Introduction

• Bill of Quantities

• What?

• Why?

• Who?
Methodology
 RS Means 2011 Data [online version]

 Corrected with historical index using:

 191.2 as 2011 Index and 239.1 as Jan 2020 Index (could not find 2021 index)

 RS Means Abbreviations Directory for units of items (SF, Ea., LM, CY etc.)

 Additional online sources for estimating certain materials and work


Methodology
M Yard
Description Quantity Unit Quantity Unit Rate Amount Remarks Assumptions/Notes
Structural concrete, ready mix, normal
weight, 3500 psi, includes local aggregate,
P.C.C 10 mm Thick 33105350200 sand, Portland cement and water,
delivered, excludes all additives and
50M3 65.4CY $ 118.00 $ 7,717.20 treatments
Structural concrete, in place, pile cap
(3000 psi), square or rectangular, under
Pile caps 33053405900 10C.Y., includes forms(4 uses),
reinforcing steel, concrete, placing and
620M3 810.96CY $ 302.48 $ 245,299.18 finishing
Snap tie beam hanger, for CIP forms,
Tie Beam and STB 31505305000
85M3 111.18CY $ 350.00 $ 38,913.00 3000#, to 30"
Structural concrete, in place, spread
footing (3000 psi), under 1 C.Y., includes
Column Necks 33053403800
forms, reinforcing steel, concrete, placing
30M3 39.24CY $ 428.92 $ 16,830.82 and finishing
Structural concrete, in place, free-standing
wall (3000 psi), 8" thick x 8' high,
R.C.C Neck Core Walls 33053404200
includes forms(4 uses), reinforcing steel,
20M3 26.16CY $ 481.35 $ 12,592.12 concrete, placing and finishing
Methodology
Meters Feet USD DHS USD  
Description Quantity Unit Quantity Unit Rate Amount Amount Remark Assumptions/Notes

FLOORING                
Marble/Granite 450 Dhs/m^2 184M2    $ 450.0 AED 82,800.0 $ 22,356.0 Rate Provided  
Granite Ceramic 25 Dhs/m^2 7455M2    $ 25.0 AED 186,375.0 $ 50,321.3 Rate Provided  
Non slip Ceramic 20 Dhs/m^2 1697M2    $ 20.0 AED 33,940.0 $ 9,163.8 Rate Provided  

Provisional Sum            
Allow a P sum for the Assume Aluminum door
Aluminium works   PC Sum   $ 12,295.00 https://civiljungle. fixtures
Allow for any profits, attendance, com/aluminum-do
installation builders work and or/ Including all profit and
other overheads on the above P overheads and material and
system. 10%     $ 1,229.50   labor costs
Allow a P sum for cradels   PC Sum   $ 4,450.00 15426500020  

Allow for any profits, attendance, Swing staging, hand operated


installation builders work and hoist, steel cable type, buy, 500
other overheads on the above P lb capacity, 60' cables, 2' wide x
system. 10%     $ 445.00   24' long
Sources
Result
 The final total cost of the project came out to be:

$14,851,448.85
 Rounded up

$ 14.9 Million