You are on page 1of 5

R2 - Overall Status

Execution

Accomplishments Challenges Opportunities

1. Data 1. Data loads, Build, and System Integration Test 1. Perform System Integration Testing per
a. Dry Run 2 Business data validation is 97% are being worked in parallel. original timeline utilizing the ‘Data Dry Run 2
complete and the final costing Environment’ in parallel with Data Dry Run 3.
load/validation nearing completion. We 2. Due to personal matters one workstream
will consider validation for Mission 2 as lead will be unavailable for 2 weeks. This 2. Travel planned during Dry Run 3/SIT1 to gain
closed due to low impact of remained 3% week’s workload (10/3 – 10/07) will be efficiencies by being on the same
expecting confirmation tomorrow from distributed among other team members. location/time.
the team. Next week (10/10 – 10/14) some data loads
b. Defect completion rate is 89% with 7 may be delayed. 3. Leverage new test manager to create detailed
opened and 71 closed defects. The System Integration Test plan.
Mission 2 defects will be considered 3. Completing the authorizations prior to SIT2
as closed and the remaining 7 defects will prior to the completion of the build phase 4. Onboarding a part time (50%) developer in
be moved to Dry Run 3 because of low and reporting tasks. Athens shortly.
priority.
4. Delayed delivery of the Zebra hand scanners 5. Coordinate the regression tests with Santa
c. Validated that the BODs run can be for Weinstadt and Lainate. Rosa during SIT2, since they have not been
completed in 3 Days. involved in the process thus far.

2. Onboarded new test manager, Ms. Pooja 6. Lessons learned from Dry Run 3: A
Sindwani on 09/26/2022. precaution, plan for a backup of the
production environment prior to the BODS
3. SIT1 Preparations data load into Production so that a restore is
a. Kickoff meeting held on 09/30/2022 possible without data loss to Santa Rosa.
b. Process definitions and schedule for
the first two weeks complete
c. Names of testers has been provided
d. Defect load with dashboard are
prepared.

March 20, 2024 1


Mission 2 -Status

March 20, 2024 2


Mission 3
Objective:
• Verify that planning and lessons learned during Dry Run 2 have brought
data load methodology under control.
• Confirm that test scripts and processes are in line with expectations.
• Obtain business sign-off on processes within SIT1 scope.

Data Dry Run 3 / System Integration Testing (Part 1) Highlights


• Aggressive timeline.
• Gather lessons learned from SIT1 and apply to SIT2.

Downside
• Multiple project activities are being worked in parallel by key
IT/Business project resources.

System Integration Test (Part 1) Timeline (Weeks)


What Who When Duration 12-16 19-23 26-30 03-07 10-14 17-21 24-28 31-04 07-11
Complete SIT1 Test Scripts IT / Business 09/30 Milestone

Prepare Test Environment IT 09/19 – 09/30 10


Perform System Integration Testing IT / Business 10/03 – 11/11 30
Document / Research / Resolve Issues IT / Business 10/03 – 11/11 30

Data Dry Run 3 – Build Completion Timeline (Weeks)


What Who When Duration 12-16 19-23 26-30 03-07 10-14 17-21 24-28 31-04 07-11
LS-400 month-end back-up / Refresh Seneca Falls 09/16 – 09/19 2
LS400 extracts (post copy clean up) Roy 09/19 – 09/23 5
Master Data Load (Item, Cust, Vendor) IT + Teklink + Z 09/22 – 09/30 7
Secondary Master and Transactional Loads IT 10/03 – 10/28 20
Validation Business 10/10 – 11/04 20
Defect Corrections IT 10/10 – 11/04 20
Build Completion IT 09/19 – 11/04 35
Complete Authorizations (SIT Only) IT 09/19 – 11/04 35

IT = Developers and Functional leaders

The only easy day was yesterday


US Navy SEALs
SAP R2 Steering Committee (September 28 th) March 20, 2024 3
Authorization items
Activity Percent
Identify all users 100%
Identify key users for SIT 100%
Map LS/400 roles 80%
Prepare customer transactions See charts
Create / adjust authorization roles See charts
Define role assignment for 33 - 34%
authorization group

Presentation Title goes here. March 20, 2024 4


System Integration Test Preparation Status

Accomplishments:
Held a testing kickoff meeting
with the business

Onboarded the new testing


manager, Pooja Sindwani Next Steps:

Acquired list of testers and Execute the test steps


testing data from the business
Capture the screen shots
Setup and published a testing
Track and priorities defects
schedule for the first 2 weeks
Report the status twice a week
Created a defect log with
dashboard
March 20, 2024 5

You might also like