Professional Documents
Culture Documents
I. Performance Sec
urity
II. Contract Pri
ces
III. Subcontracti
ng
IV. Wa r r a n t i
es
V. Va r i a t i o n O r
der
VI. Liquidated D
amages
2
PERFORMANCE SECURITY
3
FAILURE TO ENTER INTO CONTRACT
AND POST THE PERFORMANCE SECURITY
General Rule:
5
CONTRACT PRICES
Exceptions:
1. Price escalations caused by extraordinary
circumstances duly approved by the GPPB;
2. When a Treaty or International or Executive
Agreement expressly allows;
3. In cases where the cost of the awarded contract is
affected by any applicable new laws, ordinances,
regulations, or other acts of the GOP, promulgated
after the date of bid opening.
6
CONTRACT PRICE ESCALATION
Extraordinary Circumstances
7
CONTRACT PRICE ESCALATION
8
CONTRACT PRICE ESCALATION
1. Fire;
2. War;
3. Pestilence;
F AUILnUusRuaEl fOol FdB; IDDING
4 .
5. Locusts; and
6. Earthquake;
10
SUBCONTRACTING
14
SUBCONTRACTING
15
SUBCONTRACTING
FAILURE OF BIDDING
16
WARRANTIES
FAILaUaffected
s Rh
t Ee by
wOhis
oFrconstruction
ksB, IeDquDpi work;
ImNeGn,t installation and
the like to be
• Defects Liability Period –1 year from project completion up
to issuance of the Certificate of Final Acceptance.
17
WARRANTY PERIOD
FOR INFRA
PROJECTS
Contract Completion Of Certificate Of
Award The Project Acceptance
Performance Security
18
WARRANTIES
Type of Structure
and Warranty Covered Structures
Period
Permanent Buildings of types 4 (steel, iron, concrete, or
Structures: Fifteen masonry construction with walls, ceilings, and
(15) years permanent partitions of incombustible fire
resistance) and 5 (steel, iron, concrete, or
masonry construction), steel and concrete
FAILURE OF BIDDING bridges, flyovers, concrete aircraft movement
areas, ports, dams, diversion tunnels,
causeways, wharves, piers, dikes, filtration and
treatment plants, sewerage systems, power
plants, transmission and communication towers,
railway system, and other similar structures;
19
WARRANTIES
Type of Structure
and Warranty Covered Structures
Period
Semi- Permanent Buildings of types 1 (wooden), 2 (wood with 1
Structures: hour fire resistance), and 3 (masonry and wood
Five (5) years construction), concrete roads, asphalt roads,
river control, drainage, irrigation and drainage
canals, municipal ports and river landing, deep
FAILURE OF BIDDING wells, rock causeway, pedestrian overpass, and
other similar structures
Other Structures: Bailey and wooden bridges, shallow wells,
Two (2) years spring developments, and other similar
structures.(Section 62.2.3.2 of the IRR of R.A.
9184.
20
WARRANTIES
• Structural Defects
— major faults/flaws/deficiencies in one or more key
structural elements of the project which may lead
to structural failure of the completed elements or
structure
• S t ru ct u ra l F ai lu re s
F A LI U R E O F B D
I DING
— where one or more key structural elements in an
infrastructure facility fails or collapses, thereby
rendering the facility or part thereof incapable of
withstanding the design loads, and/or endangering
the safety of the users or the general public
21
WARRANTIES
Amount Of
Forms Of Warranty Effectivity Of The
Warranty
Security Warranty Security
Security
Cash or Letter of Credit Five Percent One (1) year from the
22
WARRANTIES
Amount
Amount Of
Of
Forms
Forms Of
Of Warranty
Warranty Effectivity
Effectivity Of
Of The
The
Warranty
Warranty
Security
Security Warranty Security
Warranty Security
Security
Security
One (1)(1)year
yearfrom thethe
from
Surety bond callable upon date of issuance of the
FAILURE OF BIDD ING
Ten percent
demand issued by GSIS or
(10%) of
Certificate of Final
aBank
surety or insurance
guarantee confirmed Acceptance by the
company
by a duly certified byor
Universal the Total procuring entity, and
the InsuranceBank.
Commercial Commission Contract returned
returned only
only after
after the
the
as authorized to issue such Thirty lapse
Price
percent lapse ofof the
the said
said one
one (1)
(1)
security. year
(30%) year period
period
of the Total
Contract
Price 23
WARRANTIES
Amount Of
Forms Of Warranty Effectivity Of The
Warranty
Security Warranty Security
Security
Variation Order
— refers to any increase/decrease in quantities within
the general scope of the project as bid and awarded,
in any of the following aspects:
1. Introduction of new work items ,or
2. Reclassification of work items that are either due to
FAILUcRhfield
EanOconditions
geFoBf resulting inIdisparity
pDal nDsI,between
NdGesgi n theorpre-
constructiontoplans used for
alignment suitbidding andactual
“as stated
plans” or construction drawings prepared after joint
survey by the contractor and the government after
contract award or during actual construction.
25
VARIATION ORDERS
27
VARIATION ORDERS
28
VARIATION ORDERS
29
VARIATION ORDERS
31
LIQUIDATED DAMAGES
Procuring entity may also take over the contract or award the
same to a qualified supplier through negotiation.
FAILURE OF BIDDING
8. LD will be imposed until such goods or services are finally
delivered or performed and accepted by the procuring entity.
33
PROGRESS PATYMENT
34
SESSION VII
1. Contract Drafting;
Contract administration
— is the process that begins from when the contract is
awarded to when the work is completed and
accepted or the contract terminated; payment has
been made; and disputes have been completely
resolved. It is primary part of the procurement
process that assures the project owner gets a quality
product for what it has bargained and assures that
users are satisfied with the final product.
CONTRACT ADMINISTRATION
• Contract administration concentrates on the relationship
between the department and the supplier from contract
award to contract closeout ensuring the supplier delivers
the product and/or service in conformance with the
purchase document requirements.
1. Time
2. Cost
3. Quality
4. Documentation
43
CONTRACT ADMINISTRATION
1. Time Element
• The task here is to ensure that contract performance is
on schedule.
44
CONTRACT ADMINISTRATION
1. Time Element
45
CONTRACT ADMINISTRATION
1. Time Element
• There is a need to conduct regular meetings with
supplier/contractor to know the following:
1. its contract performance as of reckoning date, and
2. Potential delays, so that preventive measures will be
put in place.
46
CONTRACT ADMINISTRATION
1. Time Element
47
CONTRACT ADMINISTRATION
2. Cost Element
• Unnecessary additional or extra quantities or works
should be avoided.
48
CONTRACT ADMINISTRATION
2. Cost Element
• The task here is to ensure that contract cost is kept
within budget or agreed amount.
49
CONTRACT ADMINISTRATION
2. Cost Element
• Any request for contract price escalation, if the required
conditions under the law are met, should be considered
and processed in accordance with the prescribed
guidelines and procedures.
50
CONTRACT ADMINISTRATION
3. Quality Element
• The task here is to ensure that the product delivered or
work completed or services rendered are in accordance
with those specified in the contract and internationally
accepted quality standards.
51
CONTRACT ADMINISTRATION
3. Quality Element
• In goods, packaging must be in accordance with
specifications to ensure that they are received in good
condition and free of defects and damages.
52
CONTRACT ADMINISTRATION
3. Quality Element
• In consulting services, consultant must perform the
services and carry out his/her obligations with all due
diligence, efficiency and economy, in accordance with
generally accepted professional standards and
practices.
53
CONTRACT ADMINISTRATION
4. Documentation
• The task here is to ensure that all decisions and actions
taken by the procuring entity during contract execution
are properly supported by documentations.
54
CONTRACT ADMINISTRATION
4. Documentation
• Contract documents are the basis of decision-making
and action taking. Given their importance, they must be
stored in a secure and safe place accessible only to
authorized officials and personnel.
56
ONITORING OF CONTRACT ADMINISTRATION
57
ONITORING OF CONTRACT ADMINISTRATION
General weaknesses of contract administration:
1. Allocation of more time to awarding contracts
rather than administering existing contracts;
2. Unclear roles and responsibilities of the Project
Manager (PM) and his/her team;
3. Excessive backlog in contract closeout and
incurred costs audits;
4. Improperly trained officials performing contract
oversight;
5. Unclear statements of work that hinder
contractor performance, and
6. Inadequate guidance on voucher processing and
contract closeout.
58
ONITORING OF CONTRACT ADMINISTRATION
59
ONITORING OF CONTRACT ADMINISTRATION
60
ONITORING OF CONTRACT ADMINISTRATION
61
NATURE OF CONTRACT
MANAGEMENT AND CONTRACT
CONTRACT
ADMINISTRATION
CONTRACT
MANAGEMENT ADMINISTRATION
Relationship focus Operational focus
Strategic Tactical
Process Development Process Compliance
Longer time frame Short-term/transactional
Holistic View Narrow Focus
Driven by Added Value Driven by key Performance
Indicators
62
CONTACT US AT:
Unit 2506 Raffles Corporate
Center
F. Ortigas Road, Ortigas Center
Pasig City, Philippines 1605
TeleFax: (632)900-6741 to 44
Email address: gppb@gppb.gov.ph
35