Compressor change over procedure
Run all the auxiliaries for 5min and observe the performance. MUG
MGC stage I & stage II spillback C/V s in manual and 100%
Cooling Lube oil
open. Confirm in field and do stroke check.
water system skid
Barring of compressor completed in depressurized condition if
starting after more than a week. Auxiliary network
Ensure all the PSVs are lined up condition.
Critical equipment change over plans / handing over procedure
90-E-09A
Discharge to RGC suction
90-E-05A/B/C
90-V-02
Mechanical
Spill back
90-P-01A 90-P-01B
Mechanical
Spill back
Lean amine pump spill back control valve in manual and 100% open. Confirm in field and stroke check if
required.
Line up LG, LT, PT of seal pot, BCW supply and return to primary and secondary seal coolers. Ensure 80%
level in seal pot.
Monitor pressure and level indications of seal pot. Pressure above 3ksc indicates primary seal leak whereas
activation of low level indicates secondary seal leak.
Lean amine surge drum pressure is 2ksc and temperature below 60degC.
Line up lean amine pump suction valves,min.recirculation valves
Pump is primed and filledup to discharge block valve.Vent the system to release entrapped vapours or air
Critical equipment change over plans / handing over procedure
Open pump first discharge valve while ensuring the other discharge valve is fully closed.
Take pump discharge flow low-low switch &Recycle gas scrubber,off gas scrubber flows low-low switches in
bypass.
Take CPP&SS-71 clearance
Press start button on LCS.
Check for healthiness of seal pot level,pressure,pump discharge pressure, suction strainer DP.
Slowly wide open pump discharge block valve by keeping watch on motor amps
Critical equipment change over plans / handing over procedure
Gradually throttle mechanical spill back valve and parallely open the mechnical spill back valve of the other
pump watching the amine flows to the system.
Throttle and close the other pump discharge block valve, once the flows are stabilised stop the second
pump.
Critical equipment change over plans / handing over procedure
Equipment handing over procedure – Hot Service Pumps (90-P-05 & 12)
Drain the liquid to CBD and counter check that no valves are passing.