Professional Documents
Culture Documents
Week : 3-4
Dr. M Shakeel
Project Cost Management
Dr. M Shakeel
Project Cost Management
Dr. M Shakeel
ESTIMATE COSTS
• Estimate Costs is the process of developing an
approximation of the cost of resources needed to
complete project work.
• The key benefit of this process is that it determines
the monetary resources required for the project.
• This process is performed periodically throughout the
project as needed.
• A cost estimate is a quantitative assessment of the
likely costs for resources required to complete the
activity
• It is prediction (based on the information known at a
given point in time)
Dr. M Shakeel
ESTIMATE COSTS
• Cost estimates include the identification and
consideration of costing alternatives to initiate and
complete the project.
• Cost trade-offs and risks should be considered, such
as make versus buy, buy versus lease, and the sharing
of resources in order to achieve optimal costs for the
project.
• Cost estimates are generally expressed in units of
some currency
(i.e., dollars, euros, yen, etc.)
Dr. M Shakeel
ESTIMATE COSTS
• Other units of measure, such as staff hours or staff days,
are used to facilitate comparisons by eliminating the
effects of currency fluctuations.
• Cost estimates should be reviewed and refined during
the course of project
• The accuracy of a project estimate will increase as the
project progresses through the project life cycle
• Costs are estimated for all resources that will be charged
to the project.
This includes but is not limited to Labor, materials,
equipment, Services, facilities, special categories such as
an inflation allowance, cost of financing, or contingency
costs.
Dr. M Shakeel
ESTIMATE COSTS
Dr. M Shakeel
ESTIMATE COSTS
Dr. M Shakeel
Estimate Costs: Inputs, Tools & Techniques, and Outputs
Dr. M Shakeel
Estimate Costs: Flow Chart
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Dr. M Shakeel
Estimate Costs: Inputs
Work breakdown structure: The WBS provides the relationships among all the
project deliverables and their various components. (Section 5.4.3.1)
• A Work Breakdown Structure (WBS) represents this division of a project into
constituent tasks. It is a tabular or graphical representation of the tasks that
make up the project’s scope. The schedule and budget is then created
and tracked by task.
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
WBS dictionary: The WBS dictionary and related detailed statements of work
provide an identification of the deliverables and a description of the work in each
WBS component required to produce each deliverable. (Section 5.4.3.)
The WBS dictionary is a document that provides detailed deliverable, activity, and
scheduling information about each component in the WBS. The WBS dictionary is
a document that supports the WBS. Information in the WBS dictionary may
include but is not limited to:
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
PROJECT DOCUMENTS:
Lessons learned register: Lessons learned earlier in the project with
regard to developing cost estimates can be applied to later
phases in the project to improve the accuracy and precision of
the cost estimates.
Dr. M Shakeel
Estimate Costs: Inputs
PROJECT DOCUMENTS:
The project schedule is the tool that communicates what work
needs to be performed, which resources of the organization
will perform the work and the timeframes in which that work
needs to be performed.
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Inputs
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Expert Judgment
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Analogous estimating:
• Analogous cost estimating uses the values such as scope, cost,
budget, and duration or measures of scale such as size,
weight, and complexity from a previous, similar project as the
basis for estimating the same parameter or measurement for
a current project.
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Parametric estimating is an estimating technique in which an
algorithm is used to calculate cost or duration based on historical
data and project parameters.
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Example
You are the project manager for the annual Earth Day 5k road race,
with three primary components: marketing, registration, and race-day
coordination.
• For marketing, there will be 500 flyers printed up at a cost $0.20
each.
• Last year the cost to host the registration website was $850.00 You
estimate the same this year.
• There will be four people used to coordinate the race. Each resource
will be paid $25 per hour and they will be working an estimated
seven hours, based on the race last year.
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Dr. M Shakeel
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Top-Down versus Bottom-Up Estimating
Dr. M Shakeel
THREE-POINT ESTIMATING:
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Triangular Distribution
The simplest three point estimate is the simple average of the three
values (known as the triangular distribution):
E = (a + m + b) / 3
Where:
E = estimated cost
a = optimistic value
m = most likely value
b = pessimistic value
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Beta Distribution
The beta distribution places the final estimate closer to the most likely
value:
E = (a + 4m + b) / 6
Where:
E = estimated cost
a = optimistic value
m = most likely value
b = pessimistic value
Comparison:
• The triangular distribution is the default and should be used if there is no
reason to use anything else.
• The beta distribution should be chosen when there is more confidence in the
most likely value, that is, where the final estimate should be tighter to the
mean.
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Reserve Analysis: Contingency Reserves
Dr. M Shakeel
Reserve Analysis: Contingency Reserves
Dr. M Shakeel
Reserve Analysis: Contingency Reserves
Dr. M Shakeel
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Cost of quality:
• Assumptions about costs of quality may be used to prepare the
estimates. This includes evaluating the cost impact of additional
investment in conformance (good quality) versus the cost of
nonconformance (poor quality).
Dr. M Shakeel
Estimate Costs: Tools and Techniques
• Rework • Complaints
• Delays • Repairing goods and redoing
• Re-designing services
• Shortages • Warranties
• Failure analysis • Customers’ bad will
• Re-testing • Losses due to sales reductions
Dr. M Shakeel
Estimate Costs: Tools and Techniques
Dr. M Shakeel
Estimate Costs: Tools and Techniques
• DECISION MAKING
The decision-making techniques that can be used in the Estimate
Costs process include but are not limited to voting.
Voting is an assessment process having multiple alternatives with an
expected outcome in the form of future actions. These techniques
are useful for engaging team members to improve estimate
accuracy and commitment to the emerging estimates.
Dr. M Shakeel
Estimate Costs: Outputs
Dr. M Shakeel
Estimate Costs: Outputs
Dr. M Shakeel
Estimate Costs: Outputs
Dr. M Shakeel
Estimate Costs: Outputs
Basis Of Estimates
The amount and type of additional details supporting the cost estimate
vary by application area. Regardless of the level of detail, the
supporting documentation should provide a clear and complete
understanding of how the cost estimate was derived.
Dr. M Shakeel
Estimate Costs: Outputs
Project Documents Updates
Project documents that may be updated as a result of carrying out this
process include but are not limited to:
Dr. M Shakeel