Professional Documents
Culture Documents
14 August 2006
1 2 3 Pipe 4 Allowable 5
Expansion Pipeline
Applicable On-bottom Calculatio Free Span Protection
Codes Stability ns Calculatio against
(Concrete ns Anchors,
Wall Coating) Flexibility Wave
Thickness Design Analysis On-bottom Liquefactio
Design Roughnes n&
Methodolo s Analysis Earthquake
gy
6 7 8 9 10
Pipeline
Use of Constructi Installation Installation
Cathodic Spoilers on - Engineerin Engineerin
Protection for Pipe Conventiona g g
Design Self-burial l&
(1/2) (2/2)
Unconventio
nal
Installation Engineering
This section also explains how a conventional rock berm affects the
behaviour of a dragging anchor and subsequently providing the
necessary protection.
As the ship continues drifting, the anchor chain tightens and pulls
the anchor shaft over, until the shaft locks.
After the anchor has tipped some way, the tip of the fluke come to
rest against the undisturbed soil at the side of the disturbed soil.
The pull exerted by the chain upon the shaft will cause the body of
the anchor to penetrate into the undisturbed soil near the bottom of
the pit until the shank locks again and the real pull out of the
anchor is about to begin. At this phase, the anchor behaves like a
dead man and its holding power is determined by the shear
strength of the soil through which it is being dragged.
As the anchor approaches the surface of the seabed, the tip of the
shank and fluke start protruding above the seabed, thus increasing
the moment which tends to flatten the anchor inclination and
decrease the resistance to movement. From this point, the surface
of sliding tends to follow a circular type of trajectory.
The flukes then gradually work down into the soil until the body of
the anchor is either partly or wholly embedded in the seabed and
the anchor attains its maximum holding power. When this holding
power is exceeded, some anchors drag horizontally through the soil,
other rotate and break free and dig in again, repeating the process
as described above.
Thereafter, the anchor will "bite" along the seabed and act as a
brake to slow down the vessel.
However, due to the shortness and tautness of the anchor chain (2-
3 "shots" released in practice), the anchor will be dragged into the
soil very rapidly and rise to the surface; it will then be dragged for
most of the way along the top of the seabed strata. Thus, the
anchor will ride over and above the pipelines provided that they are
buried with sufficient clearance.
after breaking out of the berm, anchors dragged across the berm
would cause limited damage;
the larger is the anchor, the deeper is the berm and the larger is the
rock required for the berm.
A gentle slope and the correct berm depth will ensure that the berm
deflects the anchor out before it cuts into the pipe. When the slope
is too steep and the surrounding soil is soft, the possibility of anchor
cutting into the berm and pipe is very high.
Scheme Description
No.
Any questions?