IT PROJECT

PT ESPORTS STAR INDONESIA


TABLE OF CONTENTS
PROJECT
01 OBJECTIVE
PROJECT
02 TIMELINE
PROJECT
03 TEAM
PROJECT
01 OBJECTIVE
1.
2.
3.
4.
Cloud Infrastructure
Website Fight of Legends
Integration 3RD Party Payment
ESI Tools Dashboard
PROJECT OBJECTIVE

1. CLOUD 3. ESI TOOLS


INFRASTUCTURE DASHBOARD
Create Infrastructure and Landing Zone Create internal system data management to
(Architecture Design) to accomodate all aplication collects, create, monitors, and displays complex
such as VM for Game Developer & Game data via interactive and customizable dahsboards
Publishing, Firewall, etc. and reports.

2. WEBSITE FIGHT OF 4. INTEGRATION 3RD PARTY


LEGENDS PAYMENT
Build a Game Profile website that create with UI Setup and integration with multiple 3rd party
design to branding game, promote, or share games payment to have more payment channel for
news & event. topup.
PROJECT
TIMELINE
1. Project Process
02
2. Phase & Timeline
PROJECT PROCESS

PHASE 1 PHASE 2 PHASE 4


Initiation Building PHASE 3 Control
Execution
& & (Launch) &
Planning Testing Monitoring

1.Kick Off Meeting 1.Propose Approval 1.Change Request 1.Development


2.Project Budget 2.Building (Sandbox) 2.Final Approval 2.Maintenance
3.Work Breakdown 3.Testing 3.Testing 3.Project Status
Structure 4.Launch (Production) Report
4.Project Summary 5.Project Status
Report
CLOUD INFRASTRUCTURE
Timeline Detail
Phase 1:
1. Kickoff Meeting = 5 days
2. Gathering Information = 12 days
3. Research Cloud = 26 days
Total Phase 1 = 47 days

Phase 2:
1. Compare Cloud = 33 days
2. Propose IOM = 25 days
Total Phase 2 = 68 days
Phase 3:
1. Landing Zone Meeting = 5 days
2. Deploy Landing Zone = 19 days
3. Launch (Production) = 12 days
Total Phase 3 = 40 days

Phase 4:
1. Monitoring = ~
2. Status Report = Daily
Total Phase 4 = ~
Start Project : 13 June 2022
End Project (Phase 3) : 18 Nov
Project Deadline until launch : 20 Nov
Status Project : Completed
WEBSITE FIGHT OF LEGENDS
Timeline Detail
Phase 1:
1. Kickoff Meeting = 5 days
2. Gathering Information = 5 days
3. Mockup Website = 19 days
Total Phase 1 = 26 days

Phase 2:
1. Design Approval = 5 days
2. Building Web (Staging) = 19 days
3. Testing = 12 days
Total Phase 2 = 33 days
Phase 3:
1. Collect Testing Info = 5 days
2. Fixing & Final Approval = 33 days
3. Launch (Production) = 40 days
Total Phase 3 = 75 days
Phase 4:
1. Monitoring = ~
2. Development = ~
Total Phase 4 = ~
Start Project : 4 Jul 2022
End Project (Phase 3) : 18 Nov
Project Deadline until launch : 20 Nov
Status Project : Completed
ESI TOOLS DASHBOARD
Timeline Detail
Phase 1:
1. Kickoff Meeting = 5 days
2. Collect User Needs = 5 days
3. Design System = 3 days
Total Phase 1 = 17 days

Phase 2:
1. Build System = 9 days
2. Presentation = 1 day
3. User Test = 5 days
Total Phase 2 = 16 days
Phase 3:
1. Collect User Feedback = 2 days
2. Modif / Rev System = 10 days
3. Create User Guide = 5 days
4. Launch = 12 days
Total Phase 3 = 26 days
Phase 4:
1. Control, Monitoring, Development,
Maintenance = ~
Total Phase 4 = ~
Start Project : 19 Sep 2022
End Project (Phase 3) : 18 Nov
Project Deadline until launch : 20 Nov
Status Project : Completed
3RD PARTY PAYMENT
Timeline Detail
Phase 1:
1. Kickoff Meeting = 5 days
2. Collect API Document = 20 days
3. Analysis Document = 13 days
Total Phase 1 = 68 days

Phase 2:
1. Setup Environment = 19 days
2. Starting Integration (Sandbox) = 26 days
3. Testing = 12 days
Total Phase 2 = 68 days

Phase 3:
1. Collect Testing Info= 5 days
2. Starting Integration (Production) = 40
days
3. Final Test = 12 days
4. Launch = 5 days
Total Phase 3 = 82 days

Phase 4:
1. Control, Monitoring, Development,
Maintenance = ~
Total Phase 4 = ~

Start Project : 3 Oct 2022


End Project (Phase 3) : Mid June
Project Deadline until launch : Mid June
Status Project : On Hold in Phase 3 (Collect
Testing Information) due issue with Game
Developer
03 PROJECT
TEAM
Meet The Team
THANK YOU

PT ESPORTS STAR INDONESIA