Execution
1. Data 1. Data loads, Build, and System Integration Test 1. Perform System Integration Testing per
a. Dry Run 2 Business data validation is 97% are being worked in parallel. original timeline utilizing the ‘Data Dry Run 2
complete and the final costing Environment’ in parallel with Data Dry Run 3.
load/validation nearing completion. We 2. Due to personal matters one workstream
will consider validation for Mission 2 as lead will be unavailable for 2 weeks. This 2. Travel planned during Dry Run 3/SIT1 to gain
closed due to low impact of remained 3% week’s workload (10/3 – 10/07) will be efficiencies by being on the same
expecting confirmation tomorrow from distributed among other team members. location/time.
the team. Next week (10/10 – 10/14) some data loads
b. Defect completion rate is 89% with 7 may be delayed. 3. Leverage new test manager to create detailed
opened and 71 closed defects. The System Integration Test plan.
Mission 2 defects will be considered 3. Completing the authorizations prior to SIT2
as closed and the remaining 7 defects will prior to the completion of the build phase 4. Onboarding a part time (50%) developer in
be moved to Dry Run 3 because of low and reporting tasks. Athens shortly.
priority.
4. Delayed delivery of the Zebra hand scanners 5. Coordinate the regression tests with Santa
c. Validated that the BODs run can be for Weinstadt and Lainate. Rosa during SIT2, since they have not been
completed in 3 Days. involved in the process thus far.
2. Onboarded new test manager, Ms. Pooja 6. Lessons learned from Dry Run 3: A
Sindwani on 09/26/2022. precaution, plan for a backup of the
production environment prior to the BODS
3. SIT1 Preparations data load into Production so that a restore is
a. Kickoff meeting held on 09/30/2022 possible without data loss to Santa Rosa.
b. Process definitions and schedule for
the first two weeks complete
c. Names of testers has been provided
d. Defect load with dashboard are
prepared.
Downside
• Multiple project activities are being worked in parallel by key
IT/Business project resources.
Accomplishments:
Held a testing kickoff meeting
with the business