Professional Documents
Culture Documents
2023 PGD 09. HSE Management
2023 PGD 09. HSE Management
9. HSE MANAGEMENT
Scope:
• Identify Hazards; appraise and quantify Risks
• Establish HSE policy, procedures, objectives
• Initiate/Pursue Environment Protection tools use (EBS, EIA,
EMP)
• Implement HSE policy and risk management
• Initiate/Pursue Safety Case (Safety concept)
Objectives:
• Ensure Safety and Security of all personnel, at all phases,
including future operation
• Respect and protect environment
• Protect assets
Process control
PREVENT HAZID, HAZOP Process isolation
Decrease probability of release Overpressure protection
Safe design, Frequency analysis
Material selection
Layout
Consequence analysis Fire detection
MITIGATE ESD & EDP
Escalation analysis
Mitigation of consequences Bunding & Drainage
Risk assessment Blast proofing
Active Fire protection
Passive fire protection
HSE SAFETY
CASE / REPORT DOSSIER
Environment protection
Environmental management of the project. Three essential tools:
• EBS (Environmental Baseline Survey): analysis of the initial status of the
site (reference status for further controls comparisons)
• EIA (Environmental Impact Assessment): detailed description of the
impacts of the projected activities on the site and mitigation measures for
reducing these impacts to a level as low as possible
• EMP (Environmental Management Plan): essential tool dedicated to the
Environment preservation during construction and operations, (including
Oil Spill Contingency Plan, Waste Management Plan, Chemicals
Management Plan, Biodiversity Management Plan, Monitoring, etc.)
N° SYSTEM / UNIT / GUIDE WORD CAUSE POTENTIAL DEVELOPMENT SAFEGUARDS / ACTIONS / PRIORITY
NODE LOCATION & CONSEQUENCES CONTROLS IN PLACE CONTROLS TO BE INCORPORATED
12 SUBSEA SUBSEA EXISTING Construction Potential damage or rupture of No specific protection to subsea Anchor pattern to be submitted to TA 2
ITEMS PIPELINES HIDRA activities / pipes Hidra existing pipelines. existing pipelines. marine Dept for approval.
SUBSEA laying / barge Physical & electronic surveys to be Operating procedures to be issued by
PIPELINES anchoring performed on site to locate and mark contractor and validated by project.
existing pipelines. Work permits to be used when works
are carried near live installations.
(distances to be defined by TA)
Specific HAZID to be carried out with
TA operations (Mc Dermott).
13 TOP SIDES ONSHORE PROXIMITY TO Crossing of Potential pipes damages or Survey and marking of existing pipes On site checking of pipes markings. 2
PIPELINES TRANSPORT onshore pipes rupture and gas release. carried out. Insure safe clearance between
ARRIVAL CORRIDOR existing and new pipes.
Shut down and depressurisation of
existing pipes while drilling new pipe
tunnel.
Specific HAZID to be carried out with
TA operations (Mc Dermott).
14 TOP SIDES ONSHORE PROXIMITY TO Crossing of Potential pipes damages or Safe distance required between new Landfall and pipes route to be agreed 1
10-1
Likely
10-2
(first priority)
Unlikely
10-3
Very unlikely (tolerable if
10-4
ALARP)
Extremely
unlikely
(acceptable)
10-5
Severity of consequences
EP - 21681_b_A_ppt_01 - 6. HSE Management 16
HAZOP (HAZARD and OPERABILITY)
Objectives:
Identify reaction of plant during abnormal process conditions
(Malfunction or mis-operation) that could cause a hazard
Check if design adequate to prevent hazard occurring
Check safety interfaces with other installations, surroundings
Record all corrective actions, remedies, or remaining hazard (at an
accepted level)
• Uses PIDs and process flow diagrams
No flow
NO or NOT Operation not performed.
or NONE Negation of Intention Operator error.
Operation stopped.
No reaction
Flow greater than design.
Temperature high.
Pressure high.
MORE or HIGH or Too much mass of particular material.
HIGHER Quantitative Increase
Increased mechanical stress.
High static charge.
High reaction rate.
More reaction time.
Low flow.
Low temperature.
LESS or Low pressure (possibly
LOW or Quantitative decrease negative pressure).
LOWER Low mass.
Low reaction rate.
Loss reaction time.
Main Purpose:
To state company requirements for the protection of assets &
personnel protection
To indicate safety requirements for implementation in plant
design and engineering, operation
To identify derogation to reference document (Company general
specification, certification, etc.)
To hand out to operations team a comprehensive document on
safety design of their facilities
To have a document with standard content that can be audited
Content (typical)
Bases: site conditions, meteo-oceano, surroundings, applicable references
Risks, identification and prevention principles
Systemised list
• Lay-out
• Hazardous areas
• Buildings-Ventilation-Pressurisation
• Blast protection
• Electrical power (UPS, Lighting…) FOR EACH ITEM.
• Fire & Gas - Safety system goal
• ESD - Company decision
• Blow down & relief - Safety system performance
- Applicable document
• Drainage (Spec, Derogation,…)
• Active fire fighting - Basic engineering development
- Detailed engineering
• Passive fire fighting development
Objectives
• Assemble all safety related documents for a permanent reference
• Give to the operator a clear and traceable view of safety design
• Have a safety basis for possible large modifications/extensions
Content
• SAFETY CONCEPT (updating & revisions included) Summary included
if needed
• HAZOP # 1, 2, 3
• PTR # 1, 2, 3, 4
• Derogation requests and supporting documents
• List approved safety related documents
• Safety documents & studies
Technological risks
• Generated by flammable, toxic,
explosive substances
• Risks concern individuals,
environment, integrity of
installations and production, Probability LOW – Severity HIGH
surroundings & company image
Design challenges:
• Sound and realistic set of references, policies and goals (Zero risk
does not exist)
• Reliable risk assessing processes (data banks, calculation model,
accurate data, confirmed procedure, proven concept, new items
testing, etc…),
• Experienced personnel for specific analysis (ex: QRA, EIA) to prevent
under/over designing
Construction challenges:
• Selecting experienced Contractors, and yards / vessels,
• Qualification of Personnel hired by contractors
• Control of many subcontrators
• Effective Company and Contractors integration, development of the
project HSE culture…
Reporting covers all activities called for by HSE policy and procedure, in
detection, classification, notification, record and follow-up of incident
and accident, with the final aim to reduce them, and develop
AWARENESS
Reporting is necessary to inform project participants about the safety
performance (company, authorities, contractors…) but also needed in
order to:
• To identify, and record, particular problems (recurring incident or accident
types)
• Take correct decisions with regards to remedial actions, implement them
• To be used as feedback examples and learning tools for the workforce &
management, as well as in Company statistics and record
• Compare the specific performance (with others or contractual obligations
etc.)
• As KPI (Key Performance Indicator), with given target, and monitoring
RECORDABLE ACCIDENTS:
LTI = Lost Time Incident, is any accident requiring the injured person to stay off the
job for a number of days
MTC = Medical Treatment Case, an accident where the injured person requires
medical attention, but may return to work in his original job the next day
RWC = Restricted Work Case, an accident restricting the injured person from going
back to his original job for a given time, but allowing him to perform other work.
FAT = Fatality
Essentially First Aid Cases or FACs = the injured person can be treated by a nurse or
TRIR
Total Recordable Injury Rate
LTIR
Lost Time Injury Rate
Byrd’s Pyramid
10
Traditional Safety Programs with Enhanced
Commitment - training, orientations,
Calculative investigations, supervisor's roles, communications
Advanced Approaches with Supporting
5 Management Systems - analysis, measurement,
TRI Frequency
accountability, involvement
Proactive
Modernized Approaches - behavioral
3 observation approaches, human
factors, cultural alignment, safety is a
value
1 Generative
TIMING
Sooner / Later
PROBABILITY
Certain / Uncertain
IMPACT
SC+