Professional Documents
Culture Documents
Dr A P Dash
Professor, NTPC School of Business
PROJECT COST ESTIMATION STAGES
IMPORTANT MILESTONES
• Feasibility Stage
• Procurement Stage
• Implementation Stage
• Completion stage
PREPARATION OF FEASIBILITY
REPORT COST ESTIMATE
PURPOSE OF A COST ESTIMATE – FR
STAGE
(CONTD...)
PREPARATION OF FEASIBILITY REPORTS
FOR WORKING OUT PLANT & EQUIPMENT
COST, FOLLOWING CENTAGES ARE
NORMALLY FOLLOWED IN RESPECT OF
FREIGHT & INSURANCE(F&I), ERECTION &
SPARES
F&I : 4% of Equipment
Erection : 10% Equipment price
Spares : As per actuals
(CONTD...)
Case : NTPC
CERC NORMS FOR SPARES
(CONTD...)
PREPARATION OF FEASIBILITY REPORTS
• BASIS FOR CALCULATION OF
INTEREST DURING
CONSTRUCTION(IDC) & FINANCING
CHARGES
IDC IS DEPENDENT UPON VARIOUS
FACTORS SUCH AS :
» DEBT : EQUITY RATIO
» TYPE OF DEBT - EXTERNAL COMMERCIAL
BORROWINGS(ECB) / DOMESTIC
COMMERCIAL BORROWINGS(DCB)
(CONTD...)
TYPICAL EXAMPLE FOR WORKING OUT IDC
• ESTIMATED COST : Rs. 100 Crores
• DEBT : EQUITY RATIO : 70 : 30
• TIME SCHEDULE : 4 YEARS
• PHASING OF EXPENSES
» Ist Year : Rs. 20 Crores
» IInd Year : Rs. 30 Crores
» IIIrd Year : Rs. 30 Crores
» IVth Year : Rs. 20 Crores
(CONTD...)
TYPICAL EXAMPLE FOR WORKING OUT IDC
• SINCE EXPENDITURE WILL BE OCCURING
THROUGHOUT THE YEAR, IT WILL BE ASSUMED
AT A MIDPOINT FOR WORKING OUT THE
INTEREST ON LOAN COMPONENT. THEREFORE,
THE INTEREST COMPONENT DURING
CONSTRUCTION WILL BE AS FOLLOWS
» Ist Year : Interest component for the loan
drawn during first year for 6 months(mid
point)
» IInd Year : Interest component for the loan drawn
during first year(i.e opening balance
for IInd Year) for full one year +
Interest component for the loan for
second year for 6 months(mid point)
(CONTD...)
TYPICAL EXAMPLE FOR WORKING OUT IDC
(CONTD...)
TYPICAL EXAMPLE FOR WORKING OUT IDC
• ACCORDINGLY, INTEREST DURING
CONSTRUCTION COMPONENT WORKS OUT TO
BE :
» Ist Year : Rs. 0.7 Crs.(Rs. 14 Cr.x0.1x0.5)
» IInd Year : Rs. 2.45 Crs.( Rs. 14 Cr.x 0.1+Rs.
21 Cr.x0.1x0.5)
» IIIrd Year : Rs. 4.55 Crs.(Rs. 35 Cr.x 0.1+Rs.
21 Cr.x0.1x0.5)
» IVth Year : Rs. 6.3 Crs.(Rs. 56 Cr.x0.1+Rs.
14 Cr.x0.1x0.5)
TOTAL : Rs. 14.0 Crs.
TYPICAL EXAMPLE OF COMPONENTS
OF PROJECT COST (MEGA)
WCM
IDC Civil
Overheads 2%
14% 18%
4% Civil
Plant & Equipment
Taxes & Duties
Taxes & Duties
1% Overheads
IDC
WCM
Plant &
Equipment
61%
Thank you