Professional Documents
Culture Documents
Chapter 2
Chapter 2
Project planning
A M L
B M M
C L L
D H H
Step 4: Prevent or Mitigate the Risk: Some risks can be prevented; others
can only be mitigated. Earthquakes or the retirement of an important
stakeholder, for instance, cannot be prevented.
- Proactivity is the project manager’s best friend. Kill the risk before it has a
chance to grow and flourish, and you won’t have to deal with it again.
Step 5: Consider Contingencies: Contingencies represent the specific
actions that will be taken if the risk occurs. Here, you answer the
question “If the risk becomes reality, what will we do”?
Step 6: Establish the Trigger Point: trigger point is the point at which the
risk becomes enough of a reality that the project manager needs to
trigger the contingency.
- It is a judgment call meant to maximize the value of the predetermined
contingency by implementing it at the optimal time.
- Trigger too soon and you will probably spend time, effort, or money for
no good reason.
- Trigger too late and you may end up experiencing the full impact of the
occurrence
- The trigger should be a specific point in time or a defined range of time.
Establishing Reserves: The most comprehensive risk plan can
be compromised if you realize that you do not have the time or
means to take appropriate action.
- Establishing reserves enables you to leverage the plan to its
fullest potential.
- The best-laid plans are impotent without the time and/or
budget to allow for effective implementation. As a result, you
need to establish contingency and management reserves.
- Contingency reserves are designated amounts of time and/or
budget to account for risks to the project that have been
identified and actively accepted.
- They are created to cover known risks to the project.
- Management reserves are created to cover unknown risks to
the project.
Managing Multiproject Risks
- In the multiproject world, many projects overlap or experience direct
dependencies with other projects.
- Two perspectives are required here.
1. First, you must focus on the individual project and the associated
risks for each. Then, you must assess your entire portfolio and
determine the nature of the relationship of these projects. Your
portfolio is the sum of all projects under your purview.
2. A program typically involves multiple projects working toward the
completion of a single deliverable. In the portfolio environment, you
must identify where the projects coincide or overlap with regard to
any project work. You then determine what might go wrong in these
areas where the projects “touch.”
Coordination Points: the areas where the projects touch are called
coordination points.
Risk Matrix: A useful tool when managing many risks across projects
is the standard risk matrix as shown in the figure below.
PROBABLITY
IMP LOW MEDIUM HIGH
ACT
HIGH
MEDIUM
LOW
Project Estimating
Other non-
project factor
Project duration
Quality of
estimates
Organization
structure
people
Padding estimates
Figure
2.
The Critical Path Method
- The most widely used scheduling technique is the critical path
method (CPM) for scheduling.
- This method calculates the minimum completion time for a
project along with the possible start and finish times for the
project activities.
- The critical path itself represents the set or sequence of activities
which will take the longest time to complete.
- The duration of the critical path is the sum of the activities'
durations along the path.
- Thus, the critical path can be defined as the longest possible path
through the "network" of project activities.
- The duration of the critical path represents the minimum time
required to complete a project.
- Any delays along the critical path would imply that additional
time would be required to complete the project.
- The CPM is a systematic scheduling method for a project network and
involves four main steps:
• A forward path to determine activities early start times;
• A backward path to determine activities late finish times;
• Float calculations; and
• Identifying critical activities.
Activity-On-Arrow Networks Calculations
- The objective of arrow network analysis is to compute for each event
in the network its early and late timings.
- These times are defined as: Early event time (ET) is the earliest time
at which an event can occur. Late event time (LT) is the latest time at
which an event can occur if the project is to be completed on schedule
Forward Path: -The forward path determines the early-start times of
activities. The forward path proceeds from the most left node in the
network and moves to the right, putting the calculations inside the
shaded boxes to the left.
Figure : Forward path calculations in AOA networks
Backward Path : -The backward path determines the late-finish
(LF) times of activities by proceeding backward from the end
node to the starting node of the AOA network.
- We put the LF values in the right side boxes adjacent to the
nodes, as shown in Figure below. For the example at hand, we
do the following: