Client Date Project XAD Site ID Site ID Location Site Type SOW Description

Tower marking.
Huawei 11/11/2023 HW-Zain BUK0206 BUK0206 Bukeria Rooftop 15m Civil work dimensions

Challenge:
There were electric power cables in front of building. Due to
which there was high risk of accident.
Solution: Installation completed with the help of 150 ton crane
Client Date Project XAD Site ID Site ID Location Site Type SOW Description

Chipping and tower


Huawei 12/11/2023 HW-Zain BUK0206 BUK0206 Bukeria Rooftop 15m Civil work assembling
Client Date Project XAD Site ID Site ID Location Site Type SOW Description

Huawei 13/11/2023 HW-Zain BUK0206 BUK0206 Bukeria Rooftop 15m Civil work tower assembling
Client Date Project XAD Site ID Site ID Location Site Type SOW Description

Huawei 14/11/2023 Zain XAD-BUK0206 BUK0206 Bukeria Roof top 15M Civil work Tower Assembling
Client Date Project XAD Site ID Site ID Location Site Type SOW Description

Tower erection and beam


Huawei 16/11/2023 HW-Zain XAD-BUK0206 BUK0206 Bukeria Rooftop 15m Civil work fixing
Client Date Project XAD Site ID Site ID Location Site Type SOW Description

RGS pipe and fence


Huawei 19/11/2023 HW-Zain BUK0206 BUK0206 Bukeria Rooftop 15m Civil work installation