONLINE ?
SINKRON
YES YES
OPEN PMT
UNIT 6
OPEN PMT
UNIT 7
NO ACTION NO ACTION
END
END
CONCLUSIONS
• Even to restart only one plant, it is necessary for SURALAYA to have
back feeding from the grid immediately after blackout occurred
• Maximum Back-Feeding Time needs to avoid Suralaya SPP from any
damages should be less than 60 minutes. This will minimize damages to
the main apparatus ( I.e Turbine, Air Heater & Condenser etc )
• If back feeding recover more than 2 hours should Aux Boiler be started
providing auxiliary steam to assist firing process.
• Due to the complexity of control activities HOUSE LOAD only be kept
less than 2 hours. Any action to resynchronize to the grid should initiate
immediately to avoid further tripping.
CONCLUSIONS
(continued)
M
M
Start-Up Bus B
SST 3
36/56 MVA
SST 4
36/56 MVA
GT Unit 7
M
UST 7A
UST 7B SU-BFP 7
36/56 MVA
36/56 MVA 6 MW
Gen Unit 7
M M
4. Diesel fuel oil (HSD) Igniter : Perform first firing prior to use coal firing
system or marine fuel oil firing system
Required Power to Start-Up :
CONNECTED Load Demand Load
Motor
Operation Factor Power
ITEM Qty
Voltage ( kV )
Acceleration LOAD (Bus A+B)
Factor (kW) (kVAR) (kVA)
Time (Seconds) (kW) (kVA) (% )
1. UNIT 1-4 (for 1 unit)
a. Low Voltage LVS LOAD 1 0,38 1800 2250 80 0,80 1876 1389 2334
b. Auxiliary Boiler Start-Up 1 6 & 0,38 1000 1250 80 0,80 800 600 1000
c. Cooling Water Pump (CWP) 1 6 4 1500 1875 95 0,80 1425 1069 1781
e. Condesate Extraction Pump (CEP) 1 6 4 630 788 85 0,80 536 402 669
f. Boiler Feed Po. (BFP) 1 6 4 6342 7928 90 0,80 5708 4281 7135
g. Induced Draft Fan (IDF) 1 6 28 2255 2819 50 0,80 1128 846 1409
h. Force Draf Fan (FDF) 1 6 25 1393 1741 50 0,80 697 522 871
i. Primary Air Fan (PAF) 1 6 10 1322 1653 50 0,80 661 496 826
j. 1 ea. MILL to produce 100 MW 1 6 3 522 653 95 0,80 496 372 620
TRANSFER SST to UST at 80 MW
Power to Start-Up one plant of 400 MW 13325 9975 16646
Total Power to Start-Up 4 plants of 400 MW 39976 29926 49937
2,500
2,375 CEP start SU-BFP start
2,250 Is = 7,14 x In ID Fan start
Is = 8,49 x In Is = 9,26 x In
2,125
2,000
Current (Amperes) at 10,5 kV
1,875
FD Fan start
1,750
CWP start Is = 9 x In
1,625
1,500
Is = 4,82 x
In
1,375
1,250
1,125
1,000
875
750
625 C3WP
500
375
250
125
0
Time (Second)
Station Service Transformer Bus Drop Voltage Simulation by ETAP
3.0.1)
CWP
start
CEP start
SU-BFP start
FD Fan start
ID Fan start
600
400 160 80
140
300 120 60 4
100
200 80 40
60 3 3000
100 40 20 1 2000
20 1000
0 2 4 6 8 10 12 14 16 Hours
Legend :
1. Main steam pressure (kg/cm2)
2. Main steam temperature (degree C)
3. Turbine speed (rpm)
4. Generator Loading
WARM START-UP
START UP CURVE OF SURALAYA STEAM POWER PLANT
600
2
0 2 4 6 8 10 12 14 16 Hours
Legend :
1. Main steam pressure (kg/cm2)
2. Main steam temperature (oC)
3. Turbine speed (rpm)
4. Generator Loading