Professional Documents
Culture Documents
Pile Drain
ECCD – EDRC (MMH - IC )
Objective:
To Study:
To Propose:
Introduction:
2. Aggregates:
Admixtures Used
Superplasticisers - Increase the workability
water reducing agents- Reducing the water content in concrete mix
Accelerators - To accelerate the rate of early strength
development
4. Reinforcement:
- Fe 415, Fe 500
- welded wire fabric
ECCD – EDRC (MMH - IC )
Sealant:
Sealant should have following properties to be used in
Precast concrete:
a) Seal the joints between precast elements.
b) It should bond firmly to the concrete.
c) Accommodate panel movements without splitting,
tearing or loss of adhesion.
d) It must be resistant to ultra-violet (UV) light and
other weathering effects.
e) Joints that are subject to frequent and rapid
movement require an elastic sealant.
f) Joints in massive components with high thermal
inertia, should be with an elastoplastic, plastoelastic
or a plastic sealant.
-Polysulphide, Polyurethane and Silicone
ECCD – EDRC (MMH - IC )
Mould Design:
Types of materials used:
Steel
Timber/Plywood
Glass reinforcement concrete
Steel Mould
CASTING
Casting Sequence:
•Arrange the form work as per required size & shape.
•Apply oil in formwork surface to avoid the bonding
between formwork and concrete.
•Place the reinforcement cage with required cover.
•Position of insert plate & pipes if required, before
pouring the concrete.
•Pour the concrete in formwork.
•Demould the form work after required time.
ECCD – EDRC (MMH - IC )
CASTING
.
Precast Drain
ECCD – EDRC (MMH - IC )
Delivery:
Delivery:
Handling :
Precast Slab Precast Beam
Storage:
The storage area provided in the yard and job site should be
adequate:
To permit easy access and handling of the precast elements.
The area should be relatively level, firm
It should well drained to avoid any differential ground
settlements which may damage the stored elements.
Installation:
Length : 4000m
JT12
/B
6A
NV
CO
JT13
CONV 12
A/B
JT14
JT10
JT15 JT 9
JT16 JT21 CONV 23
A/B
CONV
10A/B
SCR
JT20 CONV 23 JT 8 CH
A/B JT 7
JT17
SCR
CONV
8A/B
4 Hoppers JT18
ECCD – EDRC (MMH - IC )
Section Details
P1
PT1 to PT5
Dimension Details
SL. NO. DRAIN MKD W (mm) D (mm)
1 P1 350 450
2 PT1 350 450
3 PT2 350 550
4 PT3 350 650
5 PT4 350 750
6 PT5 350 870
ECCD – EDRC (MMH - IC )
Connection Detail
Connection Detail
Installation Procedure:
a) With reference to the drawing co-ordinates, excavation
should be made with proper slope, working space and
required depth as stated in the excavation drawing.
b) Proper line marking should be done and 75mm/100mm
P.C.C/ 50mm-100mm sand should be laid all around as per
NIT specification.
c) Each element should be numbered properly based on
depth and orientation to be aligned. Lifting should be done
based on their numberings.
d) Each precast drain elements has four hooks. There precast
drain elements are lifted using suitable capacity cranes and
placed over the markings.
ECCD – EDRC (MMH - IC )
Installation Procedure:
Conclusion:
a) One of the most obvious benefits of utilizing precast drain
elements is the dramatically shortened construction time.
(Approximately not less than 50%)
b) Moulds are repeatedly used in this construction, so the
cost of mould & labour for shuttering work is saved.
c) Before erection of precast drain, the element parameters
has to be fully inspected & should be checked, so the that
quality of precast will be better than cast-in-situ type
construction.
d) There are some design limitations associated with the use
of precast elements because of the size limitations
connected with the transportation and handling of them.
e) Precast concrete construction requires skilled labour for
the connection of precast element.
PRECAST - SCOPE FOR DEVELOPMENT
• Cable Gallery Foundation
• Stacker cum Reclaimer
• Self-Compacting Concrete
• Accelerated curing
ECCD – EDRC (MMH - IC )
Thanking You