Rob Francis
Director, Innovation & Improvement
BARCLAY’S
ARENA
B2 footprint
First phases integration to Barclays Centre
B2
First Modular Residential Building: B2
• Residential building at Atlantic Yards
• Modular construction
• 348,000-square foot (£210/sq.ft)
• 32-story building
• Approximately 363 rental apartments (£201k ea )
•Contract Value: $117 million (£73.125m)
•Preconstruction: Start Date December 2012
•Modular Pre - Production: Start Date July
2013
• Modular program: 32 weeks
•Completion Date: Summer 2014
•LEED Certification: Goal of LEED Silver
PHASE 1 -
PHASE 2 – INTEGRATION PHASE 3 – MEP
MANUFACTURED
OF SUBASSEMBLIES INSTALLATION
MODULAR STEEL FRAME
IN FACTORY
PHASE 4 – MODULE
PHASE 5 – ERECTION &
INTERIOR & EXTERIOR
MATELINE
FINISHES
CONNECTIONS
MODULAR – Union Field
Work
On-Site
MODULE 20%
FIRST FLOOR STEEL ERECTION ERECTION Factor
y
80%
MODULE
MATELINE CONNECTIONS
Typical floor
layout
Multi skilled modular teams
MODULAR – Foundations
MODULAR – Structural Scheme
Hat Truss
Mass damper
Building
Setbacks
Plinth
Basement and
Fo
undation
Structural Scheme:
• Zero concrete above ground
• Progressive collapse compliance
• Zero hot works on site
Interior Design
Bathroom Interiors
On Site installation
On Site Installation
What did we do in 9 months?
• Fit out of the factory infrastructure
• Collaborative partnership
• standardized kits
• Mateline design
• Innovative Developer
• Find a developer