You are on page 1of 24

What is the Project?

A temporary endeavor undertaken to create a unique product or service

What is the Project Management?

Project Management is the sum of all activities such as Planning, organising, implementing and controlling a project in order to meet the clients expectation from start to finish within the planned period, budget and quality.

Who is the project Manager?

A project manager is a professional in the field of project management. Project managers can have the responsibility of the planning, execution, and closing of any project.

Management Functions

Planning Organizing
Leading Controlling

Management Skills

Conceptual Skills Human Skills Technical Skills

Our Graduation Project

Project Overview
Project title : Hyatt Nablus Recreation Center

Project Title:

Multiple Service Building


Location:

Bita Village South Nablus

This Project consists of main

building and external yards with retaining walls on the land with total area of 4 dunums.

The main building is consisting of three floors with total area 1400 meter square.

Assumptions
Working days are all days except

Friday
The electrical and mechanical

works will be done by sub contractors.


Fixing the value

of Euro with (1Euro =5.0 NIS).

Construction Method

The structural method that used is : finishing the structural part for the floor and then starting on the above floor structural work , and in the same time starting with finishing works for the previous

Work Breakdown Structure

Bill of Quantity Preparation Calculations were depending on Drawings to find the quantities and tabulating it. made

Activity List
The activity list entered

in the (Primavera) program and its dependency also were managed on this program.
The dependency of the

activities were constructed according to our method of construction.

Activities Durations

The activity duration depends on the productivity of labors and machines.

[Duration = quantity budgeted for activity \ productivity]. At this project the productivity taken from site engineers and contractors.

Pricing

The costing process based upon past experience for the contractor. The pricing for each element of unit was different from each other, some units were priced according to the area, others were priced according to the number of units.

Results

Cost Results

Total cost of project calculated using Primavera project is (386,622.5) The profit percentage is 10% (since project like this depend on labor so the risk is high)

The over head percentage is 5%


The actual cost of project was

Duration Results

The total duration of the project as planed in this case study is 325 working days.
actual work in the project was 365 working days.

Some reasons of the difference of the time and cost

Material procurement Problems of finance for the project Political reasons Winter weather (rainy days)

S-Curve
cost control of this project made

By using (S-Curve), by comparing the actual cost with the plan cost of the project.
For this project the S-Curve is

done by plotting cumulative cost with time as shown.

Weather Risks
Average rainy days of the last

three years from msn weather data (for Nablus city),and depending on this calculation is done.
35 working days (40 calendar

days) added to the end of project depending on rainy days and the beginning and finishing of the activities affected by rainfall.

Thank You!

You might also like