Professional Documents
Culture Documents
Estimate Definitions
• An estimate is a projection of qty. based on
experience and/ or information available at the time
of estimation.
• It may be a detailed cost estimate computing cost of
each activity in a work.
• It is a process of calculating the total expected cost
of a project and includes not only material and
lobour but also equipments, tools, management
and overheads.
• It is a document consisting of construction plans,
specifications, project manuals, scope of work and
other related data useful for drafting the contracts,
determine project feasibility and set budgets for
financial planning. 2
01/28/24
PURPOSES
• To know probable cost of work proposed.
• To examine whether the work is financially
justified or not.
• To obtain administrative approval and
technical sanction from competent authority.
• To work out material schedule.
• If cost exceeds limit, then to take the
• sanction for revised cost.
•
01/28/24 3
PURPOSES (CONTD.)
• To get the funds available to execute the
work.
• To prepare bar chart based upon quantity of
01/28/24 7
•3) FOR RENEWALS AND REPLACEMENT OF ASSETS
CHARGED TO DF AND IF ESTIMATED TO COST Rs.
50,000/-
•4) FOR RENEWAL AND REPLACEMENTS OF ASSET
CHARGED TO REVENUE IF ESTIMATED TO COST UP
TO Rs. 2 LAKH.
•5) FOR RECONDITIONING OF EXISTING ASSETS IF
ESTIMATED TO COST UP TO Rs. 1 LAKH,AND ANY
REPAIR WORK CHARGEABLE TO REVENUE
COSTING UPTO Rs. 5.00 LAKH (c. f. PARA 701)
01/28/24 9
Preparation of Detailed Estimate
not required for
New Minor Work Recondition Renewal Repair works
chargeable to Capital works works (Revenue)
Renewal/Replacement (Revenue)
chargeable to DF,
Up to Rs. 5 Lakhs
OLWR
Up to Rs. 50000 Up to Rs. 1 Up to Rs. 2 Up to Rs. 5
Lakh Lakhs Lakhs
01/28/24 10
TYPES OF ESTIMATES.
• ABSTRACT ESTIMATES.
• DETAILED ESTIMATES.
• SUPPLEMENTARY ESISMATES.
• REVISED ESTIMATES.
• PROJECT ABSTRACT ESTIMATE.
• CONSTRUCTION ESTIMATES.
• COMPLETION ESTIMATES.
01/28/24 11
ABSTRACT ESTIMATE.(E-702)
• To form reasonably accurate idea of the
probable expenditure of any proposal.
• Required for administrative approval.
• to establish necessity, utility and financial
prospects by the CA
• Saves time & expense of preparing
detailed estimates at early stage.
• Cost is calculated based upon past
expenditure incurred in similar type of
structure duly modified for escalation,
and variation in site conditions etc., 01/28/24 12
• Accompanied with brief report and justification.
01/28/24 15
• Necessary for preparing tender & contract
documents.
• Work can only be executed after sanction of
detailed estimate.
• Open line detailed estimate should comprise:-
1 .Statement showing details of estimated
cost.(E 704/E705)
• 2. An outer sheet (E -706) giving the abstract
cost of work, report, Fund Certification &
the allocation.
• Prepared in form E -705 for P. Way. Material.
• Prepared in Form E- 704 for all other works.
01/28/24 16
TECHNICAL SANCTION
• The sanction accorded by CA to the detailed
estimate of a work is known as technical
sanction.
• Before according TS the CA should satisfy
itself that
• The details of the scheme as worked out are
satisfactory.
• The methods proposed for the execution of
the work are adequate; and
• The cost has been estimated from reliable
data and is likely to be reasonably accurate.
01/28/24 17
SUPPLIMENTARY ESTIMATE: (E-707)
• An estimate is prepared for left over items
which ought to have been included in
sanctioned estimate, but has not been so
included or items found later, should be
considered as being a part of estimate. If the
above items cannot met out of contingencies
taken for all the purposes S.E is treated as a
part of the main estimate.
• S.E. isprepared in the same form and the
same degree of details as the main
(detailed) estimate. 01/28/24 18
REVISED ESTIMATE.(E-708)
• If expenditure is likely to be exceeded in
the sanctioned detailed estimate then R.E.
is prepared.
• R.E. is not required if :-
1) estimated cost exceeds up to 20% due to
variation in quantities of items or new
item,
2) estimated cost exceeds up to 100% due
to escalation.
01/28/24 19
• Revised Estimate Should be got
sanctioned by C.A. Who
sanctioned main estimate unless
otherwise financial limits of C.A.
Has been exceeded.
01/28/24 20
• For the estimate within the competency of
local authority, the form in which R.E. is
prepared should be decided by C.A. in case
where there has been no great modification in
the scope of the main estimate, an abstract
dealing with major items with explanation only
to be prepared.
• In all other cases detailed R. E. In the same form
and the same degree of details as the main
estimate.
• Each R. E. Should be accompanied by a
comparative statement showing the excess or
saving under each sub head of account against
latest sanction.
• Reasons for each such variation is explained.
01/28/24 21
PROJECT ABSTRACT ESTIMATE(PARA-709)
01/28/24 22
ABSTRACT COST TO BE ACCOMPANIED BY :-
• 1.An abstract estimate of junction arrangements.
• 2.A narrative report explaining the salient features
and major items of expenditure.
• 3.Detailed estimate on form E- 553 under the
following heads :
• 1132-tunnels,
• 1151 & 1152-major bridges,
• 1153 & 1154-minor bridges,
• 1140-ballast and permanent way (detailed estimate
01/28/24 26
ESTIMATES OF DEPOSIT WORKS
01/28/24 28
ITEMS OF PART ESTIMATES
• Preliminary works including FLS
• Setting up of project offices and organizations
like office accommodation etc.
• Land acquisition
• Formation and Bridge work for whole or part of
the estimate
• Minimum service bldg.in case of new lines
• Minimum residential qtrs.to meet immediate
need of construction staff.
• It should be certified that no work included in
part estimate are likely to become redundant
when estimate for the whole project is prepared
01/28/24 29
01/28/24 30
Summary of Estimates
Open Line Works Construction Remarks
Projects
1. Abstract Estimate 5. Project Abstract For obtaining Administrative approval
Estimate
2. Detailed Estimate 6. Construction For obtaining Technical Sanction
Estimate
3. Supplementary Estimate Prepared both for Open Line Works &
Construction Projects
01/28/24 31
GROUPING OF WORKS
01/28/24 33
VETTING OF ESTIMATES…
• Competency of sanction:
• This should be decided with reference to the
delegation of powers given by railway
board/GM as revised from time to time.
Presently as given in Model SOP.
• Currency of sanction
• the sanction to an estimate will ordinarily
remain current for the given years from the
date on which it has been accorded. If a
specific provision of expenditure on works in
progress is available in sanctioned budget of
the year then it may be regarded as reviving for
that year irrespective of the 5years limit.
01/28/24 35
•
• But if no work has been commenced on a
sanctioned scheme within two year from
the date of sanction, then such sanction
should be treated as lapsed. Fresh
sanction with up to date estimate would
be necessary if it is decided to undertake
the work.
01/28/24 36
ANNEXURE TO ACCOMPANY THE
ESTIMATE
• Top sheet as per form E702
• Estimate as per for E553 & E554
• Checklist for estimate
• Brief history, details of previous sanctions,
latest status, detailed justification of work
• Chartshowing facilities proposed in original
estimates, stage wise approval in further
estimates and now proposed.
01/28/24 37
Contd.
• Check list and certificate regarding rates adopted
• Consolidated comparative statement showing the variation
in cost w.r.t the Abstract cost in case of Detailed
estimate/revised estimate clearly bringing out the variation
due to escalation, variation due to change in quantities and
variations due to new items.
• Technical explanatory note for increase in cost due to new
items and increase in quantities. Should be given.
• Views of associate finance and remarks thereon/
• Above annexures should be signed by an officer not below
the rank of SAG/JAG
• Top sheet and comparative statement should also be signed
by an officer not below the rank of SAG/JAG from the
executive and accounts.
01/28/24 38
01/28/24 39