Professional Documents
Culture Documents
Session 10
Hazard and Operability Studies – Overview
Originated as a hazard identification technique for
process plants – developed by ICI in mid 1960s
also commonly applied in petrochemical, nuclear and food
processing industries
HAZOP - 2
HAZOP – technical approach
In the process industries, HAZOP is normally applied once the
piping and instrumentation (P&I) diagram has been produced
Scope of study explicitly extends to cover unusual
circumstances such as startup, shutdown and plant
maintenance
Scope of study does not include making detailed design
changes, although recommendations and follow-up questions
should be produced
As with FHA, results are recorded in a tabular format
HAZOP - 3
HAZOP procedure
Start Finish
YES
Select a component NO All components analysed?
YES
NO
Select a flow All flows analysed?
YES
Suggest a deviation NO
All guide words considered?
using a guide word
Investigate and
Does deviation have plausible
document effects
NO causes and hazardous effects? YES
HAZOP - 4
HAZOP Team Members 1
Leader User(s)
planning and preparation may be site representative,
act as chairman for meeting operator, maintenance crew
sign off documentation supply information about the
ensure follow-up work is context in which the system
completed will be used, e.g. site facilities
ask questions, and help decide
Recorder
which issues affect safety
participant in study (?)
Expert(s)
document the analysis
key function is to explore
Designer(s), process / project ask questions
engineers suggest deviations / causes /
understand and explain the effects
plant design need good knowledge of
answer questions about the process chemistry, or
plant and process experience of similar plant
HAZOP - 6
HAZOP – guide words
Guide Word Deviation Example Interpretation
NO or NONE No part of the intention is achieved No forward flow when there should be.
MORE Quantitative increase in a physical Higher pressure, flow rate, temperature...
property (rate or total quantity) Quantity of material is too large.
LESS Quantitative decrease in a physical Lower pressure, flow rate, temperature...
property (rate or total quantity) Quantity of material is too small.
MORE THAN All intentions achieved, but with Impurities in flow (air, water, oil...)
or AS WELL AS additional effects (qualitative Chemicals present in more than one phase
increase) (vapour, solid)
PART OF Only some of the intention is One or more components of mixture
achieved (qualitative decrease) missing, or ratio of components is incorrect
OTHER THAN A result other than the intention is Unusual circumstances etc... see next slide
achieved
REVERSE The exact opposite of the intention Reverse flow.
is achieved
Physical properties
Temperature Flow rate Pressure Reaction rate
Viscosity
HAZOP - 7
HAZOP – guide words 2
Guide word “Other Than” has many interpretations
this word particularly is often defined specifically for
particular study
examples include
plant operation phases
startup, shutdown, maintenance, sampling and inspection
instrumentation
control philosophy, location of instruments, alarms and trips
failure of plant services
cooling water, fuels, power supplies
other external factors
weather
spare / non-installed / portable equipment
safety
fire and leak detection, emergency planning
HAZOP - 8
HAZOP example – a bit of P&I
Valve (normally closed during
Manually operated valve Pump
operation of the plant)
LC
Hydrocarbon PG
from storage
Drain PG
Settling tank
HAZOP - 9
HAZOP example – output
Guide Word Deviation Possible Causes Consequences Action Required
NONE No flow No hydrocarbon Loss of feed to reactor. 1) Ensure good communication
available from storage Polymer formed in with storage area
heat exchanger 2) Install low level alarm on
settling tank
Transfer pump fails As above Covered by 2)
(motor fault, loss of
power, impeller
corroded etc.)
MORE More flow Level control valve Settling tank overfills 3) Install high level alarm
fails to open, or LCV 4) Check size of overflow
bypassed in error 5) Establish locking-off procedure
for LCV bypass when not in use
More Isolation valve or LCV Line subjected to full 6) Install kickback on pumps
pressure closed when pump pump pressure
running
More High intermediate Higher pressure in 7) Install warning of high
temperature storage temperature transfer line and temperature at intermediate
settling tank storage
HAZOP - 10
Hazard Study Phasing 1
1 2 3 4 5 6
Project Design
Com m issioning
O peration
HAZOP - 11
Hazard Study Phasing 2
1 - Concept Study
PHI, checklist, materials and reagents study, first outline HAZOP
2 - Process Flow Study
HAZOP
3 - Detailed Design (P&I) Study
HAZOP
4 - Detailed Design (Physical) Study
HAZOP update, Sneak, Fault Trees, FMEA
5 - Audit of installed plant against design
Checklist, review of HAZOP actions, inspections
6 - Audit / review of process
Final review of evidence, completeness of HAZOP actions
HAZOP - 12
HAZOP – Pros and Cons
Advantages
very methodical. Use of guide words can give confidence
in completeness of analysis.
has both inductive and deductive phases
team conclusions may carry more weight than those
reached by individual analysts
Disadvantages
can produce lots of output. Structure is only obtained by
reference back to P&I diagrams
team approach is expensive – must be shown to be
cost-effective
HAZOP - 13
ICI Experience
More operability problems than hazards are usually found
though difference is smaller with existing plants
HAZOP - 14