MADHYA PRADESH URBAN DEVELOPMENT COMPANY LIMITED

Madhya Pradesh Urban Development Project


(MPUDP)
Financed by

Government of Madhya Pradesh

Progress Review
dated 21-10-2020

PROJECT MANAGEMENT
CONSULTANT :
Key Data
Approval by Board of the World Agreement signed/ Original Physical Closing
Bank Effectiveness
12-Apr-2017 12-June-2017/ 31-Dec-2022
12-Jul-2017 (Financial Closing after 6 months)
Loan Amount ($m) 116.2
State Funding ($m) 49.8
Total Project Cost ($m) 166.0
Disbursements of loan achieved Year 2017-18 (July-June) - US$ 7.55 m US Dollar (Cost of $ varies
till date (disbursement cycle is from ₹63.50 to ₹64.12)
per quarter) Year 2018-19 (July-June) - US$ 4.48 m US Dollar(Cost of $ varies from
₹65.75 to ₹71.56)
Year 2019-20 (July-June) - US$ 6.45 m US Dollar(Cost of $ varies from
₹69.55 to ₹75.60)
Cumulative Disbursement 18.48 million USD
Works awarded include:
Implementation Progress
•3 Water Supply and 6 Sewerage sub project
(Total cost of the works •Project Management Consultant,
•Environmental & Social Assessment Consultant (Pkg 1 & 2),
awarded= US$ 118.16 million)
•Independent Verification Team (IVT),
1US$ = INR 72 •Reform support consultant,
•Firm for safeguard audit
•Environment study consultant for Chambal Crocodile Sanctuary
2
Components
Amount in million US $
Cost of
Provision in the Cost of works works Balance
Component No.
Project (Total) awarded (award in amount
process )
1.Institutional 26.5 million 5.68m Dollar 6.94 m Dollar 13.88 m
Development Dollar Dollar
2.Urban Investments 139.2 million 112.18 million   27.02 m
on Works – 5 water Dollar Dollar (3 WSS + 6 dollar
supply and 7 Sewerage)
sewerage projects
Front End Fee 0.3 million Dollar 0.3 million Dollar    
Total 166 m dollar 118.16m Dollar 6.94 m dollar 40.90 m
dollar
Loan-28.56
m USD
State Share-
12.34 m
1 US $ = ₹ 72 3
USD
Year wise Target and Achievement
(IN million USD) (FY July-June)
Description
2017-18 2018-19 2019-20 2020-21

Year wise Target 6.50 6 17 29


3.13 till Sept
Achievement 7.55 4.48 6.45 against a target
of 3 mUSD
18.48 (till June
Total Disbursement in million USD
20)
Total Disbursement in % of loan amount till June 20 16%
Note :
1. Achievement in FY 2019-20 is lagging due to stoppage of work by The World Bank in
Shajapur & Maheshwar Sewerage Project, Non availability of land in Nasrullaganj
Sewerage Project.

4
FY20-21 Disbursement Projections(US$ million)

Q4
Q1 Q2 Q3
Quarter Apr-June- Total
July-Sept 20 Oct- Dec 20 Jan- Mar- 21
21
Disbursement
Target in million 3 5 9 12 29
US$
Actual Expenditure
in Qtr Amount INR 33.13
Cr.
Reimbursable
23.19
amount (In INR Cr.)
In million US$ 3.13 (IUFR
(INR @ Rs 74/US$) being sent)

5
Institutional Development: Sub Components and their Progress
CONTRACTS AWARDED
Expendi
Name of Award Complet Awar-
Assignment ture till
vendor date ion date ded cost
date

Consultancy for Environmental and Social


Framework (ESMF), Environmental and M/s L.N. Complete ₹0.98 ₹0.90
March 2016
Social Assessment (ESA) of 8 sub Malviya d Cr. Cr.
projects.

20-4-17
M/s 21-5-20/
Effective ₹20.79 ₹14.24
Project Management Consultant WAPCOS Extn. 31-
date 22- Cr. Cr.
Ltd. 12-20
5-17

Independent Verification Team for Third


M/s TUV- ₹5.92 ₹2.46
Party inspection of works under Urban 27.03.18 26.03.22
SUD Cr. Cr.
Investment component

27.11.18
Consultant for Reform Support Cell at
M/s IPE (effective ₹9.47 ₹2.13
Directorate of Urban Administration and 27.12.20
Global date Cr. Cr.
Development
28.12.18)
6
Continued
Institutional Development: Sub Components and their Progress
CONTRACTS AWARDED
Expendit
Name of Award Complet Award
Assignment ure till
vendor date ion date ed cost
date
Consultancy for Detailed State
14-9-20/
Environment Assessment for Morena Forest ₹0.67
28-2-19 Extn ₹0.39 Cr.
water supply source (Chambal Research Cr.
14-03-21
Gharial Sanctuary) Institute
Consultancy for Environmental and
Social Framework (ESMF), M/s Lion ₹0.52
14-1-20 30-06-20 (0.08 Cr)
Environmental and Social Consultant Cr.
Assessment (ESA) of 2 sub projects.
M/s 14 Jan, ₹0.52
Firm for safeguard audit 31-12-22 ₹0.21 Cr.
KPMG 2020 Cr.
21-7-20/
Dr
22-7-19 Extn
Hiring of Social and Environment Prajapati ₹0.67 ₹0.19
& 21-7-21
Expert & Dr Cr. Cr.
1-11-19 &
Mahor
31-10-20
7
Institutional Development: Sub Components and their Progress

Sub Component Present Status/ Progress


Works to be awarded in Component 1 (6.94 m US Dollar)
Project Management EoI published on dated 03.09.2020. Date of
Consultancy - 2 receiving EOI extended upto 06.10.2020. EOI
opened on 06.10.2020. 30 consultants have
participated in EoI. Evaluation under process.
Hiring of NGO EoI was invited earlier and 6 NGOs were shortlisted, but
the process was cancelled on the objection of The World
Bank.
Fresh EoI published on dated 03.09.2020.
EOI opened on 26.09.2020. 11 bidders have
participated in EoI. Evaluation under process.
Hiring of Advertising Agency EoI has already been invited and 6 firms have been
for media campaigning shortlisted. The RfP & ToR is already approved by The
World Bank. RfP is being sent to shortlisted firms
shortly.
Benefit Monitoring Expert Invitations invited on dated 08.07.2020. A total number of
(BME) 15 applications were received. only one candidate is
eligible. Hence it is proposed that this invitation for the
post of BME expert should be recalled once again. 8
Urban Investment: Sub Components and their Progress
Description Water Supply Sewerage Total

Total No. of Projects 05 07 12


Originally Proposed

Works Awarded 03 06 09
(Burhanpur, (Chhindwara, Dharampuri,
Khargone, Maheshwar, Nasrullaganj,
Sewda) Shajapur, Bhedaghat)
Bidding Stage 00 00 00

DPR approved by The World 00 01 (Shahdol) 01


Bank, But ESA yet to be ESA sent to World Bank
(revision no. 06) on
approved
11.06.2020
Projects proposed to be taken 02 00 02
up in other program Morena
Sheopurkalan

9
Planned Completion/Payment Schedule of Project Under WB Format
Q3-2020
3A
Q4-2020 Q1 -2021 Q2-2021
(July, Aug, Sep) (Oct, Nov, Dec.) (Jan, Feb, Mar) (April, May, June)
Sector Package Project Package Project Package Project Cost Package Project
Cost(Cr.) Cost(Cr.) Cr. Cost
(Cr.)
Water Supply        
WB-06
Sewerage         (Dharampuri)
18.14

Grand Total         01 18.14

Q3-2021 Q4-2021 Q1-2022 Q2-2022


(July, Aug, Sep) (Oct, Nov, Dec.) (Jan, Feb, Mar) (April, May, June)
Sector
Package Project Package Project Cost Package Project Package Project
Cost(Cr.) Cost Cost
WB-02
96.46
(Khargone)
Water Supply
WB-01
131.79 
(Burhanpur)

WB-03 WB-04
183.37 37.02
(Chhindwara) (Maheshwar) WB-08
Sewerage  11.70
(Bhedaghat)
WB-05 WB-07
34.07 73.71
(Nasrullaganj) (Shajapur)
Grand Total 4 445.69 2 110.73 1 11.70
PROGRESS SUMMARY FOR WORLD BANK FUNDED AWARDED PACKAGES
Contrac-
tor/
Contract Physical
Commencement Design Financial
# ULB Amount Progres Remarks
/completion Date Progress Progress
including s
O&M in
INR Cr.
12.05.2017 Works were delayed due to
JMC JV
Burhanpur 23.05.2019/31.03.2 delay in availability of lands
1. RAMKY/ 100% 61% 48.01%
(W) 0/ for OHT, change in WTP
156.13
30.09.2021 site etc.

JMC JV 12.05.2017 Works were delayed due to


Khargone
2. RAMKY/ 23.05.2019/29.03.2 100% 68% 58.11% delay in availability of lands
(W)
115.06 0/29.07.2021 for OHT.
21.07.2017 Works were delayed due to
Laxmi
Chhindwara delay in change of land for
3. Civil/ 20.07.2020/28.08.2 100% 46% 33.65%
(S) STP.
225.26 1

01. 10.2018 Inadequate resource


Maheshwar ABEIMA/ 30.09.2020 deployment by contractor.
4. 50% 5% 1.94%
(S) 44.66 1 Extension :
st Contractor is not submitting
31.12.2021 Design and drawing of STP
PROGRESS SUMMARY FOR WORLD BANK FUNDED AWARDED PACKAGES

Contrac-
tor/
Contract Commencement Design Physical Financial
# ULB Remarks
Amount /completion Date Progress Progress Progress
in INR
Cr.

04.09.2018 Land for STP could be


Nasrullaganj ABEIM
5. (S) A/ 39.01 03.09.20/ Ext. 03- 60% 13% 18.83% made available on
09-21 07-06-20.

10.09.2018
Dharampuri P. Das/ Work delayed due to
6. (S) 24.93 09.09.20/ 100% 80% 66.30%
change of STP site.
09-07-2021
06.06.2019 Work Stopped by
P. Das/
7. Shajapur (S) 92.54
80% 5% 1.36% World Bank since Feb.
05.06.2021 2020

Darshil 10.07.2020 All lands allocated by


Bhedaghat
8. (S)
Buildcon 50% 1% 0% District on 25-08-2020.
/ 11.96 09.07.2022 Survey to be started.
Status of Infrastructure Works under MPUDP
PIU: KHARGONE, Name Of Work : BURHANPUR Contractor: M/s JMC Projects Ltd in JV
PACKAGE-WB 01 with M/s Ramky Infrastructure Ltd
WATER SUPPLY PROJECT
Commencement: 12.05.17 Total duration of Project: 1602 days Stipulated Completion: 11.05.19/30.09.2021

Days Completed: 1258 Days, As on-21.10.2020


Financial
Design & Drawing Physical Progress Progress
Salient Features
100 % 61% 48.01%
Anicut : 80m stretch PCC & 0.5 m RCC done 10%
a)Source: Tapti River Intake well: Civil work up to floor slab Completed Mobilization
b)Anicut:7.5MCM Approach bridge first column near intake completed Advance
c)Intake: 10 m Dia. WTP : 50% ( Clariflocculator – 90%, Filter House – 50%, Admin Building - (11.78 Cr)
d)WTP: 50 MLD 85%, SCADA room , Staff qtr wip)
e)Existing OHT: 4 Total Payment
OHT:
f)Proposed OHT: 8 made to
g)Distribution network - 272 Zone 1- Subhash School ( shifted from Shaukat maidan)–Container wall work in contractor
KM progress Rs. 63.27 Cr
h) CWRM & RWRM (Zone 5) Shivaji Nagar – 600KL –Piping arrangement WIP (incl. advance)
22.76 Km (Zone 6) Marchika Garden – 1600KL Piping arrangement WIP
i)Population- (Zone 7A) Pragati Nagar– 1250KL-Civil Work Completed
Base(2018): 2,39,993 (Zone 7B) Nathwada – 1000KL– 19 Nos Foundation upto Ground Level WIP
Intermediate: 3,12,750 (Zone 8A) Transport Nagar 2000KL(Shifted from durga maidan)
Ultimate(48): 3,85,507 –Staging work completed.
CONTRACT AMOUNT (Cr) (Zone 9) Azad Nagar -800KL – Staging work completed.
Physical &
Design build 131.79 (Zone 10) Indra Colony – 800KL –Container wall in progress. Financial
O&M 13.24 Format
Provl Sum 11.10 Total pipes laid= 164.55Km (Including Distribution network, RWRM &
Total Cost 156.13 CWRM)
World Bank Requirement

Description Status
C-ESA Approved
Land Possession /Handover All lands available
CTE Received
Road Cutting Status given in google sheet
shifting of electrical lines/cables /
Transformers etc.
ASI Permission
Railway Crossing Permission
Permissions/NOC status for Burhanpur Water Supply Sub-project
Permissions Depart Whether Applie If not, Reason Way forward
ment obtained d on
(Yes/No)
Road Cutting PWD No 18.03.2 Fee (refundable PG) of Rs.69,20,480/- yet to be Issue of waiver of
019 deposited. PM PIU has written a letter to Fee (Performance
contractor on 22.08.2020 to deposit the FDR Guarantee) needs to
be discussed with
MPPWD.
NHAI No 06.07.2 Contractor has visited the NHAI office on
019 13.08.2020, 21.08.2020 & 22.08.2020.
Action is yet to be taken by NHAI. PM PIU
wrote a reminder letter to Project Director NHAI
on 22.08.2020 for granting the permission. . PM
PIU has submitted required documents to NHAI
vide letter no.1581, dated 23.09.2020. This is
being rigorously followed.
Shifting of MPEB Yes
electrical cables/
Transformers etc.
Railway track Railwa Yes 06.10.2
Crossings y 017
ASI Permission ASI No 02.10.2 In this area exisitng pipes are being replaced and hence, PM to follow up
No permission is required for replacement of existing
017
pipeline.
PIU: KHARGONE, Name Of Work: KHARGONE Contractor: M/s JMC Projects (India)
PACKAGE-WB 02 Limited in JV with M/s Ramky Infrastructure
WATER SUPPLY PROJECT Limited
Commencement: Total duration of Project: 1539 days Days Completed: 1258 Days
12.05.17
Stipulated Completion: 11.05.19 /29.07.2021 As on-21.10.2020
Design & Drawing Physical Progress Financial Progress
Salient Features
100% 65% 58.11%
Intake well- Civil Work Completed 10% Mobilization
a)Source: Kunda River Approach Bridge – Civil Work Completed Advance(9.62 Cr)
b)Anicut: 0.27 MCM,
WTP – 65%
c)Intake: 8 m Dia.
d)Existing WTP: 5 MLD Filter House work in progress; Admin Building Finishing Work Total Payment made to
e)Proposed WTP:30MLD completed; Clarifoculator- Hydro testing work completed; Pump Contractor Rs.56.05
g)Distribution System network house-100%; Cascade aerator-65% Cr. (incl. advance)
– 317 KM
h) CWRM & RWRM :14.07 OHT
Km 1.(Zone 7) Rahimpura– 1150 KL – Piping Arrangement WIP
f)Existing OHT: 3 2.(Zone 3) PHED campus (shifted from New Housing Board)–
g)Proposed OHT: 4 1300KL– Container Wall Work in Progress
h) Population-
Base(2018): 1,47,839 3.(Zone 5) Master Colony – 1250KL–
Intermediate: 1,92,668 Piping Arrangement WIP
Ultimate: 2,45,450 4.(Zone 1) Kila Maidan – 2250KL– Bottom beam work in
Contract Amount (Cr) progress
Physical &
Design build 96.46 Total pipes laid= 208.43 Km (Including distribution network,
Financial Format
O&M 11.60 RWRM & CWRM)
Provl. Sum 7.00
Total Cost 115.06
World Bank Requirement
Description Status
C-ESA Approved
Land Possession /Handover All lands available
CTE Received
Road Cutting Status given in google sheet
shifting of electrical lines/cables /
Transformers etc.
ASI Permission
Railway Crossing Permission

Important Issue: ANICUT CONSTRUCTION


•Construction of Anicut at River Kunda is a Linked Activity to the Khargone WSS.
•A separate Contract has been awarded by MPUDC for construction of anicut
•Work is in progress
•This work was to be financed by NVDA but despite several reminders and follow up
no funds have been received from NVDA.
•A payment of more than Rs 1 Cr is due to the contractor but MPUDC is not able to
make payment due to unavailability of funds.
Permissions/NOC status for Khargone Water Supply Sub-project

Permissions Department Whether Applied on If not, Reason Way


obtained forwar
(Yes/No) d
Road Cutting MPRDC No 06.07.2019 Revised demand draft
submitted to MPRDC on
24.07.2020. Regional
Manager, MPRDC has
written a letter to CGM,
MPRDC on 10.08.2020
for granting the
permission.
PWD Yes 16.03.2018

Shifting of MPEB No 05.01.2018 Fee has been deposited on


electrical 14.08.2020. Shifting of
lines/cables/Tra stay wire at Umarkhali
nsformers etc. road has been completed
and shifting of
transformer at WTP site
is under progress.
PIU: CHHINDWARA Name Of Work: Contractor: M/s Laxmi Civil
PACKAGE-WB 03 Engineering Services Pvt. Ltd.
CHHINDWARA
Kolhapur
SEWERAGE PROJECT

Commencement: Total duration of Project: 1499 days Days Completed: 1188Days


21.07.17
Stipulated Completion: 20.07.2020/28.08.2021 As on-21.10.2020
Design & Drawing Progress Physical Progress Financial Progress
Salient Features
100% 46% 37.67%
1. Total pipes laid :128.67 km 10% Mobilization
a)STP: 28 MLD 2. Manholes constructed: 4191 Advance(9.62 Cr)
b)SPS-1: 13.66 MLD
(deleted) 4. Construction of STP under Progress (80%).
c) Network : 302.64K.M. 5. House service chamber: 900no. Total Payment
d) House service chamber : 6. Construction of SPS-60% made to
10000 no. contractor 69.07
e) Manhole : 11241 no.
f)Population-
Cr (incl. advance)
Base(2018): 1,90,700
Intermediate: 2,38,250
Ultimate: 2,90,918 Physical &
Financial Format
Contract Amount (Cr)
Design build 183.37
O&M 30.89
Provl Sum 11.00
Total Cost 225.26
World Bank Requirement
Description Status
C-ESA Approved
Land Possession /Handover Allotted
CTE Received
Road Cutting Status given in google sheet
shifting of electrical lines/cables /
Transformers etc.
ASI Permission
Railway Crossing Permission
Permissions/NOC status for Chhindwara Sewerage Sub-project
Permissions Department Whether Applied If not, Reason Way forward
obtained on
(Yes/No)

CTE for STP MPPCB Yes 26.09.18

Road Cutting MPRDC/ Yes 20.06.18


PWD/MPRDC
Railway track Railway Yes 19.06.18 Fees deposition is under Fee will be
Crossings process by MPUDC deposited by
31.10.2020
Forest Forest Yes 27.09.18 Fee of (1) NPV- Penalty
Clearance Plantation- Rs. amount of Rs.
6802662/- 3,03,234/-
(2) Supervision Charges deposited for
10 % Rs. 528650/- 2nd stage forest
(3) Fee deposited on clearance on
10.02.2020 and penalty 03.10.2020
amount on 03.10.2020
for Second stage
clearance.
PIU: BHOPAL, Name Of Work: Contractor: M/s ABENGOA AGUA,
Package – WB – 04 MAHESHWAR S.A. in Joint Venture with Bhugan
Infracon Pvt. Ltd
SEWERAGE PROJECT
Commencement: 01.10.18 Total duration of Project: 1187 Days Completed: 751 days
days

Stipulated Completion: 31.12.2021 As on- 21.10.2020

Design & Drawing Progress Physical Progress Financial Progress


Salient Features
50% (Design of STP & MPS Pending) 5% 1.94%
Pipe Laid-7.6Km (out of 33km)
a)STP: 4.91 MLD Total Payment
b)SPS-: 1 No.
Manholes constructed-113 Nos
made to
c) Network: 32.92KM House connection – 1300 Nos
d) Manholes: 1444 no.
Contractor 0.72
e) No. of house connection: Cr
5630
f)Population-
Base(2019): 28152
Intermediate: 39452
Ultimate(2049): 55350
Contract Amount (Cr)
Design build 37.02
O&M 6.60
P. Sum 1.05 Physical &
Total 44.66 Financial Format
World Bank Requirement
Description Status Date of Remarks
Submission
C-ESA Pending at WB 27.05.2020 (3rd C-ESA will have to be
revision) revised based on design of
STP.
ARAP Pending at WB 07.07.2019 World Bank is not ready to
evaluate ARAP unless the
design of STP is finalized

Land Possession Land for STP & MPS Handed over to contractor
/Handover is in possession vide Panchnama dated
03.10.2018
CTE Received 18.02.2019
Road Crossings Road crossings have to be
identified and permission
from concerned department
has to be applied by PIU.
PIU: BHOPAL, Name Of Work: Contractor: M/s Abeinsa Infraestructuras
Package – WB - 05 NASRULLAGANJ Medio Ambiente, S.A. in Joint Venture
with Bhugan Infracon Pvt. Ltd
SEWERAGE PROJECT
Commencement: 04.09.18 Total duration of Project: 1095 Days Completed: 778Days
days
Stipulated Completion: 03.09.2021 As on-21.10.2020
Design & Drawing Progress Physical Progress Financial Progress
Salient Features 70% (Structural Design of STP
13% 18.83%
& MPS left)
5% Mobilization
a)STP: 4.20 MLD advance (1.62 Cr)
b)SPS-: 1No.
Total pipes laid : 19.00KM
c) Network: 46.07KM Manholes constructed: 505 no.
d) Manholes: 1632nos. House Chamber-6 No’s Total Payment
e)Population- house connection made to Contractor
f) Base(2018): 27656 Work of IPS yet to start by contractor
Intermediate: 35944
6.41Cr (incl.
Ultimate (2048): 44232 advance)

Contract Amount Rs.


(Cr)
Design build 34.05
O&M 5.45
P. Sum 1.05
Total 40.54

Physical & Financial


Format
World Bank Requirement
Description Status Date of Remarks
Submission
C-ESA Submitted to The 15-09-2020 C-ESA will have to be
World Bank but (targeted) revised based on design
needs revision of STP.
based on STP
design
Land Possession Land for IPS, STP Land for STP & MPS
/Handover & MPS is in handed over to
possession contractor on 8-6-20.
This delay was due to
public resentment on the
STP site.

CTE Refer next slide


Road Cutting
Permissions/NOC status for Nasrullaganj Sewerage Sub-project

Permissions Department Whether Applied If not, Reason Way


obtained on forward
(Yes/No)
CTE for STP MPPCB Yes 22.01.19

Road Cutting MPRDC No 21.08.19 PM PIU Bhopal Demand


wrote a letter to Note
contractor for received
deposition of Rs. from
12,77,702/- (License MPRDC on
Fees) and Rs. 08.09.2018
5,33,850/- (Bank
Guarantee) on
23.09.2020.
Decision for license
fee is being
discussed at higher
level.
PIU: Indore, Name Of Work: Contractor: M/s P. Das Infratructure,
Package – WB - 06 DHARAMPURI Gujarat
SEWERAGE PROJECT
Commencement: 10.09.18 Total duration of Project: 1033 days Days Completed: 772 Days
Stipulated Completion: 09.07.2021 As on-21.10.2020
Design & Drawing Progress Physical Progress Financial Progress
S.
Name of ULB
no. 100% 80% 66.30%
6. Dharampuri 1. Pipe laid : 16.60KM
Salient Features 2. Manholes constructed: 750no. Total Payment
a)STP: 2.70MLD 3. House Chamber constructed: 1180 no.
b)SPS-: 3 No.
made to
c) Network : 19.27KM 4. STP: 40% Work Completed Contractor
d) Manholes : 848 no. 5. Pumping Stations: 70% Work Completed Rs.12.03 Cr.
e) No. of house
connection: 3269
f)Population-
Base(2019): 18500
Intermediate: 23200
Ultimate (2049): 28800
Contract Amount Rs. (Cr)
Design build 18.14 Physical &
O&M 7.18 Financial
P. Sum 0.80 Format
Total 24.94
World Bank Requirement
Description Status
C-ESA Approved
Land Possession /Handover Allotted
CTE Received
Road Cutting Status given in google sheet
shifting of electrical lines/cables /
Transformers etc.
ASI Permission
Railway Crossing Permission
Permissions/NOC status for Dharampuri Sewerage Sub-project

Permissions Department Whether Applied If not, Reason Way


obtained on forward
(Yes/No)

CTE for STP MPPCB Yes 25.06.20

Road MPRDC No 20.06.20 Demand Draft Rs. Letter has


Cutting 19 13,91,742+Rs. been written
3,11,850= Rs. to MPRDC
17,03,592/- has for waiving
been received from off payment
MPRDC on for
25.07.2020. guarantee.
Decision for
license fee is
being
discussed at
higher level
for Payment.
PIU: UJJAIN, Name Of Work: Contractor: M/s P. Das Infratructure,
Package – WB - 07 SHAJAPUR Gujarat
SEWERAGE PROJECT
Commencement: 06.06.19 Total duration of Project: 730days Days Completed: 503 Days
Stipulated Completion: 31.12.2021 As on-24.08.2020

Financial
Design & Drawing Progress Physical Progress
Salient Features Progress
80% 5% 1.36%
a)STP: 2 no.(11.10 and 1. Topographical Survey, Door Pipe Procured-25KM
0.15MLD) to Door Survey Work approved. Pipe Laid-16.71Km Total payment
b)MPS : 2 No.
c)IPS : 5no.
2. Hydraulic design & drawing Manholes Constructed – 324 =1.0Cr.
c) Network : 105KM of Sewer Network approved. No.
d) Manholes : 3920 no. 3. BEP of STP submitted by House Service Chambers -
e) No. of house connection: contractor and observations 280 Nos.
15415 under compliance from
f)Population- contractor..
Base(2019): 77079
Intermediate: 95724 4, Hydraulic GAD & Structural Work stopped by World
Ultimate (2049): 119576 design & drawing of IPS 1 to 5 Bank vide email dated
Contract Amount Rs. has been approved. 13.02.2020
(Cr) Hydraulic & GAD of MPS
Design build 73.72 approved
O&M 17.21
P. Sum 02.25 Physical &
Total 93.18 Financial
Format
World Bank Requirement

Description Status Date of Remarks


Submission
C-ESA Pending at WB 20.09.2020 (7th compliance of RSA
revision) observations sent to
WB on 21.10.2020
Land Possession STP Land Allotted.
/Handover Possession of land
for all IPS & MPS
are given by
District Collector
vide letter dated
10.09.2020.
CTE
Road Cutting Status given in the next slide
Permissions/NOC status for Shajapur Sewerage Sub-project
Permissions Department Whether Applied If not, Reason Way
obtained on forward
(Yes/No)
CTE for STP MPPCB No Applied on PM PIU has uploaded the
02.12.2019 required document for
generation of fee thus fee
for STP-1
Rs. 60,000/-has generated
on 11.07.2020.
PM PIU Ujjain sent a letter
to Contractor on
14.07.2020 for deposition
of fee Rs. 60,000/- to
MPPCB.
Waiting of lifting of ban on
construction activity by
The World Bank.
Road Cutting MPRDC No 11.07.2020 Fees is to be deposited
IPS Land Yes 13.11.2019 Allotted to contractor vide
letter of CMO dated
26.06.2020
River/ Nala WRD Yes 13.11.2019
Crossing
PIU: UJJAIN, Name Of Work: BHEDAGHAT Contractor: M/s Darshil
Package – WB - 08 SEWERAGE PROJECT Buildcon, Gujarat

Commencement: Total duration of Project: 730days Days Completed: 103 days


10.07.2020
Stipulated Completion: 09.07.2022 As on-24.08.2020
Financial
Design & Drawing Progress Physical Progress
Salient Features Progress
40% 1% 0%
a)STP: 3 no.(0.43,0.22 & 0.11 Door to Door survey.
MLD) Design of sewer network under approval.
b)PTP : 2 No.( 0.06 & 0.06
MLD)
c) Network : 15.8KM
d) Manholes : 237 no.
e) No. of house connection:
450
f)Population-
Base(2019): 5364
Intermediate: 7488
Ultimate (2049): 10064
Contract Amount Rs.
(Cr)
Design build 11.70
O&M 2.02
Physical &
P. Sum 0.25
Financial
Total 13.97
Format
World Bank Requirement

Description Status Target Date of Remarks


Submission
C -ESA Under 30.11.2020
Preparation
Land All lands in
Possession possession
/Handover
Panchnama given
on 25.08.2020.
Environmental & Social Safeguard
/ soft issues

36
Status of ESA/C-ESA/ARAP
Status of ESA approvals
Sewda ESA- Approved by WB
Shahdol ESA –pending at WB

Status of C-ESA approvals


Burhanpur C-ESA - Approved by WB
Khargone C-ESA- Approved by WB
Khargone ARAP – Approved by WB
Chhindwara C-ESA- Approved by WB
Dharampuri C-ESA – Approved by WB
Shajapur C-ESA- compliance of RSA observations sent to WB on 21.10.2020
Maheshwar C-ESA – may need revision
Maheshwar ARAP- may need revision
Nasrullaganj C-ESA – may need revision
Bhedaghat C-ESA – targeted to be submitted to The WB by the end of Nov 20
Other recent submission’s to World Bank

Key deliverables
 EHS guidelines for work sites.
 Emergency Preparedness Procedure (7 subprojects) .
 Guidelines wrt. COVID 19 with suggested monitoring mechanism.
 Standard Labour Management Procedure (LMP) for 7 subprojects.
 A Guiding note on Hazardous Identification and Risk Assessment
(HIRA)
 Action Plan for strengthening of safeguard services.
 Action Plan for the compliance of Environmental, Social, Health
and safety Audit
 Action plan for strengthening of GRM under MPUDP
 Status of implementation of ESHS action plan
38
Emerging priorities
Few more Safeguard services outputs (Env. & Social)- to be sent to WB

1. EHS Training & quarterly follow ups


2. Site Documents and readiness including incidence record
3. Mechanism to review, occupational safety and health
performance
4. Process formulation to record, track and close EHS concern
and provide feedback to workers /employee to raise the
concern.
5. SOP /Note to develop a system to always provide secondary
containment for chemicals.

39
Issues regarding Environment & Social Safeguards

• Inadequate Staffing at contractor level wrt. Safeguard


services.
• Capacity deficit to ensure the implementation of ESMF at
field team.
• C-ESA of Maheshwar pending due to delay non approval of
Basic Engineering Package.
• Flushing plan yet to be submitted by the contractor for
Maheshwar.
41