steps:
Remove 1. First, confirm whether the rack placement position and the bed panel are
this

fixed block the horizontal. If not, adjust them to the horizontal state through the gasket .

2. Remove the longitudinal and transverse fixing blocks and screws from the
bed, as picture 1,2,5.

3. Remove this fixed block on the slideway, as picture 3.


Picture3 Remove this Remove this fixed
fixed block on Picture 4
block of the bucky
the slideway
4. Remove this fixed block of the bucky, as picture 4.

Picture 5

Remove the lateral fixing


拟制 审核
screw from the bed
Picture1 Take it out and put it in order
Picture 2

Steps:
1. Take out the column, chest film rack, film box, and put them in order, as
picture 1.

2. Need 3 people to put the column up, one person will keep the column
Use the M10*22 screws ,
fix the column
Stand the chest
base and block base alignment, with the M10*22 screws to fixe the
on the block base.
radiography frame Picture 4 column on the block base, as picture 3.
Picture 3 up and place it in the

designated position
3. Need 3 people lift the chest film column to the base, that was placed in
the designated position, and put it up, as picture 4.
Picture1 Picture2
Steps :

1. Adjust the ball tube arm to proper mounting height.

2. Remove 4 screws , to remove the loop, as picture 1,2.


Remove 4 screws ,
to remove the loop
3. Place the tube in the hoop and install the screw.
Note: when installing the tube, the high voltage cable connector
Picture3
Make sure the tube is of the tube should face to the column.
in a horizontal position and

tighten the screws.


4. Make sure the tube is in horizontal position and tighten
Place the tube in the the screws.
hoop and install the screw
Picture1 Picture 2 Picture 3
Steps:

1. Remover the metal cover of the collimator. Loosen the sheet metal
screws of the two side buckles and push them outward to remove the
mounting plate, as the picture 1,2.
Remover the metal of
Loosen the sheet metal
the collimator
screws of the two side

Installing plate, gasket and buckles and push them


Hang the sheet metal on 2. Installing plate, gasket and the cow head are fixed at the bottom of
the cow head are fixed at the outward to remove the

bottom of the ball tube mounting plate


both sides of the
the tube.
collimator on the
Picture 4 mounting plate and lock
Picture 5 the screws tightly 3. Hang the sheet metal on both sides of the collimator on the mounting
plate and lock the screws tightly.

Tighten
picture6
this screws

:
3.5 meters

Consist of: High-voltage cable, Rotator cable, Collimator power cable,


Serial cable,
screen signal bus,
Angle identification cable.
Picture 1 Picture 2

Put the cable Picture 4


Remove another inside
loop

Serial cable

screen signal bus

Picture 3
Angle identification cable

Two high-voltage cables and one rotator cable


pass through the left and right slots of the tube
cover

Tighten the screws


Picture1 Picture 2

Steps:
1. Connect the Angle identification cable to the touch switch, as
Connect the Angle
identification cable picture 1,2.
to the touch switch

2. Connect the collimator power cable, as picture 2.


Connect the collimator
power cable
3. Fasten high voltage cable and rotator cable by the metal, as
picture 4.
Picture 3 Picture 4 4. Put some silicon to the high voltage cable , and connect the
Fasten this cables by the
high voltage cable to the tube.
metal

Connect the high

voltage cable to

the tube
Pull out the electromagnet wire
Picture 1 Picture 2 of tube rotate. And connect this
two wires together.

Steps :
1. Insure the cable length from the tube housing to the tube
Insure this arm is: 65cm, as picture1.
length is : 65cm

2. Pull out the electromagnet wire of tube rotate. And connect


these two cables together, as picture 2.

Picture 3 Picture 4
3. The cable direction is depends on the chest radiograph
stand placed left or right, follow the chest radiograph stand
opposite direction, as picture 4.

This direction is depends on

the chest radiograph stand placed left

or right, opposite direction


Picture 1 Picture 2

Fixe this big cable Steps :


by the loop 1. Ordering and fixe the cables by cable tie, as the picture 1.
Motor, encoder and
Fixe the cables

by cable tie
pulley magnet cable
2. Motor, encoder and pulley magnet cables are wired from the
are wired from here ,

and fix them by ribbon


marked position, and fix them by cable tie, as picture 2.

All the cables

go through this Picture 4 Picture 5 3. First, the encoder wire is threaded through the slot at the bottom
Picture 3 port
of the counterweight sealing plate, and lock the plate, then lock the
motor and encoder cable into the wire slot and lock the wire slot, as
picture 4,5.

Install the metal on


Note: After wiring, rotate the column to make sure that the reserved
here to fixe the cable length of the cable is sufficient and no cable is dragged.
This connector is
Picture 1 reserved for the mobile Picture 2
controller and no need to

connect for standard Connect the tube lifting


configuration machine potentiometer ‘s cable Steps :
1. Connect the controller cable of chest radiography frame, the
Connect the tube lifting tube lifting potentiometer cable and the tube lifting motor cable and
Motor’s cable
the electromagnet cable of bed, as picture 1,2,3.
Connect the Controller’s line

of chest radiography frame 2. Use a 50cm winding pipe to wind up the cables of tube lifting
Picture 3 motor and potentiometer, as picture 4.
Connect
Picture 4

the

electromagnet
Paste a cable clip at 3. Paste a cable clip at this position to fix the cables of tube lifting
line of bed
this position to fix
motor and potentiometer, as picture 4.
the cables of tube

lifting motor and


Use a winding
potentiometer
pipe to wind up
The metal
the cable
inside to

fix
the
Picture 1 Picture 2
Remove the

retaining block Steps :


screw
Adjust bucky mounting 1. Remove the retaining block screw of the chest radiography
block to proper height.
frame, as picture 1.

2. Adjust bucky mounting block to proper height, as Picture 2.

3. First remove the bucky shell, and then fix the Bucky on the
mounting block with hexangular set screws, as picture 3.
Picture 3 Picture 4
First remove the bucky

shell, and then fix the Note: Before install the bucky, confirm the chest radiography
Bucky on the mounting
chest radiography frame
frame direction, According to the actual situation, bucky
block with hexangular

set screws has different direction. detector's socket should always be facing the operating table.
According to the actual
situation, bucky detector's
socket should always be
facing the operating table
Picture 1 Picture 2

Steps :
Put the bucky's shell

on and lock the screw


1. Loosen the filter grid fixed block, put it into the filter grid, and
confirm the position is centered, then lock the fixed block.
Note: There are positioning reference holes around the chest
installation frame.

2. After finish put into the filter grid, Put the bucky's shell on and
Loosen the filter grid fixed
lock the screw.
block, put into the filter grid,

and confirm the position is

centered, then lock the fixed Requirements:


block.
Make sure the filter grid’s cross curve, detector’s cross
Note: There are positioning

reference holes around the


curve, and the bucky housing’s cross wire are all aligned.
chest installation frame
Steps :
Lock the counterweight

sealing plate, then lock the

Picture 1 electromagnet and encoder Picture 2 1. Lock the counterweight sealing plate, then lock the electromagnet and
cables into the cable slot, and
encoder cables into the cable slot, and lock the screw, as picture 1.
lock the screw

2. Fix the electromagnet cable to the slot with the cable clip, as picture 2.
Tied up the electromagnet

wire to the slot with the

cable tie
3. Connect the chest radiography frame’s lifting motor’s cable, and the
Connect the chest
Connect the Picture3 chest radiography frame’s lifting electromagnet’s cable, and the chest
radiography frame’s
chest radiography frame’s lifting potentiometer’s cable, as the picture 1.
lifting motor’s cables
radiography frame’s
cables
lifting electromagnet’s
4. Connect the controller cable of the Bucky, as picture 3.
Controller cable

connection
Connect the
Requirments:
chest
potentiometer’s cable
radiography frame’s
1. The cable should be straightened and neat.
lifting
2. Ensure that all cable terminals are inserted in place.
Picture 1

Steps :
1. Remove the sealing plate and limit block on one side of
Remove the sealing plate and limit

block on one side of the bed and


the bed and pull the bed panel out, as picture 1.
pull the bed panel out.

2. Loosen the filter grid fixed block, put into the filter grid,
and confirm the position is centered, then lock the fixed
block, as picture 2,3.
Picture 2 Loosen the filter grid fixed block,
put into the filter grid, and confirm
Filter grids’ positioning Note: There are positioning reference holes around the
the position is centered, then lock
the fixed block.
reference holes
chest installation frame.
Note: There are positioning
reference holes around the chest
Picture 3
Requirments:
installation frame
1. Ensure that the filter grid and the detector are aligned.
Picture1

Steps :
1. Ensure the filter grid is installed completed,
put the bed panel back, and install back the
sealing plate and limit block.

Picture 2 Picture 3

Requirments:
Low High Ensure the filter grid is installed
position Position
aging test
completed, put the bed panel back,
1. During the process of disassembly and assembly,
and install back the sealing plate and pay attention to protect the bed board to prevent
limit block
collision.
Auto tracing mode calibrate steps:

Towards the tube to bucky Stand, move the tube to lowest Position, and move the bucky stand to same level,
long press “low position” button for 3 seconds.
Auto tracing mode calibrate steps:

Move the tube to highest Position, and move the bucky stand to same level,
long press “high position” button for 3 seconds.
Picture1
Using the Ribbon to
tied up the cables in
here
Wrap the High voltage Steps :
10cm cable 、
screen serial cable 、
1. Tie up the cables, as picture 1.
collimator cable with
bucket-type end straps

2. Wrap the High voltage cable, screen serial cable,


Picture 2
Picture 3 collimator cable with wrapping band, as picture 2.

3. Wrap all the cables that come out from the bed, chest
radioghy frame, and put them all in order.

10cm
Wrap the cables
with
wrapping band