Professional Documents
Culture Documents
RIY2388
RIY2388
Huawei 19/10/2023 HW-Zain RIY2388 RIY2388 Riyadh Rooftop 15m Civil work Tower marking
Challenge:
AC ODUs were installed at the place of tower during design visit.
Solution:
Coordinated with site acquisition and owner and shifted AC ODUs .
Client Date Project XAD Site ID Site ID Location Site Type SOW Description
Huawei 05/11/2023 HW-Zain RIY2388 RIY2388 Riyadh Rooftop 15m Civil work Chipping of roof
Client Date Project XAD Site ID Site ID Location Site Type SOW Description
Huawei 12/11/2023 HW-Zain RIY2388 RIY2388 Riyadh Rooftop 15m Civil work Tower assembling
Client Date Project XAD Site ID Site ID Location Site Type SOW Description