Professional Documents
Culture Documents
Settlement(preloading/precompression)
March 2022
1
1. Introduction
❖ The basic concept of preloading technology is to reduce void ratio
(i.e., compressibility) of geomaterial through consolidation (i.e.,
dissipation of excess pore water pressure) by applying loads on
ground surface for a certain time period and then removing it for
construction of a permanent structure.
❖For soft clays, the consolidation may take longer time to complete due
to their low permeability.
❖If the time for preloading and construction of the structure exceeds
the available time, vertical drains can be installed to shorten
drainage distance thus accelerating the rate of consolidation
and reducing the time for soil consolidation and settlement
3
Introduction
❖ The applied load in preloading can be fill, vacuum pressure, or a
combination of fill and vacuum pressure.
❖Vertical drains can be used to shorten the time for preloading if time
is a major concern.
❖ Vacuum preloading is more suitable for the areas where soils are
too weak to support construction equipment and fill, and/or fill
material is expensive and not readily available. 5
Principle of Pre - compression
𝑪𝒄 𝑯 𝒄 𝝈′𝒐 + ∆𝝈′𝒑
𝑺𝒄 𝒑 = 𝐥𝐨𝐠 ′ −−− −Eqn (1)
𝟏+𝒆 𝝈𝒐
❑Hence, if a surcharge of ∆𝝈′𝒑 + ∆𝝈′𝒇 is placed on the ground, the
primary consolidation settlement will Be
❑At that time, if the total surcharge is removed and a structure with a
permanent load per unit area of ∆𝜎𝑝′ is built, no appreciable
settlement will occur.
Advantages
➢It is often cost effective if fill material is readily available or
part of a permanent structure.
10
Principle of Pre - compression
➢From the figure 4(b), under a surcharge of ∆𝜎𝑝′ + ∆𝜎𝑓′ the degree
of consolidation at time 𝑡2 after the application of load is
𝑺𝒄 𝒑
𝑼= −− −𝑬𝒒𝒏 (𝟑)
𝑺𝒄 𝒑+𝒇
Substituting eqn (1) and (2) in eqn (3) we get
----Eqn. 4
11
Principle of Pre - compression
12
Principle of Pre - compression
Figure 6.
13
Cont. . .
In some cases, net continuous settlement might result.
𝟐 −𝑴𝟐 𝑻
now from eqn. 𝑼 = 𝟏 − σ∞
𝒎=𝟎 𝟐 𝒆 𝒗
𝑴
𝐔 = 𝐟 𝐓𝐯
𝐂𝐯 𝐭 𝟐
𝐖𝐡𝐞𝐫𝐞 𝐔 = 𝐦𝐢𝐝𝐩𝐥𝐚𝐧𝐞 𝐝𝐞𝐠𝐫𝐞𝐞 𝐨𝐟 𝐜𝐨𝐧𝐬𝐨𝐥𝐢𝐝𝐚𝐭𝐢𝐨𝐧 , 𝐓𝐯 = 𝐭𝐢𝐦𝐞 𝐟𝐚𝐜𝐭𝐨𝐫 =
𝐇𝟐
𝐂𝐯 = 𝐜𝐨𝐞𝐟𝐟𝐢𝐜𝐢𝐞𝐧𝐭 𝐨𝐟 𝐜𝐨𝐧𝐬𝐨𝐥𝐢𝐝𝐚𝐭𝐢𝐨𝐧 , 𝐭 𝟐 = 𝐭𝐢𝐦𝐞, 𝐇 = 𝐦𝐚𝐱𝐢𝐦𝐮𝐦 𝐝𝐫𝐚𝐢𝐧𝐚𝐠𝐞
𝐇𝐂
𝐩𝐚𝐭𝐡 ( = 𝐟𝐨𝐫 𝐭𝐰𝐨 − 𝐰𝐚𝐲 𝐝𝐫𝐚𝐢𝐧𝐚𝐠𝐞 𝐚𝐧𝐝 𝐇𝐂 𝐟𝐨𝐫 𝐨𝐧𝐞 𝐰𝐚𝐲 𝐝𝐫𝐚𝐢𝐧𝐚𝐠𝐞)
𝟐 14
Cont. . .
• In such a case, obtain 𝝈′𝒐 , ∆𝝈′𝒑 and solve for U, using Eq. (4)
or Fig. 3.
• For this value of U, obtain 𝑻𝒗 from Figure 5. Then
𝑻𝒗 𝑯𝟐
𝒕𝟐 =
𝑪𝒗
16
Procedure for obtaining precompression parameters
2. For a specified value of 𝑡2 , ∆𝜎𝑓′ must be obtained.
∆𝜎𝑓′
value of , and then calculate ∆𝜎𝑓′ .
∆𝜎𝑝′
17
Example
1. During the construction of a highways bridge, the average
permanent load on the clay layer is expected to increase by about
115𝑘𝑁/𝑚2 . The average effective overburden pressure at the middle
of the clay layer is 𝟐𝟏𝟎 𝒌𝑵/𝒎𝟐 .
Solution
18
vertical sand drains
19
Cont. . .
PVDs
20
Sand Drains
❑The use of sand drains is another way to accelerate
the consolidation settlement of soft, normally
consolidated clay layers and achieve pre-compression
before the construction of a desired foundation,
thus reducing the post-construction settlement.
The effective overburden pressure at the middle of the clay layer is 𝟕𝟎. 𝟎 𝒌𝑵/𝒎𝟐 .
Some proposed construction work is expected to impose a 𝟔𝟎. 𝟎 𝒌𝑵/𝒎𝟐 load at the
ground level.
c. the client sees the one-year duration of the preload as too long and wants to limit
this to 6 months. What should the total surcharge be during this period?
❑The soil inside the pile is then jetted out, after which
backfilling with sand is done.
24
Cont. . . .
❑ The excess pore water pressure in the clay will be
dissipated by drainage—both vertically and radially to
the sand drains—thereby accelerating settlement of the
clay layer.
25
Cont. . .
❑For a given surcharge and duration, 𝑡2 , the average
degree of consolidation due to drainage in the vertical
and radial directions (Carillo,1942) is
𝑼𝒗𝒓 = 𝟏 − 𝟏 − 𝑼𝒓 𝟏 − 𝑼𝒗
𝒘𝒉𝒆𝒓𝒆 𝑼𝒗𝒓 = 𝒐𝒗𝒆𝒓 𝒂𝒍𝒍 𝒅𝒆𝒈𝒓𝒆𝒆 𝒐𝒇 𝒄𝒐𝒏𝒔𝒐𝒍𝒊𝒅𝒂𝒕𝒊𝒐𝒏
𝑼𝒓 = 𝒂𝒗𝒆𝒓𝒂𝒈𝒆 𝒅𝒆𝒈𝒓𝒆𝒆 𝒐𝒇 𝒄𝒐𝒏𝒔𝒐𝒍𝒊𝒅𝒂𝒕𝒊𝒐𝒏
𝒘𝒊𝒕𝒉 𝒓𝒂𝒅𝒊𝒂𝒍 𝒅𝒓𝒂𝒊𝒏𝒂𝒈𝒆 𝒐𝒏𝒍𝒚
𝑼𝒗 = 𝒂𝒗𝒆𝒓𝒂𝒈𝒆 𝒅𝒆𝒈𝒓𝒆𝒆 𝒐𝒇 𝒄𝒐𝒏𝒔𝒐𝒍𝒊𝒅𝒂𝒕𝒊𝒐𝒏
𝒘𝒊𝒕𝒉 𝒗𝒆𝒓𝒕𝒊𝒄𝒂𝒍 𝒅𝒓𝒂𝒊𝒏𝒂𝒈𝒆 𝒐𝒏𝒍𝒚
26
Consolidation Due to Vertical Flow
• The degree of soil consolidation due to vertical flow can be
calculated using the Terzaghi one-dimensional consolidation
theory (Terzaghi,1943)
∞
𝟐 −𝑴𝟐 𝑻
𝑼𝒗 = 𝟏 − 𝟐 𝒆 𝒗 𝐦 = 𝟎, 𝟏, 𝟐, 𝟑, …
𝑴
𝒎=𝟎
𝟐𝒎 + 𝟏 𝝅
𝑴=
𝟐
𝑪𝒗 𝒕
𝑻𝒗 = 𝒕𝒊𝒎𝒆 𝒇𝒂𝒄𝒕𝒐𝒓 =
𝑯𝟐
𝑪𝒗 = 𝒄𝒐𝒆𝒇𝒇𝒊𝒄𝒊𝒆𝒏𝒕 𝒐𝒇 𝒄𝒐𝒏𝒔𝒐𝒍𝒊𝒅𝒂𝒕𝒊𝒐𝒏 , 𝒕 = 𝒕𝒊𝒎𝒆
𝒉𝒅𝒓 = 𝒍𝒐𝒏𝒈𝒆𝒔𝒕 𝒅𝒊𝒔𝒕𝒂𝒏𝒄𝒆 𝒅𝒖𝒆 𝒕𝒐 𝒗𝒆𝒓𝒕𝒊𝒄𝒂𝒍 𝒇𝒍𝒐𝒘
27
Cont. . .
❑ The average degree of consolidation with the time
factor under a uniform distribution of initial excess pore
water pressure can also be present by approximation
relation relationship
❑ for 𝑼𝒗 = 𝟎 − 𝟓𝟐. 𝟔%
𝟐
𝝅 𝑼𝒗
𝑻𝒗 =
𝟒 𝟏𝟎𝟎
28
Consolidation Due to Radial Flow
❑Barron (1948) proposed a solution for an average
degree of consolidation due to horizontal (radial) flow
toward a free-draining sand drain:
𝟖
𝑼𝒓 = 𝟏 − 𝒆𝒙𝒑 − 𝑻𝒓 ,
𝑭 𝑵𝑫
𝑵𝟐𝑫 𝟑𝑵𝟐𝑫 − 𝟏
𝑭 𝑵𝑫 = 𝟐 𝒍𝒏 𝑵𝑫 −
𝑵𝑫 − 𝟏 𝟒𝑵𝟐𝑫
𝑼𝒓 = 𝒂𝒗𝒆𝒓𝒂𝒈𝒆 𝒅𝒆𝒈𝒓𝒆𝒆 𝒐𝒇 𝒄𝒐𝒏𝒔𝒐𝒍𝒊𝒅𝒂𝒕𝒊𝒐𝒏 𝒅𝒖𝒆 𝒕𝒐 𝒓𝒂𝒅𝒊𝒂𝒍 𝒇𝒍𝒐𝒘
𝒅𝒆
𝑵𝑫 = 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒓𝒂𝒕𝒊𝒐 𝒊. 𝒆. , 𝑵𝑫 =
𝒅𝒄
29
Cont. . .
𝒅𝒆 = 𝒆𝒒𝒖𝒊𝒗𝒂𝒍𝒆𝒏𝒕 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒐𝒇 𝒂 𝒖𝒏𝒊𝒕 𝒄𝒆𝒍𝒍
𝒅𝒄 = 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒐𝒇 𝒂 𝒔𝒂𝒏𝒅 𝒅𝒓𝒂𝒊𝒏
𝑪𝒓 𝒕
𝑻𝒓 = 𝒕𝒊𝒎𝒆 𝒇𝒂𝒄𝒕𝒐𝒓 𝒅𝒖𝒆 𝒕𝒐 𝒓𝒂𝒅𝒊𝒂𝒍 𝒇𝒍𝒐𝒘 𝒊. 𝒆. , 𝑻𝒓 = 𝟐
𝒅𝒆
𝟖
𝑼𝒓 = 𝟏 − 𝐞𝐱𝐩 − 𝑻𝒓
𝑭𝒎 𝑵𝑫
𝑵𝑫 𝒌𝒓 𝟑 𝒌𝒓
𝑭𝒎 𝑵𝑫 = 𝒍𝒏 + 𝒍𝒏 𝑵𝒔 − + 𝝅𝒛 𝟐𝒉𝒅𝒓 − 𝒛
𝑵𝒔 𝒌𝒔 𝟒 𝑸𝑪
𝑾𝒉𝒆𝒓𝒆
𝒅𝒔
𝑵𝒔 = 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒐𝒇 𝒔𝒎𝒆𝒂𝒓𝒆𝒅 𝒛𝒐𝒏𝒆𝒅 𝒕𝒐 𝒗𝒆𝒓𝒕𝒊𝒄𝒂𝒍 𝒅𝒓𝒂𝒊𝒏 𝒊. 𝒆, 𝑵𝒔 = ,
𝒅𝒄
𝒅𝒔 = 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒐𝒇 𝒔𝒎𝒆𝒂𝒓𝒆𝒅 𝒛𝒐𝒏𝒆,
31
Cont. . .
𝒌𝒓
= 𝒓𝒂𝒅𝒊𝒂𝒍𝒍𝒚 𝒑𝒆𝒓𝒎𝒆𝒂𝒃𝒊𝒍𝒊𝒕𝒚 𝒐𝒇 𝒖𝒏𝒅𝒊𝒔𝒕𝒖𝒓𝒃𝒆𝒅 𝒔𝒖𝒓𝒓𝒐𝒖𝒏𝒅𝒊𝒏𝒈 𝒔𝒐𝒊𝒍,
𝒌𝒔 = 𝒓𝒂𝒅𝒊𝒂𝒍 𝒑𝒆𝒓𝒎𝒆𝒂𝒃𝒊𝒍𝒊𝒕𝒚 𝒐𝒇 𝒔𝒎𝒆𝒂𝒓𝒆𝒅 𝒔𝒐𝒊𝒍
𝒛
= 𝒅𝒆𝒑𝒕𝒉 𝒂𝒕 𝒘𝒉𝒊𝒄𝒉 𝒕𝒉𝒆 𝒅𝒆𝒈𝒓𝒆𝒆 𝒐𝒇 𝒄𝒐𝒏𝒔𝒐𝒍𝒊𝒅𝒂𝒕𝒊𝒐𝒏 𝒊𝒔 𝒄𝒐𝒎𝒑𝒖𝒕𝒆𝒅
𝒉𝒅𝒓 = 𝒍𝒐𝒏𝒈𝒆𝒔𝒕 𝒅𝒓𝒂𝒊𝒏𝒂𝒈𝒆 𝒅𝒊𝒔𝒕𝒂𝒏𝒄𝒆 𝒅𝒖𝒆 𝒕𝒐 𝒗𝒆𝒓𝒕𝒊𝒄𝒂𝒍 𝒇𝒍𝒐𝒘,
𝑄𝑐 = 𝑑𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑎 𝑣𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝑑𝑟𝑎𝑖𝑛
𝝅𝒅𝟐𝒄
𝑸𝒄 = 𝒌𝒄
𝟒
𝑘𝑐 = 𝑖𝑠 𝑡ℎ𝑒 𝑣𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝑝𝑒𝑟𝑚𝑒𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 𝑑𝑟𝑎𝑖𝑛 𝑤𝑒𝑙𝑙
32
Cont. . .
❑The diameter of the smeared zone depends on the shape
and size of the mandrel to install vertical drains and the
type and sensitivity of soil.
𝒅𝒔 = 𝟏. 𝟓 𝒕𝒐 𝟑. 𝟎 𝒅𝒄
33
Prefabricated Vertical Drains
❑ Prefabricated vertical drains (PVDs), also referred to as
wick or strip drains, were originally developed as a
substitute for the commonly used sand drain.
34
Advantages of PVDs over sand drains
❑The main advantage of PVDs over sand drains is that they do
not require drilling; thus, installation is much faster.
35
Potential advantage of vertical drains
The advantages of vertical drains are threefold:
36
cont. . .
2. Increased rate of consolidation
➢Reduction in time required for primary settlement.
➢Structure or embankments can put into commission
and use far earlier
➢Reduction in cost of maintenance
3. Stability to embankments
➢Many soft clay strata contain thin band, or parting,
of sand or silt
➢Excess horizontal spread of pore pressure along these
partings take place
➢Vertical drains installed can relieve these excess pore
pressure
37
Application of PVDs
❑Airport Runways
❑Golf Courses
❑Dredge Consolidation
❑Tailing Ponds
❑Swampland/Wetland Development
❑Building Foundations
❑Retaining Walls
❑Parking Lots
❑Landfills