Professional Documents
Culture Documents
DSR - Principles Techniques of Cost Planning - Week 9
DSR - Principles Techniques of Cost Planning - Week 9
TECHNIQUES OF COST
PLANNING
RMK 363 – CONSTRUCTION ECONOMICS
Introduction to Cost Planning Process
• CP as a process is difficult to define concisely as it involves a variety of
procedures and techniques used concurrently by the QS or building
economics or cost consultant.
• The elemental method is a detailed cost plan which is broken down into
a series of elements. Initially, the elemental cost plan will simply be the
total construction cost for the project divided into elements on a
percentage basis. As the design becomes more detailed however, the
elemental cost plan will be 'measured', based on the actual quantities of
work and materials that will be required to construct the project.
Introduction to Cost Planning Process
• The elemental cost plan should be prepared in a spreadsheet
format that is easy to interrogate and import into costing software
and should adopt a standard approach.
• The elemental cost plan should set out any assumptions that have
been made, should identify any exclusions agreed with
the client and should present an outline assessment of whole life
costs. It might also include a list of abnormal or non-standard items,
to help inform any value management exercises.
• Cost plans are generally prepared by cost consultants (or quantity surveyors).
They evolve through the life of the project, developing in detail and accuracy as
more information becomes available about the nature of the design, and then
actual prices are provided by specialist contractors, contractors and suppliers.
• They range from very early initial cost appraisals through to tender pricing
documents and the final account:
o Initial cost appraisals (studies of options prepared during the feasibility study stage).
o Elemental cost plan (prepared during the project brief stage and carried through
to detailed design).
o Approximate quantities cost plan (from the end of detailed design through
to tender).
o Pre-tender estimate (prepared alongside tender documentation).
o Contract sum (agreed with the contractor during the tender period and adjusted
during the construction period).
o Contract sum analysis (a break down of the contract sum prepared by
the contractor on design and build projects).
o Final account (agreed during the defects liability period).
Objective of Cost Planning
• The client receives value of money, not necessarily lower than the
initial cost. There must be a balance between quality, usage suitability,
initial cost and life cycle costing for the entire span of the element.
• It allows the costs checked as the design develops with the amount
allocated.
• The effectiveness of cost and value for money can be achieved with
cost planning
• The designers may have some limitation in their work style. They
need to consider requirement for ease of CP production.
13
1st – Inception Stage (Within Brief Stage)
• Decision to have a building
• No design team
14
2nd – Feasibility Stage (Within Brief Stage)
17
5th – Tender Document Stage
• Objectives:
- To ensure that the completed design is contained within the
cost limit set at the sketch design stage; and
- within the budget set at the Brief Stage!!
• Design contingency
(incomplete design)
• Contract contingency
(unknowns occurring during construction)
20
Cost Planning: Comparison of Stages