ELECTRO-MECHANICAL WORKS

Description of Works:
Central air conditioning works for 5 Dormitaries, 3 staff
residences, 1 Adminstration building, 1 Cafeteria building,
Toilet ventilation system for adminstration building and an
elevator for adminstration building.
CONSULTANT
CONTRUCTORS

GETAYER ENGINEERING PLC ABRHAM MENGISTU


ELECTRO-MECHANICAL WORKS
4 DORMITORIES, 1 STAFF RESIDENCE &
1 ADMINSTRATION BUILDING.

ULTIMATE ENGINEERING PLC


1 DORMITORY, 2 STAFF RESIDENCES &
1 CAFETERIA BUILDING.
ABRHAM MENGISTU ELECTRO-MECHANICAL WORKS
IMPOPRTANT PROJECT DATA

 DATE OF CONTRACT SIGNING: MARCH 29, 2022


 DATE OF SITE HANDOVER: MAY 22, 2022
 CONTRACT PERIOD: 365 DAYS
 CONTRACT COMPLETION DATE: MARCH 29, 2023
 INITIAL CONTRACT AMOUNT: 335,673,538.44 ETB
 ADVANCE PAYMENT CERTIFIED TO DATE: 106,702,061.53
 PAYMENT CERTIFIED TO DATE: 48,481,703.87
 VALUE OF ITEMS TO BE IMPORTED: 123,000,000 estimate
 VALUE OF WORK EXCUTED AND MATERIAL ON SITE TO DATE: 107,247,540
 PROJECT PROGRESS IN PERCENTAGE
(FINANCIAL COLLECTED WITH RESPECT TO TOTAL PROJECT COST): 30%
 PAYMENT UTILIZATION IN PERCENTAGE
(WITH RESPECT TO COLLECTED PAYMENTS): 69%
ULTIMATE ENGINEERING PLC
IMPOPRTANT PROJECT DATA

 DATE OF CONTRACT SIGNING: MARCH 29, 2022


 DATE OF SITE HANDOVER: MAY 22, 2022
 CONTRACT PERIOD: 365 DAYS
 CONTRACT COMPLETION DATE: MARCH 29, 2023
 INITIAL CONTRACT AMOUNT: 83,674,026.12 ETB
 ADVANCE PAYMENT CERTIFIED TO DATE: 24,218,969.97 (Unpaid 883,237.86)
 PAYMENT CERTIFIED TO DATE: 11,551,931.105
 VALUE OF ITEMS TO BE IMPORTED: 23,000,000 estimate
 VALUE OF WORK EXCUTED AND MATERIAL ON SITE TO DATE: 17,254,123
 PROJECT PROGRESS IN PERCENTAGE
(FINANCIAL COLLECTED WITH RESPECT TO TOTAL PROJECT COST): 20.5%
 PAYMENT UTILIZATION IN PERCENTAGE
(WITH RESPECT TO COLLECTED PAYMENTS): 68%
PROBLEMS FACED

1. Some buildings are not ready for the proper execution of electromechanical works
2. Payment delay
3. National wide foreign currency shortage
4. Frequent work distraction due to different governmental activities in the compound,
i.e. national examination and Conflict
PROJECT

BUILDINGS