Chaired by :
Mr. Mahamaya Prasad Sukla, Executive Director-Works
Coordinated by
Mr. A. K. Dewangan, General Manager-QCD and MR
Attended by
HoDs, Steering Committee & Core Team members.
SMC Power Generation Limited, engaged in steel making and power generation aims to satisfy
all its stakeholders by focusing on delivery of quality products with special emphasis on
environment friendly, safe, healthy, energy efficient and sustainable work practices.
1 Price
2 Delivery
3 Response
4 Quality of the Product
01 30.01.15 Side sheeting near PSB bag filter area 1.00 Last week Apr’15 Completed
02 30.01.15 Side sheeting at dust silo unloading point 0.30 Last week Apr’15 Completed
03 30.01.15 Side sheeting at Char bunker un-loading point 0.50 Last week Apr’15 Completed
04 30.01.15 Preparation of vehicle washing ramp with oil water 2.60 Last week Apr’15 Completed
separator at automobile section
05 30.01.15 Plantation inside & outside the plant 0.60 Last week Feb’15 Completed
06 30.01.15 Development of Used oil storing area 0.50 Last week Feb’15 Completed
07 30.01.15 Development of Hazardous waste disposal pit 0.20 Last week Completed
March’15
08 30.01.15 Provision of hot water at canteen 0.20 Last week Feb’15 Completed
09 30.01.15 Provision of PPE for food handlers 0.05 Last week Feb’15 Completed
10 30.01.15 Provision of fly catcher at canteen 0.20 Last week Completed
March’15
11 30.01.15 Provision of Bio-medical waste bins at first aid 0.01 Last week Feb’15 Completed
Centre
12 30.01.15 Development of Bio-Medical waste disposal pit 0.05 Last week Completed
March’15
13 30.01.15 Development of lab waste water disposal facility 0.25 Last week Feb’15 Completed
14 30.01.15 Soak pit for canteen waste 1.20 Last week Apr’18 Completed
15 30.01.15 Stationary water sprinkler laying 0.50 Last week of Completed
March’15
16 30.01.15 Development of fresh oil storing area 0.50 Last week Feb’15 Completed
17 30.01.15 Eye wash at Q.C. building 0.10 Last week of Feb’15 Completed
18 31.03.15 Fire hydrant line in RMP mega shed 4.00 Last week of Nov’15 Completed
19 30.08.15 Concrete road in front of rolling mill and Admin building 14.82 Last week of Dec’15 Completed
20 30.11.15 Stationary water sprinkler laying 0.50 Last week of Jan’16 Completed
21 30.11.15 Hot billet conveyer from CCM to RLMD 30.00 Last week of Completed
March’16
22 03.04.16 Electronics display board at main gate for display of 1.00 30.06.2016 Completed
environmental parameters
23 01.12.16 Widening of swiveling hood of the induction furnaces 1.00 30.04.2016 Completed
24 01.12.16 RCC internal Road 67.22 30.06.2016 Completed
from SMS to Dumping yard
from stores to PSB area
from Kiln-1 to Mist cooling system
25 22.04.16 Insulation of pipeline and hot surface of boiler & turbine 4.00 31.03.2017 Completed
pipelines
26 22.04.16 Application of glass filled polymer coating in CW rotating 5.50 31.03.2017 Completed
& static internal body
27 22.04.16 Replacement of FRP blade in place of metal (aluminum) 7.50 31.10.2018 Completed
blades in SMS and RMLD existing cooling tower
28 22.04.16 Installation of VFD in AFBC FD fan 61.00 31.08.2018 Completed
29 22.04.16 Replacement of clarified pump with suitable energy 2.00 31.03.2017 Completed
efficient pump
30 20.06.18 Twine ladle car -15T liquid LM capacity for double strand 30.00 Dec’18 Completed
CCM 6/11
31 10.09.18 Installation of Ladle refining furnace capacity 15T 235.00 June’19 Completed
32 02.04.18 Installation of water cooler for different location for 4.00 May’18 Completed
providing safe drinking water
33 02.01.18 Telescopic chute installation at discharge end of silo 22.00 Nov’18 Completed
6 pieces
34 02.05.18 Modification of PSB bag filter unit 14.00 Dec’18 Completed
35 30.04.18 Concreting of SID day Bin area bin Floor 40.00 Dec’18 Completed
36 13.12.17 Concreting of TMT Yard 42.00 Sept’18 Completed
37 23.03.18 Concreting of Middle area floor between line one 14.00 Jan’19 Completed
and line two
38 02.05.19 Coil diameter change in furnace no. 2 & 3 from 325.00 Feb’20 Completed
56inch to 59 Inch
39 10.11.19 Installation of Iron Ore crusher 44.00 Apr’20 Completed
40 01.12.19 Installation of Ladle Refining Furnace in SMS 325.00 Jan’20 Completed
process
41 02.04.20 Wheel washing facility to be developed 11.00 Oct’20 Completed
42 04.07.20 Enhancement of turbine capacity from 8MW to 12.6 1100.00 Nov’20 Completed
MW
43 04.04.20 Installation of Bundling Machines No.3 & 4 250.00 March’21 Completed
44 02.04.20 Rough Mill-2 extension 27.00 Aug’20 Completed
45 04.05.20 Flouring of Rolling mill plant area 18.00 Aug’20 Completed
46 10.08.20 Kiln-2 re castable 205.00 Sept’20 Completed
T O T A L 2913.30
• No product non-conformity
• No environmental non-conformities are detected during
environmental monitoring and measurement
• No occupational health and safety non-conformities are
detected during OHS monitoring and measurement but the
actions are found to be taken on the safety visits conducted
Incidents:
Sl. Incident 2020-21 (April 2020 to 2021-22 (April 2021 to
NO. March 2021) Dec 2021)
01 Reportable Accident Nil Nil
02 Fist Aid Cases 36 26
03 Near Miss Cases reported 08 05
04 Fatal Case Nil Nil
All above incidents found to be investigated and accordingly
corrective actions have been planed and implemented.
Corrective actions taken were reviewed and found effective.
OUTPUT
Action planned/ decision taken and Resource identified
Ref. Action Plan Review Report
&
Ref. Annual Objective Achievement Plan for 2020-21