You are on page 1of 8

PPT REPORT FOR TOWER RECTIFICATION WORK - (NUT BOLTS BROKEN IN

DIFFERENT JUNCTION POINTS)

CW & Construction/Tower Infra./Technology


Site Name: KUDGP1, Tower Type: 42mM Angle Tower
Inspection date: 10-06-2022, Partner: Mizan Construction Ltd.
PPT Report for Angle Tower Rectification work - (Nut Bolts broken in different junction points)

After Picture
Before Picture Before Picture
After Picture

2
NB: If it is stuck in the forest, the infrastructure
Internal
longevity of the tower is reduced.
Sensitivity: Internal
PPT Report for Angle Tower Rectification work - (Nut Bolts broken in different junction points)

Before Picture

After Picture Before Picture After Picture

3 Internal
Sensitivity: Internal
PPT Report for Angle Tower Rectification work - (Nut Bolts broken in different junction points)

Picture before nut Picture after nut The next picture to be


Next picture of welding
bolt change bolt change painted by changing the
with new nut bolt
nut bolt

NB: Thus we have changed all the nut bolts of the leg joint from bottom to 20 meters
4
Sensitivity: Internal
PPT Report for Angle Tower Rectification work - (Nut Bolts broken in different junction points)

Picture before nut Picture after nut The next picture to be


Next picture of welding
bolt change bolt change painted by changing the
with new nut bolt
nut bolt

NB: Thus we have changed all the nut bolts of the leg joint from bottom to 20 meters
5 Internal
Sensitivity: Internal
PPT Report for Guy Tower Rectification work - (Nut Bolts broken in different junction points)

After
Before

NB: Thus we have changed all the nut bolts of the leg joint from bottom to 20 meters
6 Internal
Sensitivity: Internal
PPT Report for Angle Tower Rectification work – (Nut Bolts broken in different junction points)

Before Picture After Picture

Sensitivity: Internal
THANKS