Professional Documents
Culture Documents
3
Introduction
4
Introduction
Factors favoring the use of manual assembly lines include the
following:
Demand for the product is high or medium
The products made on the line are identical or similar
The total work required to assemble the product can be
divided into small work elements
It is technologically impossible or economically infeasible to
automate the assembly operations.
5
Fundamentals of Manual Assembly Lines
6
Assembly Workstations
7
1.2 Work Transport Systems
8
1.2 Work Transport Systems
Three major categories of work transport systems in production
lines are:
(a) continuous transport
(b) synchronous transport
(c) asynchronous transport
9
1.2 Work Transport Systems
10
1.2 Work Transport Systems
11
1.2 Work Transport Systems
12
1.3 Line Pacing
(3) no pacing
Reference: Faccio, M., Gamberi, M., & Bortolini, M. (2016). Hierarchical approach for paced mixed-
model assembly line balancing and sequencing with jolly operators. International journal of
production research, 54(3), 761-777. 13
1.4 Coping with Product Variety
where
Rp = average hourly production rate, units/hr
Da = annual demand for the single product to be made on the
line, units/yr
Sw = number of shifts/workers
Hsh = hours per shift, hr/shift
15
2. Analysis of Single-Model Assembly Lines
2.1(Cycle Time and Workload Analysis)
The cycle time must take into account the reality that some
production time will be lost due to occasional equipment failures,
power outages, etc.
where
E =line efficiency;
Rp = required production rate
where
w = number of workers on the line
WL = workload to be accomplished in a given time period, min/hr
AT = available time per worker during the period, min/hr/worker
16
Example
A small electrical appliance is to be produced on a single-model
assembly line. The work content of assembling the product has
been reduced to the work elements listed in Table 4 The table
also lists the times for each element and the precedence order
in which they must be performed. The line is to be balanced for
an annual demand of 100,000 units/yr. The line will operate 50
wk/yr, 5 shifts/wk, and 7.5 hr/shift. There will be one worker per
station. Previous experience suggests that the uptime efficiency
for the line will be 96%, and repositioning time lost per cycle will
be 0.08 min.
Determine
(a) total work content time Twc,
(b) required hourly production rate Rp to achieve the annual
demand,
(c) cycle time Tc,
17
Example
18
Answer
19
2.2 Repositioning losses
Repositioning time
21
2.3 The Line Balancing Problem
Problem
To assign the individual work elements to workstations so that all
workers have an equal amount of work to perform
It is not possible to divide work content time evenly among workers.
Precedence constraint
Variation in work element times.
Restriction on the sequence of work elements can be performed.
Some elements must be done before others.
Precedence constraints can be presented graphically in precedence
diagram. 22
2.3 The Line Balancing Problem
23
2.3 The Line Balancing Problem
24
Example
25
Precedence Diagram
0.11
6
: Work elements
0.2 3 7 9
1
0.1 0.6 0.5 0.12
0.4 4 8 11 12
0.38
2
0.3 10
5
26
3. Line Balancing Algorithms
28
3. Line Balancing Algorithms
29
1. Largest Candidate Rule
b.
Balance delay, d
Smoothness index, SI
where,
Twc : work content time per product [min/unit]
w : number of worker
Ts : max. available service on the line [min/cycle]
Tsi : service time at station i
n : number of station in the line
36
Evaluation of Line Balancing
Compute the balance delay for the previous example
Station 3
0.2 Line balance efficiency:
Station 1 4 0.4 Twc 4.3
7
Eb 0.86
wTs 5(1.0)
0.3
2 5 Balance delay, d = 1 – Eb = 0.14 = 14%
0.5 Station 4
0.1
1 Smoothness index:
0.3 = (0 0.01 0 0.04 0.16 )
3 8 9 Station 5
= 0.21
0.8 0.6 0.5 0.6
Station 2 6 10 = 0.458
This overcomes one of the difficulties with the largest candidate rule in
which an element may be selected because of a high Te value but
irrespective of its position in the precedence diagram.
38
Example- Kilbridge and Wester Method
First we should draw the precedence diagram. It will help us to easily follow
the correct sequence of work elements while designing the workstations:
I II III IV V VI
2 7
1 9
5
3 8
10
6
40
Example- Kilbridge and Wester Method
Due to the existed precedencies, it seems that activities 3 and 6 have free
float and can be forwarded:
I II III IV V VI I II III IV V VI
4 4
2 7 2 7
1 9 1 9
5 5
3 8 3 3 8
10 10
6 6 6 6
41
Example- Kilbridge and Wester Method
Now start from the first column and write work elements to form work stations until the
maximum service time allows. At each stage follow the largest candidate rule. If a work
element can be placed in more than one column, write all possible columns for it.
Work Tek Preceded
I II III IV V VI element Column by
(min)
0.2 1 I 0.5 -
0.3 4 0.4 3 II,III 0.8 1
2 7
2 II 0.3 1
0.5 0.1 0.3 6 III,IV,V 0.6 3
1
5 9 4 III 0.2 2
0.8 0.5 5 III 0.1 2
3 3 8 0.6 8 IV 0.5 3,5
0.6 10 7 IV 0.4 4,5
6 6 6
9 V 0.3 7,8
10 VI 0.6 6,9
42
Example-
Station Work element Column Tek (min)
Kilbridge and Wester Method
1 1 I 0.5
2 II 0.3
Work Tek Preceded 4 III 0.2
element Column by 2 3 III 0.8
(min) 5 III 0.1
1 I 0.5 - 3 6 III 0.6
3 II,III 0.8 1 7 IV 0.4
4 8 IV 0.5
2 II 0.3 1 9 V 0.3
6 III,IV,V 0.6 3 5 10 VI 0.6
4 III 0.2 2
5 III 0.1 2 I II III IV V VI
8 IV 0.5 3,5 0.2
7 IV 0.4 4,5
0.3 4 0.4
9 V 0.3 7,8
10 VI 0.6 6,9 2 7
0.5 0.1 0.3
1 5 9
0.8 0.5
3 3 8 0.6
0.6 10
6 6 6
43
Example- Kilbridge and Wester Method
Station Work element Column Tek (min) Station time Line balance efficiency:
1 1 I 0.5 Twc 4.3
2 II 0.3
Eb 0.86
wTs 5(1.0)
4 III 0.2 1.0
2 3 III 0.8
Balance delay, d = 1 – Eb = 0.14 = 14%
5 III 0.1 0.9
Smoothness index:
3 6 III 0.6
7 IV 0.4 1.0 = (0 0.01 0 0.04 0.16 )
4 8 IV 0.5 0.21
=
9 V 0.3 0.8
5 10 VI 0.6 0.6
= 0.458
44
3. Ranked Positional Weights Method
45
Example- Ranked Positional Weights Method
46
Example- Ranked Positional Weights Method
Elements ranked according to RPW
0.2
Work Tek (min)
4 0.4 RPW Predecessor
element
7 1 4.3 0.5 -
0.3
2 5 3 2.8 0.8 1
0.5
0.1 2 2.4 0.3 1
1
0.3 5 1.9 0.1 2
3 8 9 4 1.5 0.2 2
0.8 0.5 8 1.4 0.5 3,5
6 10 7 1.3 0.4 4,5
0.6 0.6 6 1.2 0.6 3
9 0.9 0.3 7,8
Quick example:
10 0.6 0.6 6,9
RWP7= 0.4+0.3+0.6 = 1.3
RWP2= 0.3+(0.2+0.1)+(0.4+0.5)+0.3+0.6 = 1.3 Ts = 1.0 min
47
Example- Ranked Positional Weights Method
Station Work element Tek (min) Station time Line balance efficiency:
1 1 0.5 Twc 4.3
2 0.3 Eb 0.86
wTs 5(1.0)
5 0.1 0.9
2 3 0.8
Balance delay, d = 1 – Eb = 0.14 = 14%
4 0.2 1.0
Smoothness index:
3 8 0.5
7 0.4 0.9 = (0.01 0 0.01 0.01 0.16 )
4 6 0.6
= 0.19
9 0.3 0.9
5 10 0.6 0.6 = 0.435