Professional Documents
Culture Documents
Ratings
TOPICS
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
1. Substation Equipment
Circuit breakers;
Isolators or disconnectors;
Power transformers;
Lightning arresters;
Bus bars (rigid or flexible);
Earthing transformers;
Auxiliary transformers;
Instrument transformers;
Compensation equipment (Shunt rectors, capacitor
banks);
Earthing and Lightning Protection systems;
Substation protection and control;
SCADA and Communication Equipment;
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
1. Substation Equipment, cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
2. Functions of Substation Equipment
Equipment Function
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND
PICTURE
3.1 Circuit Breaker
a) Type of circuit breakers
- Bulk oil
- Mini oil
- Air blast
- Vacuum
- SF6
b) Introduction to SF6
3.2 Disconnector
c) Type of disconnectors
- Vertical break
- Centre break
- Double side break
- Pantograph
- Earthing disconnector
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3.1 CIRCUIT-BREAKER
Standards/Codes
ANSI/IEEE C37-04/06
AC High Voltage
Circuit-Breaker Rated
on a Symmetrical
Current Basis
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3.1 CIRCUIT-BREAKER, cont
1) Interrupter unit
2) Post insulator
3) Pillar
4) Control cabinet
5) Drive housing
1) Interrupter unit
2) Post insulator
3) Pillar
4) Control cabinet
5) Drive housing
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3.2 DISCONNECTOR
Isolators or Disconnector
• Essentially off load devices
• Capable of dealing with small charging currents of bus
bars and connections
• Its design is closely related to the design of
substations
• Isolator design is considered in the following aspects:
Space Factor
Insulation Security
Standardisation
Ease of Maintenance and Cost
Standards/Codes
ANSI/IEEE C37-30 Standard Requirement for High Voltage
Switches
IEC 62271-102 High Voltage Alternating-Current
Disconnector and Earth Switches
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3.2 DISCONNECTOR, cont
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3.2 DISCONNECTOR, cont
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3.2 DISCONNECTOR, cont
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND
PICTURE, cont.
a) Potential transformer
- Main characteristics
- Type of Potential transformers
b) Current transformer
- Main characteristics
- Type of current transformers
c) Earthing transformer
- Main characteristics
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
3.3 Voltage Transformer
Electromagnetic Voltage
Transformers, generally referred
to as Potential Transformers
(PT), and Capacitor Voltage
Transformers (CVT) are used for
protection and metering.
The secondary windings are rated
for 110 or 100 / √3 Volts
• Isolate meters and relays from
high voltage
• Can be connected phase-to-
ground (grounded wye
connection) or phase-to-phase
(open delta)
• Secondary voltage between 100
to 120 V phase-to-phase with
one or two windings
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
Standards/Codes
CEI/IEC 60099
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
3.5 Transformer
Transformer is a static electric
machine which changes the level
of voltage and current in the
circuit without changing the
power and supply frequency.
Standards/Codes
CEI/IEC 60076.1 Power
Transformers–General
CEI/IEC 60076.6 Reactors
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
a) Dehydrating breather
b) Gas relay (Bucholz)
c) Oil level indicator
d) Pressure relief device
e) Oil temperature indicator
f) Winding temperature indicator
g) Control cabinet
h) Radiators
i) Tap changer
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
A transformer consisting of three pairs
A transformer with a single electric
of winding used to transform a set of
Construction winding, which can be used as a step-
three-phase voltages from one voltage down or step-up device.
level to another.
Primary and secondary windings are Primary and secondary windings are
Insulation
insulated electrically. not insulated electrically.
Representation
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
3. MAJOR SUBSTATION EQUIPMENT TYPES AND PICTURE, cont.
Cooling Systems
• Can be a wye-delta
transformer with a resistor
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.1 HV switchgear ratings cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.1 HV switchgear ratings
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.2 HV Circuit Breaker rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.2 HV Circuit Breaker ratings
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.3 HV Disconnector rating
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.3 HV Disconnector rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.3 HV Disconnector rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating
Ratings
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.4 Current Transformers rating cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.5 HV Capacitive Voltage Transformer rating
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.5 HV Capacitive Voltage Transformer rating
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.5 HV Capacitive Voltage Transformer rating
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.5 HV Capacitive Voltage Transformer rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.5 HV Capacitive Voltage Transformer rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.5 HV Capacitive Voltage Transformer rating
cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.6 Lightning Arrester rating
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.6 Lightning Arrester rating
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.6 Lightning Arrester rating cont.
Step no 1
Step no 2
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
4.6 Lightning Arrester rating cont.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
4. MAJOR SUBSTATION EQUIPMENT RATING CALCULATIONS
Step no 3
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
5. Trainers Example
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
5. Trainers Example
Capacitive Voltage Transformers, 230/√3:0.1/√3:0.1/√3 :0.1/√3kV
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
5. Trainers Example
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023