Training on
Planning & Scheduling
using
Oracle Primavera P6 Professional (P6 22.12)
for
OROMIA ENGINEERING COORPORATION
Presenter: Matiwos Tsegaye
Planning Engineer, MSc CoTM, Practicing Construction Engineer in PM [PPECM/1945]
OCT 2023
CONTENTS (SCHEDULE) •Key Problems Const. Sector [SOU]
Day 1 • Basic Theory & Practices: PM
(Planning & Scheduling)
• P6 Interface & Windows customize,
Define-Scope Day 2 EPS management
(WBS-tasks, site layout, • Schedule management strategy
Code, UDF Organize)
8.2
8 7.3
7 6.5 6.3
5
5 3.5
4
3 4.5
3 3.5
Outcomes
Actions/
1. Aware key problems of construction sector Activities
4. Components of
1. Goal Value Delivery,
(Output) [Protifolio-
PROJECT Program-Project
with
Operation] &
OPM & OPM3
6. Competency
5. Environment
(PESTLE)
PROJECT PLANNING
[PLANINING PROCESS]
PLANNING BASICS
Planning
• One Element of PM
• Setting goal → Identify
activities & inputs →
to achieve the goal
• while project Customer
Satisf.
constraints (2R2C3S) Cost Scope
• Establish metrics & KPI
→ to measure progress Project
toward goal Sched.
Risk
Resource
PLANNING BASICS…
Planning Benefit
• Facilitate later
accomplishment
Meredith, 2018 “Strategic Project Management”
Planning output
• Project Management Plan (integrate all aspects)
SCHEDULE MANAGEMENT
PROCESS
[PROJECT SCHEDULING]
SCHEDULE BASICS (DEFINATION)
Schedule/Time Management ROOFING 00
Jun-20
• one element of Planning
10
& Project Management FINISHING
Dec-20
• Develope Roadmap to
Foundation
execute activities Feb-10
20 WALL-
Finishing
• Set start & finish times & 05
8
Aug-20
1. Design
2. procurement
3. Installation/build
4. quality control (QM FIDIC 4.9)
5. resources
6. communications (submittal, approval)
SCHEDULE MANAGEMENT FRAMEWORK
MODEL
Well-defined General
Procedure/GUIDE:
Sequential/Iterative/Rolling wave
PURPOSE METHODS
COMPITENCY Detail procedure/Process: Input,
: PM-SP tools &Techniques, outputs:
CPM/PERT
05 Monitor &
04 & Duration) Control Schedule
Step 05
Estimate (Resource
&
Develop Scedule Step 04
03 Constraints
Sequence &
Step 03 (dependency-order,
02
constraints,
Define Calendar)
Scope [WBS, Step 02
Activities,
Milestones,
Codes], Site Step 01 01 Plan
Mngt
Schedule
No
• work flow (cycle time, No
variation, supervisor-crew ratio)
Yes
• resource availability
6. Risk Analysis
(contingency, monitoring
• cashflow meet
contractual requirement &
priority) contractor capacity?
SCHEDULING METHOD..... (INPUTS)
PPA 2011/FIDIC 2017
SCHEDULE MANAGEMENT METHOD (INPUTS, TOOLS&TECH,
OUTPUTS)
• Business case (feasibility report at design stage)
• Contract Document (Dwg, BOQ, GCC&SCC, Specs)
INPUTS • EEF: socioeconomic studies [resource availability & culture [internal/external], Weather data
(Artifacts) • EEF: Industry Schedule guide & Productivity standards,
• OPA: Organization plans [Strategic & portfolio plan], organizational
standards/guides
Process
TOOLS & TECHNIQUES
1. Tools: P6 PM, Risk Master, ASTA, Output (Artifacts)
TILOS, MSP , Excel
2. Techniques: 1. Gant chart/TSLD/TLD/LOB
• Determinastic & 3-Point Estimating 2. Network diagram,
• Network Analysis, Schedule compression 3. Resource schedule &
• Expert Judgment, Delphi Organogram/Cashflow
• Checklists (verfying compliance) 4. Narrative Report/MS: Site
• Claim & Progress evaluation layout, risk manag.Plan
• Document Analysis [to gain project requirements] 5. Progress Dashboard
Scheduling Method..... (TECHNIQUES & OUTPUTS)
Techniques
1. CPM: determinastic
project period & activity
sequence determination,
excluding resource constraints
2. PERT: Probablstic duration
estimation
3. Critical Chain Method
(CCM): Resource constraint
driven CPM
Output of Schedule
1. Activityschedule
2. Resource Schedule
3. Cashflow Schedule
Scheduling Method... (TOOLS or PM Software)
Project Management Software
• Purpose: To respond dynamic nature of project execution
Benefits of PM Software:
1. Speed, acuracy & flexibility in: Data intry, Analysis/forecasting, record & Report
scope
Schedule
sequence
Creation & Estimate & Assign resource
Schedule Develop
Develop schedule
D2(31%)
Manage
ment Physical work
Schedule Measuring-Analysis- Effort
Monitoring & Reporting Duration elapsed
Controlling Revised Schedule Test, safety
D3(35%) EVM
1. Starting Primavera P6
2. User Interface screen
3. Windows & their functions
4. Admin & User preferences
5. Creating EPS & Project
6. Customizing Columns & Tabs
7. Customize layout (Modify, Save, Import/Export)
8. Import Export Project & resource
P6 INTERFACE
STARTING P6
USER PREFERENCE
Under Menu → edit →User Preference
1. Time Units→
• Unit of Time →set “hour” &
Decimals “1”
• Duration format →set “day “ &
Decimal “0”
• Units/Time format → set “show as
units/duration (4h/d)”
ADMIN & USER PREFERENCES
USER PREFERENCE...
Under Menu → edit →User Preference
2. Dates→
• Date format→set “day, month, year”
• Opion→tick “months name“ & untick
“leading zero “, Separate “/”
• Time→ set “do not show time”
3. Currency→
• Currency option
→set seen in
snapshot
ADMIN & USER PREFERENCES
USER PREFERENCE... 5. Application→
Under Menu → edit →User
Preference • Start up window → set “Project”
4. Assistance→ • Grouping & Sorting, Codes
• Wizard →set seen in snapshot set as snap shot
ADMIN & USER PREFERENCES
USER PREFERENCE...
Under Menu → edit →User Preference 7. Resource Analysis→
6. Password→ • set all preference as snap shot
• You can set any value
ADMIN & USER PREFERENCES
USER PREFERENCE...
Under Menu → edit →User Preference 9. Startup filter→
8. Calculation→ • set all preference as snap shot
• set all preference as snap shot
CREATE EPS & PROJECT
Create EPS
• Click Enterprise under menu → add →adjust by
right/left/up/down arrow
• View in Table/Chart → Print
CREATE EPS & PROJECT...
CREATE PROJECT
Create Project (under Project window) →
edit project start & end date
To edit start & finish date → detail tab
• Dates Tab →set planned start date, data
date, must finish by (contract date)
CUSTOMIZE DETAIL TABS & COLOMN
Customize Tabs
1. On activity window →click on bottom layout detail bar →right click on
detail tab area → customize →select Available Tabs (on left) →click on
move to right arrow →apply →ok
Note:
• During export make sure desired project to be
exported is opened
• Multiple projects can be exported
• You can export to excel, then open exported
excel file & add activity or resource date you
want (number format need to be converted into
text under data menu ”text to column”), then
import back to P6 (use update existing)
PLAN
SCHEDULING
SET SCHEDULING PARAMETERS
(SETTINGS, PERFORMANCE TYPE &
THRESHOLD/UDF, CRITICAL PATH
DEFINITION)
SET SCHEDULING PARAMETERS
Set Scheduling Parameters
1. Under project window select project → detail
tab
• Dates Tab →set planned start date, data date,
must finish by (contract date)
SET SCHEDULING PARAMETERS
Set Scheduling Parameters
1. Under project window select
project → detail tab
• Settings Tab →critical path
definition →set Longest
Path
• Default Tab→ performance
complete type (set physical)
& Default calendar (set 7
day workweek)
• Calculations Tab → Default
price/unit (set 1) & set
others to default p6 value
SET SCHEDULING PARAMETERS
Set Scheduling Parameters
1.Under Menu → admin
preference (or under WBS window detail
tab) → Earned Value
• Techniques for computing
performance % complete
→set activity % complete
• Techniques for computing
Estimate at completion
(ETC)→set PF 1
SET SCHEDULING PARAMETERS
Set Scheduling Parameters
1.Under Menu →Enterprise
• User defined fields → select field
type as project → add field (status
indicator → select data type as
indicator
• project codes → create required
parameters (status indicator its
bands)
SET SCHEDULING PARAMETERS
Set Scheduling Parameters
1. Under Menu → admin Category
• Baseline type → add baseline type
& rename it