Retaining Wall and Slope Protection (PB1 9-3-22)
Retaining Wall and Slope Protection (PB1 9-3-22)
ACCOMPLISHED ACTIVITIES
Excavation – 40%
Installation of rebars – 40% (MATLS DEL’D-70%)
Concreting – 10% (MATLS DEL’D-75%)
Installation of formworks – 2% (MATLS DEL’D-50%)
%ACCOMPLISHMENT REPORT RETAINING WALL AND SLOPE PROTECTION
LOAD FACTOR PERCENT ACCOMPLISHMENT WT. IN % ACCOMPLISHMENT
ITEM NO. DESCRIPTION THIS PERIOD (9-
% PREVIOUS TO DATE PREVIOUS THIS PERIOD TO DATE
2-22)
I. PRELIMINARIES / GEN REQTS
1.0 PPE's -Safety/ Workers Uniform 0.81 100% 100% - 0.81 0.81
2.0 Mobilization 1.08 100% 100% - 1.08 1.08
3.0 Temfacil Construction 0.81 100% 100% - 0.81 0.81
4.0 Site Transportation / Delivery Cost 1.08 50% 50% - 0.54 0.54
5.0 Badging / Workers Access / Orinetation 0.67 100% 100% - 0.67 0.67
6.0 Supervision 2.69 40% 40% - 1.08 1.08
SAFETY VIOLATION 0 0 0